Method of repair of pipeline with insulation coating

FIELD: machine building.

SUBSTANCE: proposed method comprises contactless unearthing, removing damaged coating, pipe surface processing, applying new coating and burying repaired pipeline. Pipeline separate equal-length sections are unearthed while all process job time intervals are equal. Said removing damaged coating, pipe surface processing, and applying new coating are executed without contact between process equipment and pipeline surface and spark-forming mechanical contact of work tools.

EFFECT: repair without interrupting transfer of product, reduced repair interval.

1 dwg

 

The present invention relates to the field of pipeline construction and the execution of works on repair of the insulation coating on pipelines for various purposes, and can be applied to other process operations, such as insulation of welded joints, operations, quality control, etc.

Known methods of repair of pipelines (Rules of work with the repair of gas pipelines VSN 51-1-97, Moscow, 1997, section 3, p.13-20, more. 2)in which the work is carried out on the pipeline after its shutdown, blowdown, installation parallel (bypass) pipeline with a violation of the provisions of its location.

The main disadvantages of these methods are significant and estimate the costs of stopping the transportation of the product, construction site temporary piping, long term repair work. When performing work on the replacement of insulation used machines based on the pipeline that have scroobious tools (brushes, scrapers, ignorez) (Catalog of machines for the construction of pipelines. Eighth edition, Appoligized of the Moscow regional Council, 1990, p.61-70).

The closest in technical essence to the solution which is claimed, is a way to overhaul the master of the high gas pipeline replacement insulation coating (Rules of work with the repair of gas pipelines VSN 51-1-97, Moscow, 1997, more. 2, section III. p.60-65), which includes disclosure of the pipeline, the rise of the pipeline, clearing of old insulation, surface preparation and application of a new coating, pipe laying and backfilling.

This technical solution is adopted for the prototype.

The main disadvantages of this solution are the need off, blowing the repaired piping, installation of parallel (bypass) of the pipeline, the violation of the provisions of its location, the additional load of the pipeline during its ascent, which requires additional state of stress control tubes, the inability to apply in the winter insulating materials, which require positive temperature metal pipes.

All the above requires considerable time and money when performing repair work.

The task of the invention is to provide a method of repair of insulation coating without stopping the transportation of it product (gas, oil etc) and reducing time to repair.

This technical result is achieved in that in the method of repair of insulated coating of the pipeline, which includes contactless with pipe excavating the pipeline, removing damaged insulation coating, surface preparation pipeline the od of the application of the new insulation, the application of new coating, and the instillation of the repaired pipeline, which is characterized by the fact that excavating the pipeline carry out individual sections, each of the sections has the same length, and each technological operation - the same time, removing the damaged insulation coating, surface preparation of the pipeline under the application of the new insulation, the application of new coating, performed without contact equipment surface of the pipeline and sparkle-forming mechanical contact of the working tools.

Since the unearthing of the pipeline perform consistently, separate equal parts, and cleaning, preparation for application of the new insulation and the application of new coating, perform process sequentially on each plot, and the total length of the plots corresponds to the conditions, which ensure equality of time of completion of surface preparation for the application of new coating, on the last section with the end of time gaining the strength of a new coating on the first segment.

Repair of insulated coating of the pipeline in areas of residual ground poles is performed in the above sequence. Figure 1 shows a diagram of the sequence you is filling up works by way of repair of insulated coating of the pipeline, which is claimed.

The process of performing major repairs individual local areas MG is carried out with a pressure drop not less than 10% of the maximum working pressure for the last year of operation that meets the requirements of the standard documentation on safety.

The peculiarity of this method is the use of equipment that does not create stress on the pipe surface and has no sparkle-forming mechanical contact working tools when cleaning, surface preparation and pipework.

First, it performs excavation work on the disclosure section of the pipeline and the formation of the trench with the use of excavator and bulldozer equipment, provided the proximity of the cutting edges at a distance not closer than 0.5 m to the generatrix of the pipe on all sides. The spoil is removed by hand kapisanan at a distance of not less than 0.1 m of the pipe without the use of percussion instruments, and the final purification is fire resistant, for example, water-jet tool.

Earthworks are carried out by separate sections. Length of the plot is determined for each pipe provided to prevent plastic deformation of the tube as a two-way fixed-fixed beams, takes into account the dependence on the diameter of the pipe, the thickness is in the walls, the type of soils, the pressure of the product in the pipe and other parameters.

Between two adjacent pits remains unpaved bearing 1.

A sequential workflow is caused by the need for "hard" save the previous position of the pipeline and to completely eliminate the appearance of additional longitudinal-transverse stresses in the body of the pipe.

In connection with the prohibition of processing the surface of the existing pipeline equipment with sparkle-forming mechanical contact working tools, as well as the mechanical load on the pipe surface, the one possible means of surface preparation methods are using intrinsically safe technology (see information technology monthly Ukraine "Market instalacji", No. 2, 2000, p.18-19).

The operation is removal of the old coating by using intrinsically safe, for example, high-pressure manual water jet equipment 2, which may be a mobile unit (crane, pipelayer), equipped with a boom on which you installed the pump unit ("WOMA", Germany) with a feed hose and the work nozzle, mounted on the boom.

After the process of removing the old insulation on the first separate area and it begins the process of surface preparation is of Truboprovod under the application of a new coating, for example, vodoistochnaya processing 3 equipment, which may be a mobile unit (crane, pipelayer), equipped with a boom that has sandblasting (DSK-250 Russia) with the feed hose and the work nozzle, mounted on the shaft, and removing the old insulation perform in the next section.

After completion of surface preparation on the first separate area and it begins the process of applying the new coating of the pipeline 4 equipment, which may be a mobile unit (crane, pipelayer), equipped with a boom that has installation airless coating ("WIWA" Germany) or similar to the supply hose and the work nozzle, mounted on the boom.

The second section begins the process of preparing the surface of the pipeline under the application of new coating, and removing the old insulation perform in the next section.

Special attention should be paid to the materials and equipment for applying the new coating. The perform insulation work on active pipeline and General operating conditions of the pipeline, at the present time, cause application of insulating materials, which can be applied without contactor is affected with pipe insulation machines which create mechanical stress on the surface of the pipeline. This is, basically, polyurethane coatings, such as "Protegol UR-Coating 32-55", "Copon Hycote 165-Varplex", "polyurethane coating T.U.", etc. that can be applied by airless application.

After completion of the process of applying a new coating of the pipeline on the first separate area and it begins the process of gaining strength (polymerization) of the new coating, the second part is applying a new coating of the pipeline, the third section begins the process of preparing the surface of the pipeline under the application of new coating, and removing the old insulation perform on the last section. To save the General rhythm of the technological process, prevent downtime, and as a result, to save time and money is important and necessary so that the total length of individual sections was calculated depending on the time of gaining new strength of the coating, while the work is finished surface preparation for the application of new coating, on the last section coincided with the end of time gaining the strength of a new coating on the first segment. Subsequently the tamping of the soil under the pipe and complete the backfilling of the trench 5 with the layer-by-layer filling of the soil and its seal. Repair of insulated coating of the pipeline in areas of residual g is antovich supports is performed in the above sequence. Finally run earthwork reclamation works, relocation of equipment to the next prepared the sections and the order of technological operations is repeated.

Thus, the proposed solution provides a repair coating without stopping the transportation of it product (gas, oil etc) and reducing time to repair.

Repair works on the active pipe determines the ability of doing work in the winter period due to the positive surface temperature of the pipe, the heated product, which is exported.

The proposed solution is embodied in the overhaul of MG "Vasevichi Valley III thread"MG "Yelets-Kremenchuk-Kryvyi Rih.

The method of repair of insulated coating of the pipeline, which includes contactless with pipe excavating the pipeline, removing damaged insulation coating, surface preparation of the pipeline under the application of the new insulation, the application of new coating, and the instillation of the repaired pipeline, characterized in that the digging of the pipeline carry out individual sections, each of the sections has the same length, and each process step is the same time, removed the e damaged insulation coating, surface preparation of the pipeline under the application of the new insulation, the application of new coating, performed without contact equipment surface of the pipeline and sparkle-forming mechanical contact of the working tools.



 

Same patents:

FIELD: machine building.

SUBSTANCE: before insertion of sleeve inside pipe bandage of fibrous material is fixed on internal surface of pipe by means of metal band impregnated with solidificated binding. There is formed an open circular section of the bandage. A tube-like sleeve of fibrous material is inserted inside the pipe. The sleeve is impregnated with solidificated binding and is enclosed into a flexible casing of polymer material. Further, the sleeve is reversed and moved inside the pipe, is straightened and pressed to internal surface of the pipe due to pressure of water on internal surface of an inverted sleeve. The bandage is solidificated simultaneously with the sleeve.

EFFECT: reduced amount of air in space between internal surface of pipe and sleeve inserted into pipe; elimination of working fluid leakage between internal surface of pipe and external surface of solidificated sleeve coating.

4 dwg

FIELD: machine building.

SUBSTANCE: procedure for application of protective enamel on internal surface of pipe consists in preliminary surface cleaning, in application of enamel and in drying. Also, initially pipe is heated and dried by blowing air of t=+40÷80°C through it. Further, internal surface of the pipe is cleaned by an abrasive-jet method for elimination of impurities and obtaining roughness as high, as RZ 40, where upon dust is removed by air blowing. There are applied not less, than two layers of enamel. Each wet layer of enamel has thickness, as high as 90÷180 mcm. Each enamel layer is dried at flow rate 2÷8 m/sec by blowing air of temperature +15÷25°C through pipe during not less, than 3 hours. Interval between application of layers should last no more, than 24 hours. Here is also disclosed the procedure for control over application of a protective cover on internal surface of the pipe. A sample in form of a cylinder of length equal to 0.5-1.5 diametre of a pipe is cut out from the pipe with protective enamel applied on it as a coating. The sample is subjected to compression in a radial direction till coating fractures. Quality of protective coating is determined by a value of deformation of the sample at the moment of detection of this coating fracture.

EFFECT: simplified process, raised efficiency, reduced power input and upgraded quality of coating.

2 cl

FIELD: machine building.

SUBSTANCE: installation for trenchless repair of pipelines consists of drum with cloth shell wound on it, of bath for impregnation of this shell with polymer composition, of hollow cantilever for laying cloth shell into film sleeve, and of pneumatic-mechanical gate with pressure gauges and valves arranged on it. The bath is equipped with freely rotating rollers and has a cover with an opening hatch for refilling polymer composition and with thermo-electric heaters for polymer composition controlled heating. In the cover from the side of the bath there are made two slits opposite to each other for input and output of the cloth shell. The bath, the cover and its hatch have heat insulation coating on external side.

EFFECT: impregnation of cloth shells with polymer composition at low ambient temperature and accelerated impregnation, increased efficiency of installation for trenchless repair of pipelines.

3 dwg

FIELD: machine building.

SUBSTANCE: input consists of band of fireproof material arranged on plastic tube and of a collar to fix band of fireproof material on plastic tube. The band of fireproof material and the collar only partially envelopes the plastic tube.

EFFECT: compact positioning of wall or ceiling input.

13 cl, 8 dwg

FIELD: construction.

SUBSTANCE: threaded joint for pipes (the first version) comprises a rod (100) and a body (200) elements. The rod element has a thread adapted for matching with the body element. The thread shape and the rod and body elements shape are determined by the thread profile, where the thread surface has a coating. This coating contains the first layer (24) with high friction and antiscoring properties, applied onto the whole surface of the rod element (100), and the second layer (25) with low friction properties applied into separate parts of the surface of either only the rod element, or only the body element. The threaded joint for pipes (the second version) comprises a rod (100) and a body (200) elements. The rod element has a thread adapted for matching with the body element. The thread shape and the rod and body elements shape are determined by the thread profile, where the thread surface has a coating. This coating contains the first layer (24) with high friction and antiscoring properties, applied onto the whole surface of the body element (200), and the second layer (25) with low friction properties applied onto separate parts of the surface of either only the rod element, or only the body element.

EFFECT: increased efficiency of the structure operation, its resistance to corrosion.

48 cl, 12 dwg

FIELD: machine building.

SUBSTANCE: anti-corrosion coating is applied to inner pipe surface, bushes made from corrosion-resistant metal and having on outer surface the sealing layers in the form of elastic coating are installed inside ends of pipe with covering some part of coating and bushes are fixed by their expansion till they tightly touch inner pipe surface. Sealing layer can be made from elastic polymer material.

EFFECT: reducing labour intensity of production and reducing the cost of products.

6 cl, 3 dwg

FIELD: machine building.

SUBSTANCE: first, before welding end of pipeline, heat-shrinkage clutch-bushing is positioned on pipeline close to joint. Upon joint welding, insulated surface is cleaned with metal brushes and dried from moisture. Prime coating - "liquid" primer and mastic band corresponding to coating with 80…90 degrees C temperature of mastic material softening are applied on this surface. Further, the heat-shrinkage clutch-bushing is pushed to a zone of a welded joint symmetrically to it and is heated to temperature 110…120 degrees C. Simultaneously, layers of the mastic band are heated and melted through the heat-shrinkage clutch-bushing ensuring pressure onto melted mastic of the mastic band and filling interstices with it in a zone of welding joint strengthening (hemi-spherical zones) and places of transition to base coating and overlapped layers of the mastic band. Insulating coating of the welded joint of the pipeline contains prime coating- "liquid" primer, the mastic band made either in from of a polymer-bitumen with base out of polyvinylchloride with mastic of 80…90 degr. C of softening, or in form of a base-less material consisting of polymer-bitumen mastic with softening temperature 80-90 degrees C and glass mesh. Also insulating coating consists of the heat-shrinkage clutch enveloping the pipeline and made in form of a solid bushing out of a sheet of light- and heat stabilised one-layer polyethylene modified by radiation-chemical method. The clutch is installed on the pipeline before pipeline joint welding and can travel along axis of the pipeline.

EFFECT: raised efficiency of anti-corrosion protection due to increased resistance of insulation coating.

2 cl, 2 dwg

FIELD: machine building.

SUBSTANCE: according to procedure surface of isolated coupling is prepared and rolled adhesive material is applied on prepared surface. Material is heated to softening; a section of thermo-contracting polymer band is placed on a softened layer. Ends of the band are connected with overlap, thereby forming a collar. A locking plate is put on the point of ends connection; further, the collar is thermo-contracted.

EFFECT: raised adhesion of insulating collar to surface of coupling and increased period between repair operations for re-insulating coupling of pipeline.

11 cl

FIELD: oil and gas production.

SUBSTANCE: method for manufacturing a tubing string involves coating formation on its internal surface. The coating represents at least one polyurethane coating layer containing ureal groups with their mass fraction in the coating makes 6 to 14%. Total coating thickness is within the range 10 to 500 microns.

EFFECT: increased service durability of the tubing string ensure by more efficient deposit protection and abrasive, hydroabrasive and corrosive wear.

9 cl, 5 dwg

FIELD: machine building.

SUBSTANCE: procedure for application of coating on internal surface of pipeline consists in inserting tube-shaped sleeve out of fibre material inside pipeline. The sleeve is impregnated with binding and enclosed into a flexible shell. Further, the sleeve is turned out, propelled inside the pipeline, straightened and pressed to internal surface of the pipeline under simultaneous effect of a water column on internal surface of the turned out sleeve and pneumatic pulses pneumatically communicated with a compressor. Then the sleeve is solidificated. Variations of value and frequency of pulses is achieved by changing air pressure at the outlet from the compressor. Also a pulse generator is placed inside the pipeline before the sleeve, as far, as it propels inside the pipeline, so, that exhaust openings in the case of the generator are arranged at acute angle to generator axis in the direction of sleeve motion. In air medium around the generator there is periodically generated circular series of pulses.

EFFECT: prevention of occupational injuries.

1 dwg

FIELD: construction.

SUBSTANCE: device comprises drive and rod provided with a set of flexible collars that are in a contact with the inner surface of the pipe. Between the collars is the vessel. The brush is mounted downstream of the batching collar. The vessel that is open from above is filled with a polymeric material to be applied to the pipe, and the device is set in the pipe. The device moves along the pipe and rotates simultaneously. The polymeric coating is made preliminary by the batching collar, and the brush downstream of the batching collar provides finishing leveling of the coating in thickness.

EFFECT: expanded functional capabilities.

3 dwg

FIELD: construction engineering.

SUBSTANCE: invention is used for protection of pipelines from corrosion. Proposed pipe with inner plastic lining contains protective bushings fitted on ends and secured with pipe. Outer diameter of protective bushing is less than inner diameter of pipe by half of thickness of inner plastic lining. Aluminum foil in multilayers is loosely wound on free end of outer surface of protective bushing.

EFFECT: reduced labor in manufacture of pipes.

2 cl, 1 dwg

FIELD: pipeline transport.

SUBSTANCE: pipe comprises protecting bushings concentrically mounted at the ends of the pipe. The outer diameter of the protecting bushing is less than that of the pipe by half thickness of the inner plastic shell. The free end of the outer surface of the protecting bushing is provided with high-temperature filler, e.g. the mixture of chamotte sand with liquid glass or aluminum foil with high-temperature filler. During welding the end of the pipe, the high-temperature filler protects the plastic shell.

EFFECT: enhanced reliability.

1 dwg

FIELD: construction.

SUBSTANCE: method comprises turning the hose made of fiber material impregnated with a solidified binder enclosed in the flexible polymeric shell inside out, moving the hose inside the pipeline, expanding the hose, and pressing it to the inner side of the pipeline under the action of water pressure to the inner side of the turned out hose. The water column is simultaneously affected by the pulses generated by the generator-source of the hydraulic impacts submerged in the water. The amplitude and frequency of the hydraulic impacts change by changing the air pressure at the outlet of the compressor connected with the pulse generator.

EFFECT: simplified method.

1 dwg

FIELD: mechanical engineering.

SUBSTANCE: invention relates to reprocessing of polymeric materials, namely, to lining of metal articles with flanges, for instance, cylindrical mixing reactors. Proposed method consists of two steps, with lining of cylindrical part of article at first step, and lining of flange end faces at second step. At first step alternating cylindrical, confusor and diffuser members, preliminarily treated by sealing compound from outer surface, are driven into inner space of article. Said members are press-fitted at two sides and are subjected to heat treatment. At second step, free inner surface of metal article and outer surface of two cylindrical members are coated with sealing compound, and cylindrical members are driven into end faces of article to thrust against preliminarily formed lining and flush with surface of flanges which are coated also with sealing compound and subjected to heat treatment at press-fitting from two sides.

EFFECT: provision of high-strength adhesion between lining and inner surface of metal article.

1 dwg

FIELD: pipeline transport.

SUBSTANCE: device comprises trestle, bath for covering material, device for rotating the pipe, batching-distributing device. The device comprises distributing roller with flexible covering, crushing baffle that embraces the pipe to be insulated in the direction of rotation by 1/4-1/3 of the length of its periphery and has pressing strip and weight. The batching-crushing device has rod whose end is provided with the adjustable rectangular batching opening whose length is equal to the length of the batching-distributing device for applying the outer insulation. The distributing roller underlies the batching opening and is connected with the batching openings through the guiding chute. The crushing baffle is mounted on the side of the rod and is provided with the pressing strip and weight.

EFFECT: expanded functional capabilities.

8 cl, 3 dwg

FIELD: pipeline engineering.

SUBSTANCE: method comprises assembling combined hose that has hose made of reinforcing material and outer film hose. The reinforcing material of the hose is impregnated in two stages. First, the binder is supplied from the face of the hose until the plug inside its inner space is formed, and, second, the inner space of the film hose is evacuated in the region of the plug from the side opposite to the roller device through which combined hose with the binder passes.

EFFECT: enhanced quality of impregnation of the reinforcing material.

2 ex

FIELD: pipeline transport.

SUBSTANCE: method comprises removing the exhaust insulation, applying the 120-μm priming coat, and hating the pipe up to 50°C in two stages. In the first stage, the pipe is heated up to 20°C by means of open flame, and, in the second stage, it is heated up to 50°C by means of induction heating. The heat-shrinking insulation belt is wound on the priming coat, with preliminary heating of the adhesive layer of the belt up to 60°C by hot air. The insulating coating is then heated up to 100°C for heat shrinking of the polymeric base.

EFFECT: improved corrosion protection.

5 cl, 1 dwg

FIELD: pipeline engineering.

SUBSTANCE: method comprises forming soft three-layer hose by setting the intermediate layer made of a reinforcing material impregnated with a binder between the inner and outer pressure-tight hoses made of synthetic film materials. In the stage of preparing the binder, 0.25-1.0% of organosilicon liquid is added to the binder with a boiling temperature above 200°C. The three-layer hose is set in the pipeline and pressed to the inner side of the pipeline with subsequent solidification of the binder and removing the inner pressure-tight hose. Before removing, the space of the pressure-tight hose is evacuated down to 0.2-0.8 atm.

EFFECT: improved quality of pipeline coating.

1 cl, 3 ex

FIELD: construction of conveyance pipelines used in sanitary engineering systems.

SUBSTANCE: flexible plastic extrusion profile has plastic sleeve which gives the impression of painting and/or metal plating. Method involves applying onto outer side of flexible plastic extrusion profile, in particular, plastic sleeve a system of layers including internal layer giving the impression of thin metal layer, and external at least partly transparent protective covering layer. Described in Specification are methods of applying said layers, their parameters and properties.

EFFECT: wider range of technical means.

39 cl, 4 dwg