Method to construct station tunnels with low subsidence of earth surface

FIELD: mining.

SUBSTANCE: method to construct station tunnels with low subsidence of earth surface includes erection of an advance support and a temporary support along a tunnel vault, erection of permanent lining and mining of bottomhole rock, according to the invention, in a bottomhole under protection of the advance support along the longitudinal axis of the tunnel there are injection fibreglass anchors installed, the temporary support is erected providing for maintenance of the advance support, and mounted from steel arcs directly following face advance with filling of the support space with concrete, the permanent lining is erected after temporary support concrete gains strength. At the same time injection fibreglass anchors are cut in layers with a tunnelling unit together with rock in the bottomhole as it advances. At the same time the advance support is erected by drilling of wells along the tunnel vault at the angle to its longitudinal axis, placement of metal pipes in wells and filling of pipes with cement mortar.

EFFECT: increased quality of tunnel construction by reduction of earth surface subsidence at main stages of construction.

2 cl, 2 dwg

 

The invention relates to the construction of underground structures and can be used in the construction of the deeper stations in moderately and weakly resistant soils.

The known method of tunnel construction in moderately and weakly resistant soils (patent RU C1 2096622, CL E21D 9/00, E21D 13/04 was investigated, 1997), including the construction of advanced and temporary supports on the arch of the tunnel, under the protection of the permanent lining construction and development of the breed slaughter.

The disadvantage of this method is that during its implementation occur large displacement of the soil mass and precipitation of the earth surface, which reduces the quality of the construction of the tunnels.

The known method of tunnel construction in moderately and weakly resistant soils (patent RU C1 2205957, CL E21D 9/00, E21D 13/04 was investigated, 2002)adopted for the prototype. The method includes the construction of advanced and temporary supports on the arch of the tunnel, under the protection of the permanent lining construction and development of the breed slaughter.

The disadvantage of this method consists in the fact that the project would occur large displacement of the soil mass and upsetting the earth's surface. This is due to large displacements of the roof and bottom of the tunnel on the main stages of construction, which reduces the quality of the construction of the tunnels.

The technical result of the invention is to improve the quality of tunnel construction by reducing the sediment of the earth surface on the main floor the groin construction.

The technical result is achieved in that the method of construction of the station tunnels with low precipitation the earth's surface, including the construction of advanced lining and temporary supports on the arch of the tunnel, under their protection the construction of the permanent lining and the development of rock bottom, according to the invention in the pit under the defense advanced lining along the longitudinal axis of the tunnel set injection fiberglass anchor, temporary shoring is erected to ensure maintenance of advanced lining and mount steel arches directly behind podvigina face with the filling Sakrebulo space with concrete and permanent lining erected after curing concrete temporary piles, while injecting fiberglass anchor layers cut tunnel Assembly together with rock in the pit as it podvigina.

The technical result is also achieved by the fact that ahead of the support is constructed by drilling holes on the tunnel ceiling at an angle to its longitudinal axis, accommodation in wells metal pipes and fill pipes with cement mortar.

The method is implemented as follows (as shown in the drawing).

The method of construction of the station tunnels with small rainfall earth surface includes construction of an advanced lining 1 and the temporary roof support 2 on the tunnel ceiling 3, under their protection vowed is the permanent lining 4 and the development of rock bottom 5. In the pit 5 under the defense advanced lining 1 along the longitudinal axis of the tunnel 3 sets of injection fiberglass anchor 6. Temporary shoring 2 erect with maintenance of advanced lining 1 and the mount of steel arches directly behind podvigina bottom 5 with filling Sakrebulo space with concrete 7. Permanent lining 4 erect after curing concrete 7 temporary roof support 2. Injection fiberglass anchor 6 layers cut tunnel unit together with the rock in the bottom 5 as it podvigina.

Ahead of the support 1 being constructed by drilling holes on the tunnel ceiling at an angle to its longitudinal axis, accommodation in wells metal pipes and fill pipes with cement mortar.

Install injection fiberglass anchors in the face along the longitudinal axis of the tunnel layer by cutting them as podvigina slaughter leads to the fact that the breed slaughter permanently rigidly connected to the array and is not able to move in a goaf. This limits the displacement of the soil mass in front of the tunnel and above the tunnel and reduces precipitation the earth's surface. The erection of temporary piles of steel arches directly behind podvigina slaughter eliminates periods of time when the bottom part of the tunnel is in a loose condition and test b is greater offset, as it happens in traditional construction technologies tunnels. It also limits the sediments of the earth's surface.

Thus, reinforcement of the roof and bottom of the tunnel on the main stages of construction of the tunnel the proposed method reduces the displacement of the soil mass and upsetting the earth's surface, which increases the quality of construction of underground structures.

1. The method of construction of the station tunnels with low precipitation the earth's surface, including the construction of advanced lining and temporary supports on the arch of the tunnel, under their protection the construction of the permanent lining and the development of rock bottom, characterized in that the bottom under advanced protection lining along the longitudinal axis of the tunnel set injection fiberglass anchor, temporary shoring is erected to ensure maintenance of advanced lining and mount steel arches directly behind podvigina face with the filling Sakrebulo space with concrete and permanent lining erected after curing concrete temporary piles, while injecting fiberglass anchor layers cut tunnel unit together with the breed in the pit on as it podvigina.

2. The method according to claim 1, characterized in that the better the support is constructed by drilling holes on the tunnel ceiling at an angle to its longitudinal axis, accommodation in well the metal pipes and fill pipes with cement mortar.



 

Same patents:

FIELD: mining.

SUBSTANCE: complex for tunnelling of a subway mine of round cross section comprises mechanisms of rock breaking arranged on a carcass equipped with a movement drive, a transshipment device for loading of rock mass into transport facilities. The transshipment device is made in the form of a chute of cylindrical shape fixed on the frame and normally oriented towards the bottomhole, the lower edge of the chute is located at the sharp angle a to the mine base and with limitation of the upper edges of the chute with the horizontal plane arranged at the level of the central axis of the mine or with certain downward displacement. Inside the chute in its middle part there is an infinitely closed double-chain scraper contour on driving and tension sprockets with a curvilinear external profile of scrapers, and with the possibility of interaction of scrapers in the lower weight-bearing branch with the chute base, and the upper idle branch - with resting against the rollers.

EFFECT: improved reliability of complex operation, elimination of rock mass accumulation near a bottomhole as a result of mine tunnelling, reduced labour intensiveness of complex maintenance and its increased efficiency due to elimination of complex idle time.

3 dwg

FIELD: mining.

SUBSTANCE: method includes the following stages. Installation of a structure inside or tightly with an underground mine, so that the structure provides for reactive forces when pushing a cutting head in direction of the material by means of a series of rigid materials fixed on the structure, which i arranged so that series of rigid elements may be fixed to it simultaneously at least in two directions, so that parts of tunnel branches could be formed in at least two appropriate directions, of the underground mine designed for transportation of people, mechanisms and extracted material. Formation of multiple parts of tunnel branches entering the material. Formation of the first part of the tunnel branch with the help of a cutting head and a series of rigid elements in the first direction, and afterwards formation of the second part of the tunnel branch in the second direction. During formation of the second part of the tunnel branch, movement of rigid elements from the part of the first tunnel into the part of the second tunnel branch for extension of the series of rigid elements in the part of the second tunnel branch.

EFFECT: application of the method considerably reduces costs, makes it possible to considerably increase speed of tunnelling and increases efficiency of production.

21 cl, 10 dwg

FIELD: mining.

SUBSTANCE: method to erect an underground mine with shield tunnelling using elements of an assembled circular lining of a support consists in mining soil with a mechanised shield. Plugging of the space behind the lining is carried out via holes in elements of a tubing support with a grouting mortar. At the initial stage of tunnelling a bottomhole is mined, and a part of the space behind the lining is filled at the length of 0.25-0.75 of the length of the element of the assembled circular lining of the support behind the first ring after the shield in the lining of the tubing support with a long-setting grouting mortar. The next stage of mining at the length of 0.5-1 of the length of the element of the assembled circular lining of the support is carried out with supply of the grouting mortar into the space behind the lining with a setting accelerator. At the stage of process shutdown of a shield for assembly of the next ring of the tubing support, the pressure of the grouting mortar in the space behind the lining behind the first ring after the shield for lining of the tubing support is maintained by means of the long-setting grouting mortar into the area of the section of the space behind the lining, initially filled with the long-setting grouting mortar. Further stages of soil mining and plugging of the space behind the lining are repeated.

EFFECT: higher efficiency and improved manufacturability of performed works, reduced labour intensiveness of overcoming emergency situations that occur in process of tunnelling.

4 cl

FIELD: mining.

SUBSTANCE: device for formation of tunnels contains cutting head provided with electric or hydraulic motor, mechanism for cutting head actuation, hydraulic mechanism connected to cutting head and designed with possibility of pushing of cutting heads towards the end of tunnel during material removal and supporting structure for support of previously formed part of tunnel. Supporting structure is designed so that to provide support on the tunnel surface both during stop and movement along the tunnel. Cutting head is designed with possibility to move independent of supporting structure. Besides the device has a conveyor for transportation of removed material from cutting head to the place distant from the cutting head during formation of part of tunnel. Also the method of tunnel formation using this device is proposed.

EFFECT: reducing time for tunnel driving.

31 cl, 4 dwg

FIELD: mining.

SUBSTANCE: method of tunnel building includes the following operations: soil development and its transportation, support of mine workings at driving with shotcrete, probably with anchors, arcs and net, geophysical measurement of rock density in bottom-hole zone, which results are used for correction of length of planned driving and thickness of layer of shotcrete in order to speed-up driving and to reduce shotcrete flow rate.

EFFECT: accident prevention, possibility of correction of driving method in order to speed-up it and correction of structure of temporary support in order to improve its efficiency, improving safety of underground operations.

2 cl, 5 dwg

Duplex geovehicle // 2469192

FIELD: mining.

SUBSTANCE: duplex geovehicle consists of three sections. Two front sections are mounted on load-carrying beams with drives by means of ball races with toothed rims of bevel gear. Section rotation drives are located on diaphragms that are mounted on front ends of load-carrying beams with drives. Each load-carrying beam with a drive is mounted in the guides of rear section with possibility of its retraction. A screw with a separate drive is mounted inside the load-carrying beam. On external surfaces of front rotating sections there located are screw blades with opposite winding direction. Before each blade there mounted are small actuating elements with individual drives and sleeves with screws. In the centre of diaphragms there mounted are hollow beams inside which screws with drives are mounted Flared ends and loading rotors with drives are mounted on the front side of face ends of hollow beams. Drives and actuating elements of rear section are located on its front wall. Outside the front wall: at the top and at the bottom - horizontally, and in the centre - vertically. Drag conveyor, tray and screw with a drive are located behind the front wall inside rear section.

EFFECT: increasing the strength of out-contour layer of rock mass.

5 dwg

FIELD: mining.

SUBSTANCE: method involves uniform destruction of rock mass with continuous cross cutters of cycloidal direction with working tool of planetary flat disc actuators and of tangential direction with working tool of rotary elements. The latter are installed behind front and rear parts of the disc and fixed on reduction gears of planetary flat disc destruction elements.

EFFECT: increasing rock mass destruction efficiency using cross cutters.

2 cl, 3 dwg

FIELD: ventilation.

SUBSTANCE: method involves moving of air with moving trains through the circulation ventilation connection connecting the tunnels near the subway station, and through the station. To create the desired air flow through the subway station from moving trains in the tunnel and its regulation depending on the frequency of train movement, the aerodynamic drag of circulation ventilation connection is changed.

EFFECT: lower economic costs for the ventilation of tunnels and subway stations.

2 dwg

FIELD: mining.

SUBSTANCE: method is implemented due to destructing the working face with cross cutters using rotary and planetary disc working members with lower power consumptions and yield of small ore fractions. In order to improve the efficiency of cross cutters, rock-destructing tool of planetary disc members moves in cycloidal-radial directions.

EFFECT: higher efficiency of destructing processes of mine rocks using heading-and-winning machines with cross cutters.

2 cl, 2 dwg

Loading elevator // 2456455

FIELD: machine building.

SUBSTANCE: tow hitch is made in the form of rods, eyelets and two mutually perpendicular axles of different diameters, with a smaller diameter axle that passes through a hole in the large-diameter axle for rotation and is connected through the eyelet with a thrust, and the axle of diameter is inserted with a gap into eyelets of a stretcher section of the loading elevator.

EFFECT: free movement of the machine in three directions with respect to the loading elevator, simplified design, reduction of overall size and weight of the loading elevator.

3 dwg

FIELD: mining industry.

SUBSTANCE: device has frontal, two side and two conical working tools with rock-destroying tools on outer surfaces, drives, rigidly connected to axes of each working tool, and displacement mechanism, connected to guides, placed at angle relatively to each other, which angle is determined from mathematical expression. Frontal and each of side working tools are made in form of two rotation bodies, having arced forming lines with given value of convexity. Axes of frontal working tool and axes of two conical working tools are rigidly connected to guides, axes of upper rotation body of frontal working tool being displaced relatively to axis of its lower rotation body towards pit-face, and axes of each pair of side working tools are jointly connected to each other and to guides. Frontal working tool may be made in form of several modules.

EFFECT: higher efficiency.

2 cl, 4 dwg

FIELD: mining industry.

SUBSTANCE: method includes expanding guiding pipeline by extracting soil from around it by driving shield with rotor working implement. Soil is extracted to value, surpassing needed outer diameter of shield cover. Forming ring-shaped space inside tunnel mine is compacted from back side and continuously filled with liquid. Concurrently sedimentation of extracted soil is drained from lower portion of face. Displacement of driving equipment relatively to guiding pipeline is performed along soft trajectory. Device has means for driving guiding pipeline and driving shield with rotor working implement. Rotor working implement is mounted on body of driving shield. Front surface of working implement with cutters extends beyond outer contour of shield cover, provided with back end compaction. Device is provided with fluid pump device. Force hose of pump is outputted from upward portion beyond outer contour of shield cover. Device for transporting extracted soil from face is made in form of suck-in hose connected to pump device and to lower portion of ring space beyond rotor working implement.

EFFECT: lower transverse loads on guiding pipeline.

2 cl, 1 dwg

FIELD: mining industry.

SUBSTANCE: device has two asynchronous electric engines, connected via reducers to drive sprockets of continuous traction chain, provided with plane carriages with their possible displacement along the guide, and hydraulic cylinders for displacing guide on pit-face. To windings of stators of first and second electric engines connected respectively are outputs of first and second frequency converters, inputs of which are connected to power grid and control inputs of which are connected respectively to outputs of first and second frequency adjusters. To frequency adjusters also connected are inputs of load detectors, to outputs of which load balancing block is connected, outputs of which are connected to inputs of first frequency adjuster. To inputs of both frequency adjusters output of load adjuster is connected, inputs of which are connected to load-setting block and load sensor for second engine. To output of second frequency converter connected are input of control block, other input of which is connected to signal block of base plant, and stator winding of third asynchronous engine, which via mechanical link is connected to first and second hydraulic pumps, having constant working volumes. Output of first hydraulic pump is connected to force hydro-main and input of second preventing hydraulic valve and to first inputs of two-position hydraulic distributors with electromagnetic control, to electromagnets of which outputs of control block are connected. Second inputs of two-positional hydraulic distributors with electromagnetic control are connected to control chambers of hydro-controlled two-positional hydro-distributors, which are part of hydro-blocks. Outputs of hydro-controlled two-positional distributors are connected to opposite hollows of volumetric dosing device of each hydro-block, and their inputs are connected respectively to outputs of hydro-distributors for controlling hydro-cylinder for moving the guide on pit-face, inputs of each of which are connected to force and drain hydro-mains, and outputs are connected to piston and rod hollows of appropriate hydro-cylinder.

EFFECT: higher efficiency.

1 dwg

FIELD: mining industry.

SUBSTANCE: method includes erection of wall, prior reinforcement of rock massif along extraction track by drilling longitudinal and slanting wells and forcing reinforcing cementing solutions into these wells, destruction and cleaning of rocks under protection of cementing cover, erection of permanent support, following reinforcement of contour-adjacent massif by cementation solutions through wells, drilled perpendicularly to mine axis. Draining wells are additionally drilled with delay through cementing layer having length greater than thickness of reinforced rocks zone, to form a draining layer around reinforced cover.

EFFECT: higher effectiveness.

2 cl, 4 dwg

FIELD: mining industry.

SUBSTANCE: rotor is made in form of cylindrical body, on working surface of which cutter holders are radially placed, each of which is made in form of shaft, freely placed in cylindrical groove of rotor body. Along whole length of each cutter holder cutting elements are mounted with hard-alloy inserts. Between cutter holders cutting elements are placed, made in form of rectangular prisms with hard-alloy inserts.

EFFECT: higher efficiency.

3 dwg

Tunnel // 2250962

FIELD: building, particularly underground structures erected in difficult mining and geological conditions, namely in soft watered ground bedded under tunnel scoop and forming tunnel base.

SUBSTANCE: tunnel has composite lining including hollow metal members driven in ground and forming screen, load-bearing frames and grouting concrete. Metal members are connected one to another through interlocks. At least some of metal members have rigidity varying along length thereof and increasing in direction opposite to metal member driving direction. Metal members have constant outer diameters.

EFFECT: increased tunnel reliability and operational safety due to prevention of original ground deformation during tunnel building and operation; reduced ground settlement at base of tunnel built under motor road without traffic interruption, reduced building time, power and labor inputs, material consumption due to optimal material distribution along driven member in accordance with load distribution among member parts.

24 cl, 11 dwg

FIELD: construction.

SUBSTANCE: method includes making a mini-tunnel by serial pressing through, in soil with concurrent feeding of special solution, at least two hollow concrete sections connected with pressing, each of which is made with end portions open at ends, one of which is made on outer side with ring-shaped groove open from end portion, wherein metallic ring is mounted projecting beyond section end, with thickness not greater than groove depth, hollow of which together with inner hollow of end portion of section forms shelf-like cone, and other end portion of section is made stepped and narrowing towards end with forming of bushing portion with one shelf for ring of adjacent section cone and no less than with one shelf for ring compacting insert made of soft pressurizing gas and water impermeable material, tightly clinging by one side to surface of shelf, and by other - to inner surface of ring, while shelves of bushing portion are made within limits of section wall half thickness, which half is directed outwards. End portions of pipeline sections adjacent to mini-tunnel are made matching with adjacent mini-tunnel sections or transfer sections are used and/or inserts, while pipeline is connected to mini-tunnel after pressing through in soil and/or embankment of the last mini-tunnel section.

EFFECT: lower costs, higher reliability and durability.

8 cl, 16 dwg

FIELD: construction.

SUBSTANCE: method includes cleaning pipes and wells and further maintenance while providing for continuous draining of sewage by liquidating breakdowns, liquidating random obstructions, and also launching new areas of network into operation, while at least one constructed network area is driven though soil or body of existing embankment by, micro-tunneling by means of serial pressing through in soil with concurrent feeding of special solution, at least two hollow concrete sections connected with pressing, each of which is made with end portions open at ends, one of which is made on outer side with ring-shaped groove open from end portion, wherein metallic ring is mounted projecting beyond section end, with thickness not greater than groove depth, hollow of which together with inner hollow of end portion of section forms shelf-like cone, and other end portion of section is made stepped and narrowing towards end with forming of bushing portion with one shelf for ring of adjacent section cone and no less than with one shelf for ring compacting insert made of soft pressurizing gas and water impermeable material, tightly clinging by one side to surface of shelf, and by other - to inner surface of ring, while shelves of bushing portion are made within limits of section wall half thickness, which half is directed outwards. After pressing through all sections of reconstructed network portion free ends of end sections are connected to existing network.

EFFECT: higher reliability and durability, lower costs.

8 cl, 16 dwg

FIELD: construction.

SUBSTANCE: method includes continuous feeding of electric power having appropriate frequency and voltage to consumers due to maintenance operations, and also launching new areas of network into operation, while at least one of constructed network areas is driven in soil or in body of existing embankment by micro-tunneling by means of serial pressing in soil with concurrent feeding of special solution of at least two hollow concrete sections, connected to each other and to network with pressing, each section being made with open end portions, one of which is made on outer side with open circular groove at end portion, wherein metallic ring is mounted, projecting behind end piece, having thickness no greater than groove depth, hollow of which together with inner hollow of end portion of section forms shelf-like cone, and other end portion of section is made stepped and narrowing towards end with forming of bushing portion with one shelf for ring of adjacent section cone and no less, than with one shelf for ring compacting insert of soft pressurizing gas and water impermeable material, tightly clinging by one side to shelf surface, and by other side - to inner surface of ring, while shelves of bushing portion are made within limits of outward-directed half of thickness of section wall. After pressing through all sections of reconstructed network portion, free ends of end sections are attached to existing network.

EFFECT: lower laboriousness, lower costs, higher reliability and durability.

8 cl, 16 dwg

Tunnel // 2251610

FIELD: building, particularly underground structures built under difficult mining and geological conditions, namely in presence of soft watered grounds at tunnel base.

SUBSTANCE: tunnel comprises prefabricated lining including hollow metal members driven in ground and forming a screen, load-bearing frames and grouting concrete. Metal members are joined by means of locking means. At least some metal members driven in ground have constant outer diameters. At least part of above metal members are composed of sections having different lengths. Lengths of the metal members decrease in direction opposite to the driving direction.

EFFECT: increased reliability and operational safety due to prevention of original ground surface settlement during tunnel building and operation; prevention of ground settlement during tunnel building under traffic road without traffic interruption, reduced time of tunnel building, labor and power inputs, material consumption due to optimal material distribution along driven member in correspondence with loading of its sections.

21 cl, 12 dwg