Method for joint sealing with lead-based molten material

Method for joint sealing with lead-based molten material
IPC classes for russian patent Method for joint sealing with lead-based molten material (RU 2284400):
E04G23/02 - Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
Another patents in same IPC classes:
Method to recover water permeability and waterproof coating of building structures / 2283405
Method involves determining brittle temperature of organic binding agent; calculating plastic range thereof; heating organic binding covering with heating member laid on the covering and compacting the covering. The organic binding agent is heated up to temperature 1.6-3.2 times greater than plastic range.
Building structure water-tightness and waterproof covering recovery method / 2282007
Method involves arranging roof paper between coating area to be repaired and movable heating member; heating organic binding material to soften thereof by means of the heating member; compacting the coating along with rolling-on roofing paper to heated coating.
Building structure reinforcement method Building structure reinforcement method / 2277620
Method involves installing reinforcing members on structure to be reinforced and connecting the members with fastening members; welding the fastening members to one reinforcing member; heating thereof and welding the heated members to opposite reinforcing member; terminating the heating operation. The fastening members may be installed between reinforcing member surfaces or laid on ends thereof. In the first case initial fastening member length is determined from the following equation: L=SBH-α·(T-Ta), where SBH is distance between inner reinforcing member surfaces, α is linear expansion factor of fastening member material, T is fastening member heating temperature, Ta is ambient temperature. In the second case fastening member length is defined as L≥So, where So is distance between outer surfaces of reinforcing members.
Reinforcement method for reinforced concrete pillar with decreased load-bearing capacity Reinforcement method for reinforced concrete pillar with decreased load-bearing capacity / 2274719
Method to recover load-bearing capacity of reinforced concrete column subjected to concrete and reinforcement corrosion by column surface moistening, scoring, column cross-section widening, enclosing with ferrule and reduction of longitudinal compressing force application eccentricity involves deforming steel pipe; reducing steel pipe cross-section by compressing thereof with two rollers to impart oval cross-section to the pipe so that major oval axis is equal to three minor axes; cutting the pipe in longitudinal direction; inserting damaged column in steel ferrule so that major cross-sectional axis is directed in plane of compressing force application eccentricity and reducing eccentricity; connecting two halves of oval pipe in air-tight manner and filling gaps between steel ferrule and damaged column with expanding fine concrete injected through nozzles in the cavities in bottom-top direction; compacting concrete with vibratory action and applying stress to cross-section during concrete setting by compressing thereof from all sides by steel form to reinforce the whole structure.
Method for building reconstruction and raising Method for building reconstruction and raising / 2265705
Method involves forming main drilled piles along building foundation perimeter, where the piles are arranged outside the foundation; mounting the main load-bearing supports on the drilled piles so that load-bearing supports are arranged in pairs from opposite sides of the building; mounting load-bearing girders on load-bearing vertical support heads, wherein the bearing girders are arranged in rows; erecting additional stories on the bearing girders. Main drilled piles extend for depth not less than building foundation depth in ground. Upper pile parts are pulled together in pairs. Additional drilled piles adapted to support additional load-bearing vertical supports are driven outside the building foundation beyond the main ones. At least one additional load-bearing support is arranged in the main vertical support row from one building side.
Method for elimination of bitumen roll roofing material separation / 2260098
Method involves injecting material forming liquid bitumen layer in roof area of separation through orifices arranged in waterproofing mat above the area; consolidating the area to be repaired. Orifices are spaced 0.2-2.0 m apart. At the beginning of material injection process air or water is removed from the cavities through above orifices and then emulsified bitumen, including 30-80% of bitumen, is fed. Emulsified bitumen is spread in cavity over the full area of separation using weight, which is moved over the roof surface. Before compaction the area of separation is heated up to 100-160°C and then held at this temperature up to bitumen dewatering and water vapor discharge from the area through above orifices in atmosphere.
Reinforcing structure for bendable reinforced concrete members Reinforcing structure for bendable reinforced concrete members / 2250325
Structure includes trussed tie bar and additional compressed member. Structure is provided with telescopic post having spring. Post is arranged between trussed tie bar and compressed member formed of channel bar. Compressed member is located in level with lower belt of beam to be reinforced and encloses it. Trussed tie bar ends are connected to compressed member, which in turn is secured to beam to be reinforced by compressed member ends through collars.
Reinforcing structure for bendable reinforced concrete members Reinforcing structure for bendable reinforced concrete members / 2250325
Structure includes trussed tie bar and additional compressed member. Structure is provided with telescopic post having spring. Post is arranged between trussed tie bar and compressed member formed of channel bar. Compressed member is located in level with lower belt of beam to be reinforced and encloses it. Trussed tie bar ends are connected to compressed member, which in turn is secured to beam to be reinforced by compressed member ends through collars.
Method for elimination of bitumen roll roofing material separation / 2260098
Method involves injecting material forming liquid bitumen layer in roof area of separation through orifices arranged in waterproofing mat above the area; consolidating the area to be repaired. Orifices are spaced 0.2-2.0 m apart. At the beginning of material injection process air or water is removed from the cavities through above orifices and then emulsified bitumen, including 30-80% of bitumen, is fed. Emulsified bitumen is spread in cavity over the full area of separation using weight, which is moved over the roof surface. Before compaction the area of separation is heated up to 100-160°C and then held at this temperature up to bitumen dewatering and water vapor discharge from the area through above orifices in atmosphere.
Method for building reconstruction and raising Method for building reconstruction and raising / 2265705
Method involves forming main drilled piles along building foundation perimeter, where the piles are arranged outside the foundation; mounting the main load-bearing supports on the drilled piles so that load-bearing supports are arranged in pairs from opposite sides of the building; mounting load-bearing girders on load-bearing vertical support heads, wherein the bearing girders are arranged in rows; erecting additional stories on the bearing girders. Main drilled piles extend for depth not less than building foundation depth in ground. Upper pile parts are pulled together in pairs. Additional drilled piles adapted to support additional load-bearing vertical supports are driven outside the building foundation beyond the main ones. At least one additional load-bearing support is arranged in the main vertical support row from one building side.
Reinforcement method for reinforced concrete pillar with decreased load-bearing capacity Reinforcement method for reinforced concrete pillar with decreased load-bearing capacity / 2274719
Method to recover load-bearing capacity of reinforced concrete column subjected to concrete and reinforcement corrosion by column surface moistening, scoring, column cross-section widening, enclosing with ferrule and reduction of longitudinal compressing force application eccentricity involves deforming steel pipe; reducing steel pipe cross-section by compressing thereof with two rollers to impart oval cross-section to the pipe so that major oval axis is equal to three minor axes; cutting the pipe in longitudinal direction; inserting damaged column in steel ferrule so that major cross-sectional axis is directed in plane of compressing force application eccentricity and reducing eccentricity; connecting two halves of oval pipe in air-tight manner and filling gaps between steel ferrule and damaged column with expanding fine concrete injected through nozzles in the cavities in bottom-top direction; compacting concrete with vibratory action and applying stress to cross-section during concrete setting by compressing thereof from all sides by steel form to reinforce the whole structure.
Building structure reinforcement method Building structure reinforcement method / 2277620
Method involves installing reinforcing members on structure to be reinforced and connecting the members with fastening members; welding the fastening members to one reinforcing member; heating thereof and welding the heated members to opposite reinforcing member; terminating the heating operation. The fastening members may be installed between reinforcing member surfaces or laid on ends thereof. In the first case initial fastening member length is determined from the following equation: L=SBH-α·(T-Ta), where SBH is distance between inner reinforcing member surfaces, α is linear expansion factor of fastening member material, T is fastening member heating temperature, Ta is ambient temperature. In the second case fastening member length is defined as L≥So, where So is distance between outer surfaces of reinforcing members.
Building structure water-tightness and waterproof covering recovery method / 2282007
Method involves arranging roof paper between coating area to be repaired and movable heating member; heating organic binding material to soften thereof by means of the heating member; compacting the coating along with rolling-on roofing paper to heated coating.
Method to recover water permeability and waterproof coating of building structures / 2283405
Method involves determining brittle temperature of organic binding agent; calculating plastic range thereof; heating organic binding covering with heating member laid on the covering and compacting the covering. The organic binding agent is heated up to temperature 1.6-3.2 times greater than plastic range.
Method for joint sealing with lead-based molten material Method for joint sealing with lead-based molten material / 2284400
Method involves drying joint and filling thereof with dry non-combustible materials before lead-based molten material pouring in joint; filling the joint with lead-based molten material, which is supplied through pouring channel system made of molding material, wherein the molding material provides predetermined geometry of sealed joint. The molten material is supplied as continuous jet. Joint to be sealed may be located in vertical or horizontal planes or in plane inclined at 0-90° angle with respect to horizontal plane. The lead-based molten material may be reused for repairing work performing.
Method and kit to erect inserted structure between two existent buildings Method and kit to erect inserted structure between two existent buildings / 2292434
Method involves erecting foundation of inserted structure, forming through pass in-between and constructing one or several stories over the foundation. The stories are built of kit including vertical panels and floor panels, which are connected with existent building walls by tie members. Joints are hermetically sealed. Floor panels are installed on guiding means having opened parts. Opened parts of guiding means are welded with each other after structure assemblage. Roofs of adjacent buildings are extended up to inserted structure walls. Projection adapted to drain water from the structure is hermetically installed over joint between the roof and the inserted structure. Guiding means are made as outer centralizers in upper parts of vertical and floor panels and as inner centralizers in lower panel parts.
Superstructure skeleton Superstructure skeleton / 2305739
Superstructure skeleton comprises lower row transversal frames arranged within the limits of building length and lower end transversal frames projecting out of the building length and including two belts. The end transversal frames have columns and trusses located from building outside and provided with parallel belts. Arranged in the trusses are upper row and end frames having two belts and including columns and trusses. Skeleton also comprises floor panels. Lower superstructure stories are provided with central columns installed in lower frame truss joints and are united with each other by structural stands of intermediate stories. Space of one intermediate story is free of frame structures. Main beams of upper intermediate stories are secured to upper frame trusses by means of suspension brackets.

FIELD: repairing, for instance filling cracks, restoring, altering, enlarging, particularly for repairing monuments, museum pieces and applied and decorative art pieces.

SUBSTANCE: method involves drying joint and filling thereof with dry non-combustible materials before lead-based molten material pouring in joint; filling the joint with lead-based molten material, which is supplied through pouring channel system made of molding material, wherein the molding material provides predetermined geometry of sealed joint. The molten material is supplied as continuous jet. Joint to be sealed may be located in vertical or horizontal planes or in plane inclined at 0-90° angle with respect to horizontal plane. The lead-based molten material may be reused for repairing work performing.

EFFECT: reduced labor inputs and material consumption, increased environmental safety and joint sealing reliability, elimination of additional mechanical or chemical treatment.

17 cl, 2 dwg

 

The invention relates to the restoration and repair and repair and construction work on the monuments of monumental sculpture and architecture, small sculptural and architectural forms, Museum objects and works of decorative art, namely, to seal the seams on the specified object.

Known method of sealing a seam of pavement rack that includes a thorough cleansing from dust, dirt, oil stains using metal brushes, drawing on each of the joined surface ciocalteau composition, immediately after applying the specified composition docking space between the joined surfaces are filled with mortar based on cement (RU2047703 C1, MPK E 04 1/04, 10.11.1995, example 4) /1/.

Described in /1/ the method adopted for the prototype.

However, the method described in the source /1/, provides a thorough preparation of the surface before sealing, manufacturing Ticonderoga composition should be carried out under strict control, and the resulting composition has a limited shelf life and require special storage conditions. In addition, the materials used in the known method cannot be reused.

The objective of the invention is to develop a low-overhead, materials.because, eco-friendly way to GE the cross seam, enabling a reliable sealing of the seam without additional mechanical or chemical treatment resealable seats, to form a seam configuration on surfaces that form an angle between 0° to 180° with the horizontal plane, sealing it to a predetermined depth.

This object is achieved by a method of sealing a seam melt lead-based, by pouring the melt into the joint through a system of Gating channels, made of molding material.

The sealing seam is carried out to a predetermined depth, for example to a depth of 5-250 mm

If necessary, in particular, when the sealing seam, the depth of which is considerably greater than its width, before pouring the melt seam dried and put in misonoo space dry non-flammable materials to conserve melt lead-based.

The pouring of the melt is carried out through the Gating channels, equipped with Gating bowls.

As the molding material used refractory mass on the basis of kaolin clay.

Form the seam of a given configuration.

It can be convex, concave, having a complex topography.

The seam may be located on the vertical plane.

The seam may be located on a horizontal plane.

The seam may be located on the surface, forming an angle between 0° to 18° with the horizontal plane.

This method allows you to seal narrow joints width 2-5 mm wide seams of a width exceeding 5 mm

The molten lead-based is obtained by loading dry charge lead or alloy-based pre-calcined metal crucible furnace download small portions, providing uniform heating of the charge, then the charge is heated up to 320-350°C.

Pouring molten lead into the seam start from the bottom Gating of the channel.

Pouring molten lead into the seam carried out in a continuous stream.

After solidification of the melt on the basis of lead in the seam if necessary, conduct in the particular case of the striking surface of the seam.

Then, the surface of the seam if necessary tone.

Pouring molten lead-based you can make the seam underneath the plinth of the monument, with the pouring of the melt into the seam passes through the upper channel Gating system.

The molten lead-based use again.

As the melt based on the use of lead lead.

As the melt based on the use of lead melt on its basis, not containing antimony.

Using the proposed method melt lead-based allows you to get a tight seam with corrosion resistance, adaptability, the ability t is the planning, as well as the possibility of repair without cost material by procchance seam.

Lead and alloys on its basis be tinted in a wide range of colors, which is important when carrying out restoration works.

The claimed method is environmentally friendly, as the molten lead-based liquid and solid state is multi-material, not requiring disposal and material Gating channels - kaolin clay is also reusable material that does not require disposal.

Holding pouring molten lead through a system of Gating channels allows the fill resealable seam with a minimum flow rate of the melt, to regulate the feed rate of the melt into the joint and reduce the formation of slag on the weld surface.

In addition, when performing system Gating channels seam fill the molding material so that after pouring was formed seam desired configuration.

The method is illustrated by figure 1 and figure 2. Figure 1 shows the seam sealing molten lead-based; figure 2 - seam sealing under the plinth restored object molten lead-based, with 1 terminal block, 2 - melt lead-based, 3 - Gating channels, 4 - pedestal restored object, 5 - Gating bowl.

Example 1 illustrates the sealing of joints is acceptable depth of molten lead-based, located on the vertical and horizontal planes restored object comprising an angle between 0° to 180° with the horizontal plane of the restored object (see figure 1).

Before seam sealing molten lead-based from misonoo space, subject to sealing, remove all old loose, drop-insert (termination), earth, moss and the like.

If necessary, the joints and dried produce filling in misonoo space dry non-combustible materials to ensure a minimum flow rate of molten lead.

Create a system of Gating channels for delivery of molten lead-based in resealable seam.

For this seam and adjacent parts of the surface sformovat refractory mass on the basis of kaolin clay and are in the form of Gating channels and vapory. When filling the vertical joints is preferable to use Gating bowl.

The molten lead-based is obtained by loading dry charge lead or alloy-based pre-calcined metal crucible furnace download small portions, providing uniform heating of the charge in the crucible.

Then, using a blowtorch or a gas burner, the mixture is heated to 320-350°C.

Fill start from the bottom Gating of the channel.

Fill races the lava lead-based conduct continuous stream.

After casting, Gating system are removed.

If necessary, the surface of the sealed seam area to remove excess lead or alloy based on it.

Depending on the requirements of the joint surface, and if it is not possible to form it by casting (i.e. by adding the seam configuration using a molding material, in which the Gating system of channels), then the surface of the weld prochekayut special tool.

Then the seam tone.

Example 2 illustrates the sealing of the molten lead-based joints under the plinth restored object (see figure 2).

The space under the plinth is cleaned with compressed air, dry, create Gating the channel system of the refractory mass on the basis of kaolin clay and foundry set the bowl near the top of channel Gating system.

Pouring molten lead-based conduct continuous stream.

After casting, Gating system are removed.

1. Method of sealing a seam when carrying out restoration work on the monuments of sculpture, characterized by the fact that before pouring the molten lead-based seam dried and put in misonoo space dry non-flammable materials, seam sealing is carried out by pouring the melt into the joint through a system of Gating channels, made of the molding m is material, providing a holding sealing seam weld formation of a given configuration, with the pouring of the melt is carried out in a continuous stream.

2. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to claim 1, characterized in that the sealing seam melt lead-based hold to a depth of 5-250 mm

3. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 and 2, characterized in that the Gating channels supplied with Gating bowls.

4. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 3, characterized in that the molding material used refractory mass on the basis of kaolin clay.

5. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 4, characterized in that the conducting sealing bead located on a vertical surface.

6. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 4, characterized in that the conducting sealing bead located on a horizontal surface.

7. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 4, characterized in that the spend is hermeticaly seam, located on the surface, forming an angle between 0 and 90° horizontal surface.

8. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 7, characterized in that hold the sealing seam has a width of 2-5 mm

9. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 8, characterized in that hold the sealing seam has a width of more than 5 mm

10. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 9, characterized in that conduct seam sealing molten lead-based, which is obtained by loading dry charge lead or alloy-based pre-calcined metal crucible in small portions and further heating the mixture up to 320-350°C.

11. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to claim 5, characterized in that the pouring of molten lead into the seam start from the bottom Gating of the channel.

12. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 11, characterized in that after the pouring of molten lead into the joint conduct the strike of the seam.

13. Method of sealing a seam when conducting restaur the traditional work on the monuments of sculpture at para.12, characterized in that after procchance seam tone.

14. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 11, characterized in that the pouring of molten lead-based exercise in the seam underneath the plinth of the monument, with the pouring of the melt into the seam passes through the upper channel Gating system.

15. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 14, characterized in that the sealing seam is carried out by melt lead-based, recycled.

16. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 15, characterized in that the sealing seam is carried out by melt lead.

17. Method of sealing a seam when carrying out restoration work on the monuments of sculpture according to any one of claims 1 to 15, characterized in that the sealing seam is carried out by melt lead-based, does not contain antimony.

 

© 2013-2014 Russian business network RussianPatents.com - Special Russian commercial information project for world wide. Foreign filing in English.