Method to perform underwater technical works during installation of bulk items and device for its realisation

FIELD: construction.

SUBSTANCE: method to perform underwater technical works during installation of bulk items includes delivery of an item in the form of a box caisson to the place of installation, its flooding and assembly with the help of a cargo barge and a floating lifting facility. Delivery is carried out using a double-hulled watercraft made as capable of placement of the loaded barge in the space between pontoons that form the double hull and are connected to each other with metal frame structures with weight-lifting facilities for lifting and lowering of the box caisson, and also equipped with structures having extended elements, providing for retention of the box caisson as it is delivered to the place of installation. The barge with the box caisson of full availability is driven in the water area in the space between pontoons of the double-hulled watercraft, the box caisson is lifted with the help of its weight-lifting facilities, the unloaded barge is driven from the space between the pontoons into the water area, the box caisson is lowered for its installation onto extended elements, the specified elements are extended with the help of a drive, and the box caisson is rested onto them. The watercraft with the box caisson by self-motion or towing is delivered to the place of works production, the watercraft is moored, and the box caisson is flooded and installed by release from extended elements that retain it using weight-lifting facilities, which are installed on the watercraft.

EFFECT: optimised technology and reduced costs for production of underwater technical works during assembly of bulk items and structures.

7 cl, 5 dwg

 

The invention relates to hydraulic construction, in particular to the construction of piers, underwater walling, artificial island, subsea protective structures on the shelf.

It is known that during the construction of the piers of floating caissons method of delivery of arrays giant floating way with their subsequent flooding and loading ballast (Ugualmente "berths" - M.: Transport, 1981, p.106-111, 170-173).

A known method of construction of berths is characterized by a high volume of work due to the complexity of the run at large depths operations installation under water floating caissons and download the ballast, as well as the need for the installation of such objects floating cranes large capacity.

There is a method of block-modular construction of hydraulic structures in underwater excavations, adopted as a prototype, which consists in the fact that the block-modules prefabrication delivered to the construction site on barges, platforms and set in the design position underwater base in one or more layers using a floating lifting means high capacity, while the barge-platform with the block module is set on the underwater excavation, using floating lifting means implementing tlaut astropulse and the rise of the units above the barge deck, take a barge-pad from under the block-module, then the unit is lowered and set in the design position underwater base, block-modules structures fasten to each other and sealed by the mating parts with the quick-connect devices (patent RF №2401356 C1, priority date 17.02.2009, publication date 10.10.2010, the authors V.A. Kiselev, etc., RU, prototype)

The disadvantage of this method, adopted as a prototype, is the high complexity of the work, as well as the costs caused by the use of floating lifting means high capacity, and complexity of maneuvering barges at the place of installation works.

Known lifting means high capacity, used in the method according to the patent of Russian Federation №2401356 comprising a floating base in the form of the hull and installed on it lifting boom lifting device made balanced on the rotary column containing the bulk of the cargo boom and auxiliary counterbalanced boom hinged on her external counterweight connected polyspastny systems, and relies on the support cylinders and lifting heavy products perform multiple lifting devices installed on the same hull, working jointly and synchronously, with the possibility of changing the distance between the load suspension points, depending on the length and mass distribution raised products, samokleyushchikhsya in the transport position at an angle relative to the longitudinal axis of the vessel (patent RF №2320529 C1, the priority date of dated 25.05.2006, publication date 27.03.2008, the authors V.A. Kiselev, etc., EN).

A disadvantage of the known device is the design complexity and high intensity, and therefore, economically viable use of this construction to perform work on lifting, installation and overload supertiling and superhumanity products.

Famous boats catamaran base type to perform rescue operations, for example for lifting emergency submarines (patents of the Russian Federation№№2284277, 2328405, 2377155, 2388648). Each of them has a special purpose and are not suitable for installation under water, for example, arrays giants, as placebos catamaran combined into a single structure with bow and stern so that between them it is impossible to enter a barge with an array of giant.

Known complex for lifting sunken object, taken as a prototype device that includes a base ship-catamaran, consisting of two buildings placed on it lifting mechanism in the form of a bridge crane, associated with steel wire, kanatas traverse, equipped with a lifting device and a rocket propulsion unit with adjustable thrust, while lifting device made in the form of pivotally mounted on the transverse lever is kinematically connected with it by means of a power cylinder and cooperating with a sunken object (patent RF №2366591 C1, priority date 07.05.2008, publication date 10.09.2009, author Tarasov WD, RU, prototype)

The drawback of the device, taken as a prototype, is of limited use associated with lifting objects and unsuitability for installation under water.

The objective of the invention is to optimize the technology and reducing the cost of manufacture of underwater technical works during installation of large objects and structures.

To solve this problem the method of manufacturing underwater engineering works during installation of large objects, including delivery of object in an array-giant to the place of installation, its flooding and installation using cargo barges and floating lifting means according to the invention, it is carried out using boats catamaran base type, made with the possibility of placing the loaded barges in the space between the forming catamaran pontoons interconnected metal frame structures with lifting medium spans the you for lifting and lowering a massive giant, and also have designs with sliding elements ensures retention of the array-giant at its delivery to the installation site, the barge with an array of giant cooked wind on the water area in the space between the pontoons boats catamaran base type, is lifted by means of its lifting means an array of giant, is removed from the space between the pontoons in the water area of the unloaded barge omit the array-giant for laying it on the sliding elements to bring these items with drive and relies on them an array of giant, floating with an array of giant roll off or towing delivered to the work site, moor the craft and implement the flooding of the array-giant and installation of exemption from restraint of his retractable elements using the lifting means, which are equipped with the craft.

According to the invention, the method can be applied to arrays giants in the form of a parallelepiped.

According to the invention, the method can be applied to arrays giants in the form of a truncated parallelepiped with a beveled base, or made with regard to the topography of the underwater surface, when they perform with the response niches-jacks, interacting with the corresponding sliding elements that hold an array of giant, and rabaut at the base of the ground tabs.

According to the invention, the method can be applied to an array of giant, formed of small objects by combining them on the platform in a large module.

According to the invention, in the method using arrays giants with permeable walls and waterproof walls and bulkheads.

To solve the problem in the craft catamaran base type, including the joint between the pontoons placed in between lifting and hoisting machinery, according to the invention, the pontoons in the United catamaran metal frame structures with location between cargo vessels with large objects in the fore and aft parts of the boats are equipped with removable transitional bridges, building each of the pontoons are equipped with structures with sliding elements-polubinski, which support elements cantilever type, located in the upper part and/or in the bottom of the hull of the pontoon and operated by hydraulic or mechanical servomotors with their corresponding actuators, metal frame equipped with polyspastny pendants and traction winches, forming a lifting and traction system, and on the deck of the watercraft installed mooring winch.

According to the invention, the design vidigreet.com-poloumnim, controlled hydraulic actuator supplied is made in the case of pontoon guide, probems, guide hermetically connected with the end wall of the hydraulic cylinder, and the movable rod of the hydraulic cylinder is connected to poloumnim, while the hydraulic cylinder is connected with the supply system of the liquid in the cavity containing the injection pump.

1 schematically depicts a craft catamaran base type used in the production method of underwater engineering works during installation of large objects as arrays giants, General view; figure 2 is a top view; figure 3 shows the craft with designs of retractable elements polubesova located in the bottom; figure 4 shows a scheme of a sliding element polubelca using the hydraulic actuator; figure 5 (a, b, C) shows the shapes of the blocks used in the method.

The craft catamaran base type used in the production method of underwater engineering works during installation of bulky objects, for example in the construction of the piers of floating caissons formed of two pontoons 1, combined in a catamaran metal frame structures 2 with location between barges with an array of giant 3 designed for installation under water (conventionally not shown). To ensure ill the bone structure and manufacturing operations in the bow and stern of the craft is fitted with removable transitional bridges 4, partially relieve the metal frame 2 from the action of bending moments. The case of each of the pontoons 1 equipped designs with sliding elements-polubinski 5, designed for the installation of the array-giant 3. Retractable elements olubisi 5 are support elements of the cantilever type and are located in the upper part of the body of the pontoon, as shown in figure 1, or in the bottom 3. This arrangement retractable elements polubesova relates to the form of execution was fixed on them floating caissons 3. To install the array of giant flat shape of the base, as shown in figure 5(a) or 5(b)are retractable elements olubisi above, and to install a massive giant with a beveled base, as shown in figure 5(b)are retractable elements olubisi that are located below. This secured them an array of giant fitted with made it return niches-jacks 6, which interacts with the lower retractable members polubinski. The most optimal variant in which design with retractable elements-polubinski 5 is installed in the upper part and the bottom of the hull of the pontoon (conventionally not shown). To control the sliding elements-polubinski 5 buildings pontoons installed hydraulic servomotor with actuator. With vomitory may also be in mechanical design with rack-and-pinion, screw, etc. movement mechanisms (not shown conventionally). However, each must have its own drive. The most effective is the use of a hydraulic motor with a hydraulic drive. The design with retractable element poloumnim controlled hydraulic actuator supplied is made in the case of pontoon guide 7, which features a retractable element probems 5. Guide 7 is hermetically connected with the front wall 8 of the cylinder 9, and a movable rod 10 of the hydraulic cylinder with the piston 11 is connected with a sliding element poloumnim 5. When the cylinder 9 is connected with the supply system of a liquid in a cavity containing a pressure pump 12 and the elements of the system the fluid in the cylinder cavity, in the form of automatically-controlled locking devices 13, 14, 15, 16, 17. To ensure the fluid in the cavity of the working cylinders involved one pressure pump 12.

Metal frame construction 2 connecting the chassis of the pontoons 1 in the fore and aft fitted with polyspastny pendants 18 and traction winches 19 forming the lifting and traction system that allows you to find the optimal conditions of tractive effort on the winches and polyspastny suspensions when conducting business operations.

On the deck of the craft in the fore and aft parts of the set t is the train mooring winch 20, used for boats at a given point.

Method for the production of underwater technical works during installation of bulky objects, for example in the construction of the piers of floating caissons using published boats catamaran base type is as follows. It is assumed that the arrays giants made and load ballast on the surface. While the blocks of floating caissons can be of any shape, as shown in figure 5 (a, b, C). However, they can be made with the holders 21 in the base may be formed of compact objects by combining them on the platform 22 in a large module, and the array enclosure-giant to reduce adverse seepage impacts and their control comply with permeable or impermeable sides and bulkheads (not shown conventionally). Ready arrays giants, for example, on the barge-platform deliver on the specified gear. Barge-pad is slid into the space between the pontoons 1 catamaran in the water zone and fail under load lifting polyspastny suspension 18. Using the lift-propulsion systems catamaran array-giant 3 is lifted to a height sufficient for the removal of the barge and extensions polubesova 5. Then the barge is taken out into the waters. Then by means of a hydraulic drive in the move olubisi 5, for example the top or deck, on which omit the array-giant 3. When using the lower or submerged sliding elements polubesova array-giant feature with the possibility of their interaction with the response niches-jacks 6 array-giant. After installation of the array of giant retractable elements olubisi 5 raskrepljajut. Next catamaran roll off or towing transported to the place of laying array-giant on the ground. With the approach of the boat to the dive sites of the array of giant ground catamaran exhibited in the estimated target and escalivada mooring kranzo with mooring winches 20. When immersing the array of giant under water is possible maneuvering hull catamaran with mooring winches 20. Polyspastny suspension 18 catamaran allow you to adjust the speed of immersion and precision to set the array-giant on the ground with regard to pitch and roll.

The advantage of the proposed method of production of underwater technical works during installation of large objects is to simplify the technology and reducing the cost of manufacture of underwater technical works during installation of large objects and structures through the use of for its implementation of pleurodema catamaran base type, which allows to optimize the technology and refuse to use design, the sports complex and expensive floating crane large capacity.

1. Method for the production of underwater technical works during installation of large objects, including delivery of object in an array-giant to the place of installation, its flooding and installation using cargo barges and floating lifting means, characterized in that it is carried out using boats catamaran base type, made with the possibility of placing the loaded barges in the space between the forming catamaran pontoons interconnected metal frame structures with lifting means for lifting and lowering a massive giant, and is also provided with structures with sliding elements ensures retention of the array-giant at its delivery to the place of installation, when this a barge with an array of giant cooked wind on the water area in the space between the pontoons boats catamaran base type, is lifted by means of its lifting means an array of giant, is removed from the space between the pontoons in the water area of the unloaded barge omit the array-giant for laying it on the sliding elements to bring these items with drive and relies on them an array of giant, floating with an array of giant roll off or towing delivered to the work site, moor the craft and implement the flooding of massimiliana and installation of exemption from restraint of his retractable elements using the lifting means, which are equipped with the craft.

2. Method for the production of underwater engineering works according to claim 1, characterized in that it can be applied to arrays giants in the form of a parallelepiped.

3. Method for the production of underwater engineering works according to claim 1, characterized in that it can be applied to arrays giants in the form of a truncated parallelepiped with a beveled base or made with regard to the topography of the underwater surface, when they perform with the response niches-jacks, interacting with the corresponding sliding elements that hold an array of giant, and provide the basis of ground tabs.

4. Method for the production of underwater engineering works according to claim 1, characterized in that it can be used an array of giant, formed of small objects by combining them on the platform in a large module.

5. Method for the production of underwater engineering works according to claim 1, characterized in that it uses arrays giants with permeable walls and waterproof walls and bulkheads.

6. The craft catamaran base type, including the joint between the pontoons located between lifting and hoisting machinery, characterized in that the pontoons in the United catamaran metal frame structures with the ability dissolved, and the situation between them cargo vessels with large objects in the bow and stern of the craft is fitted with removable transitional bridges, building each of the pontoons are equipped with structures with sliding elements-polubinski, which support elements cantilever type, located in the upper part and/or in the bottom of the hull of the pontoon and operated by hydraulic or mechanical servomotors with their corresponding actuators, metal frame equipped with polyspastny pendants and traction winches, forming a lifting and traction system, and on the deck of the watercraft installed mooring winch.

7. The craft catamaran base type according to claim 6, characterized in that design with a sliding element poloumnim controlled hydraulic actuator supplied is made in the case of pontoon guide, probems, guide hermetically connected with the end wall of the hydraulic cylinder, and the movable rod of the hydraulic cylinder is connected to poloumnim, while the hydraulic cylinder is connected with the supply system of the liquid in the cavity containing the injection pump.



 

Same patents:

FIELD: construction.

SUBSTANCE: underwater garage comprises a tight body, descents for entry and exit of transport from the garage, floors arranged within the body. The body is arranged in the form of a module representing a tight solid reinforced concrete box. At the end sections of the body there are ramps arranged, which are made curvilinear and rise above water. Entry and exit are carried out along a piled bridge that connects the quay and the curvilinear ramps. The method to construct the underwater garage includes construction of a coastal pit separated from the river with a soil dam. The pit is arranged by providing vertical walls reinforced with the help of a metal rabbet. Then assembly is carried out in the module pit, and it is hydraulically insulated. The pit is filled with water, the dam is dismantled, and the module is transported to the place of installation. The module is installed into a previously prepared underwater pit by means of partial filling of the module with water, the module is surcharged in order to prevent floating and, and works are performed to reinforce the bottom with subsequent water pumping. Descents are arranged in the form of the piled bridge that connects the quay and the ramps of the underwater garage.

EFFECT: improved conditions for operation due to considerable reduction of space for entering a garage using curvilinear ramps.

2 cl, 5 dwg

The invention relates to the field of construction and mining and can be used in the construction of sub-seabed tunnel large extent

The invention relates to the field of construction and can be used in the construction of new pipelines or repair of existing in remote areas, mainly in swamps and flooded areas

The invention relates to a method of production of oil and gas activities in deepwater areas with severe weather and climate conditions, including the Arctic shelf, and marine structures hydraulic structures for this

The invention relates to a method of construction of underwater structures for preservation of submerged hazardous objects resulting from human activity, for example, due to accidents, flooding

The invention relates to the field of construction, allows you to build the foundations for deep water and is that the bearing shell is made of sections manufactured in the form of cylindrical rings with holes symmetrically positioned around the circumference of, and coaxially lowered to the ground by stringing on rails suspended from the conductor, located above the water surface, then through the cavity are developing well, which then together with the cavities of the shell are filled with structural material

FIELD: construction.

SUBSTANCE: underwater garage comprises a tight body, descents for entry and exit of transport from the garage, floors arranged within the body. The body is arranged in the form of a module representing a tight solid reinforced concrete box. At the end sections of the body there are ramps arranged, which are made curvilinear and rise above water. Entry and exit are carried out along a piled bridge that connects the quay and the curvilinear ramps. The method to construct the underwater garage includes construction of a coastal pit separated from the river with a soil dam. The pit is arranged by providing vertical walls reinforced with the help of a metal rabbet. Then assembly is carried out in the module pit, and it is hydraulically insulated. The pit is filled with water, the dam is dismantled, and the module is transported to the place of installation. The module is installed into a previously prepared underwater pit by means of partial filling of the module with water, the module is surcharged in order to prevent floating and, and works are performed to reinforce the bottom with subsequent water pumping. Descents are arranged in the form of the piled bridge that connects the quay and the ramps of the underwater garage.

EFFECT: improved conditions for operation due to considerable reduction of space for entering a garage using curvilinear ramps.

2 cl, 5 dwg

FIELD: construction.

SUBSTANCE: method to perform underwater technical works during installation of bulk items includes delivery of an item in the form of a box caisson to the place of installation, its flooding and assembly with the help of a cargo barge and a floating lifting facility. Delivery is carried out using a double-hulled watercraft made as capable of placement of the loaded barge in the space between pontoons that form the double hull and are connected to each other with metal frame structures with weight-lifting facilities for lifting and lowering of the box caisson, and also equipped with structures having extended elements, providing for retention of the box caisson as it is delivered to the place of installation. The barge with the box caisson of full availability is driven in the water area in the space between pontoons of the double-hulled watercraft, the box caisson is lifted with the help of its weight-lifting facilities, the unloaded barge is driven from the space between the pontoons into the water area, the box caisson is lowered for its installation onto extended elements, the specified elements are extended with the help of a drive, and the box caisson is rested onto them. The watercraft with the box caisson by self-motion or towing is delivered to the place of works production, the watercraft is moored, and the box caisson is flooded and installed by release from extended elements that retain it using weight-lifting facilities, which are installed on the watercraft.

EFFECT: optimised technology and reduced costs for production of underwater technical works during assembly of bulk items and structures.

7 cl, 5 dwg

FIELD: construction.

SUBSTANCE: method to erect underwater tunnels, including tunnelling of slopes and drifts, creation of a mine of arched shape, fixation of its walls and fixation of its walls and vault by monolithic reinforced concrete, backlining external hydraulic insulation from bitumen putty, a ramp and a water impermeable lock, water drainage by means of drainage trays, differing by the fact that in order to ensure efficiency of tunnelling works and higher reliability of tunnel hydraulic insulation, its length is divided into sections with open and underground methods of tunnelling. An inclined entry trench is built on an open area with minimum water level in a river by means of open works, in the end of the trench a protective horseshoe-shaped border is erected from reinforced concrete, walls are erected, the arched vault of the tunnel with rigging, on top of which they lay a hydraulic insulation jacket from Typar material and filled with removed soil, the tunnelling of the underwater section of the tunnel is carried out in a regimen of moderation by tunnelling combines in counter headways until they are joined at the design elevation, and water breakthrough in the tunnel is collected in a sump with subsequent pumping by pumps via wells to a surface interception ditch, connected with a water reservoir.

EFFECT: higher reliability of tunnel hydraulic insulation, reduced labour intensiveness and material intensity in construction.

1 tbl, 4 dwg

FIELD: construction.

SUBSTANCE: underwater structure (US) operates at depth in the range from 100 to 120 m from sea level. At the same time the US comprises a support-bearing underwater complex and a drilling complex or a production complex. The support-bearing underwater complex includes a support-bearing plate and a wellhead complex. The support-bearing plate, in its turn, comprises a wellhead block, an energy block, a residential block, and also a life support block, internal and external circular corridors, radial transitions, sectioned ballast pontoons of circular shape and propelling agents. Retention of the underwater structure in the vertical position at the specified point for the whole period of stay is provided by control of filling of ballast pontoon sections, at the same time retention in the horizontal plane is done due to operation of the propelling agents. The inner surface of the body of the drilling complex and the production complex is congruent to the external surface of the wellhead complex, and the lower surface of the body of the drilling complex and the production complex is congruent to the upper surface of the support-bearing plate.

EFFECT: increased safety, reliability and quality of performed works.

13 cl, 5 dwg

Pier // 2535726

FIELD: construction.

SUBSTANCE: pier is a linear gravitational hydraulic structure located on the coast of the Arctic seas, mainly in lower reaches of navigable rivers. The pier is designed in the form of an ice platform 1 of a rectangular section, placed on the sea bottom. The pier is equipped with wind-capture electric power plants 10 of a tower type located on the shore, liquid cooling and air cooling systems in the form of pass channels 2. The pier is additionally equipped with a thermo-fluid insulating screen 7, placed on the platform surface 1, and a solid floor covering 8 in the form of flat elements of a rectangular shape in plan, arranged at an angle of 45°C to the longitudinal axis of the platform. The platform 1 is designed with slopes at side edges, located at the level of calved ice. The liquid cooling system is designed of interconnected atmospheric cold storage batteries 3, 4 of cooling pipelines 5, 6 and consumers of a coolant 9. The cooling pipelines are arranged along the slopes and under the thermo-fluid insulating screen 7.

EFFECT: increased strength, stability, reliability and durability of the ice structure.

6 dwg

FIELD: construction.

SUBSTANCE: invention relates to construction, particularly, to underwater structures built below bed surface level. Method for construction of tunnel bridge in underwater channel for overcoming shallow crossings involves construction of underwater channel and building underwater structure on its bottom, which is covered with protective casing. Underwater structure is made in form of tunnel bridge, which is built along underwater channel with arrangement of entries and exits into/from tunnel bridge on banks of crossing; tunnel walls are made as retaining walls, which are attached to steel-concrete pillars, fixed in bottom of underwater channel, and coated with plastic sheets. Protective casing is made of steel concrete, tightly placed on retaining walls above tunnel bridge, and also covered with plastic sheets.

EFFECT: technical result consists in providing security and favourable operation conditions in tunnel bridge, reduction of material and labour expenditures for tunnel bridge construction.

1 cl, 1 dwg

FIELD: construction.

SUBSTANCE: invention relates to construction, namely to erection of underground structures. Erection method of multilayer walls of underwater structures includes installation of frame from three and more panels and their separation with air layers. All three and more panels of multilayer walls are made of fibre-glass. They are bound together by adhesion to separating mounting frames with additional reinforcement using screws. Air layers between panels are connected to sources of compressed air or liquid nitrogen, which is connected to pressure sensors and (or) water detection sensors installed in air layers.

EFFECT: high strength of frame structure, safer operation of destruction of panels, lower material consumption.

1 cl, 1 dwg

FIELD: construction.

SUBSTANCE: invention relates to underwater structures and can be used in construction of automobile and railway tunnels under reservoirs. Transport passage contains an underwater tunnel placed in water under the navigable channel of a water reservoir or strait made of interconnected reinforced concrete monolith sections positioned relative to the surface of the reservoir or strait bottom and provided with transport infrastructure, consisting of two transport purpose trackways with a rail track between, while the latter is separated by arch colonnades from auto transport carriageways; adjoining the opposite banks of a water reservoir or strait spanned bridges of reinforced concrete structures to ensure water exchange directly along the shores made with transport infrastructure, consisting of two auto transport carriageways with a rail track between, and inclined access ways connecting the underwater tunnel with the spanned bridges having transport infrastructure, consisting of two auto transport with a rail track between. Reinforced-concrete monolith sections of the underwater tunnel, having a two-layer covering, are laid on a base in the form of a reinforced concrete plate, serving as a balance weight for implementation of the injection strengthening of soil under the tunnel base and enlargement of the area of the tunnel supporting on the reservoir or strait bottom with a specific pressure of not more than the pressure of from soil retracted during preparation of a pit for accommodating of the two-layer base. Throughout the whole length of the tunnel along its whole perimeter and between the layers of the bottom and the base there is stretched an anti-filtration coating of geo-membrane, protected by backfilling of the tunnel side walls supported by inclined outer faces of the tunnel walls from heavy loam. Inclined accesses connecting the underwater tunnel with spanned bridges, at least on a part of their length, are made in the embankment with arrangement of the remaining part of length in the groove, relative to the bottom of a water reservoir or strait, separated from its water area on both sides by earth dams and supporting walls and by strengthened on the external slopes rock mass. Above the reinforced concrete monolith sections of the underwater tunnel in the navigable channel there is a protective reinforced concrete plate resting on backfills of side walls of the tunnel and being a bottom of the navigable channel going from which are vertically oriented conjugated abutments, which are the walls of the navigable channel.

EFFECT: higher operational reliability and longer service life of the structure, simplification of construction technology and structure design.

7 cl, 4 dwg

FIELD: gas industry.

SUBSTANCE: group of inventions relates to underwater structures and is intended for underwater development of gas deposits and liquefaction of natural gas in water areas of Arctic Ocean, which for a long time or permanently are covered with ice fields that are hard to navigate for Arctic ice breakers prevent production and transport of borehole fluid by conventional method. Underwater system for underwater development of gas deposits and natural gas liquefaction is designed for year-round operation at depth within range of 100-120 m from sea level. Said system comprises drilling-extraction underwater structure, underwater accommodations with control center, underwater nuclear power plant, underwater plant to liquefy natural gas, underwater tank for receiving/storage of liquid nitrogen, underwater tank for receiving/storage/shipment of liquefied natural gas and underwater liquefied gas tanker. Drilling-extraction underwater structure has capacity for year-round underwater well drilling and operation with well fluid purification from mechanical impurities. Drilling-extraction underwater structure is connected to plant for natural gas liquefaction by binding flexible tube with length, providing cooling of natural gas in Arctic environment of sea to a specified value. Underwater plant to liquefy natural gas is configured for its liquefaction by cascade stepped successive cooling to condensation temperature in counterflow with liquid nitrogen and providing output of spent liquid nitrogen in exhaust flexible pipe into atmosphere and/or under ice. Underwater nuclear power plant is configured to provide electric energy via flexible floating cables to all underwater structures.

EFFECT: higher safety and quality of work in underwater development of gas deposits and underwater liquefaction of natural gas.

7 cl, 2 dwg

FIELD: construction.

SUBSTANCE: group of inventions relates to hydrotechnical construction and can be used for creation and operation of offshore pile-gravity platforms for exploration of continental shelf hydrocarbon resources. Platform comprises superstructure, body with foundation, equipped with slots in form of direct correct cylinder, through which piles are installed. At that, piles are equipped with heads in form of inverted truncated regular cones with base diameters, smaller than diameter of slots in foundation, mounted on piles buried into slots with head cone base gradient above slot top.

EFFECT: technical result consists in improvement of platform stability and reduction of materials consumption.

10 cl, 5 dwg