Multiple drilling rig with simplified layout of assembly

FIELD: oil and gas production.

SUBSTANCE: multiple drilling rig consists of units made in form of modules including frames with process equipment, unit of well cementing, unit of circulation system, pump unit with drill pumps, unit of electrical equipment, compressor unit, and also derrick-hoist unit and receive bridge with drilling pipes mounted on guides for horizontal transfer. The rig is composed of two rows on 4 parallel guides. Also, the units-modules are connected with a system of communication and can change their relative position. The receiving bridge with drilling pipes is set in space between rows and is connected with the derrick-hoist unit. The latter is mounted on internal guides and can be retracted beyond overall line of the assembly formed with units-modules. This layout reduces area for drilling rig maintenance and communications between units-modules.

EFFECT: installation of additional shelters for heating working areas; reduced heat losses from shelter surface; raised efficiency of rig operation.

5 cl, 5 dwg

 

The invention relates to oil and gas equipment, namely, drilling rigs, and is intended for pad drilling exploration and production oil and gas wells.

The famous "Repair drilling unit (Patent RF №2320842, the priority date of 29.06.2006, the patent owner: limited liability Company "Licensed Company "KUNGUR"), the Equipment placed on the platform, which is installed on the rail guides. The unit is designed for servicing oil and gas wells, especially in the specific conditions of the cluster development wells. However, the design of unit not provided by the application of additional units to expand its capabilities for use of the unit when Bush exploration and production of oil and gas wells.

For pad drilling exploration and production oil and gas wells of Russian and foreign manufacturers produce special well drilling rigs, which allows multiple drilling (drilling multiple wells on one rig floor when moving complex rig special-tables-guides or special basis).

The famous "Rig" (Patent of RF # 24231, the priority date of 05.10.2001, the patent: "the Engineer is Nero-economic innovation center Open joint stock company "Surgutneftegas"), contains blocks-modules with the drilling equipment installed echelon fastened together quick couplings and connected through a passage from the work site until the end of the module. The disadvantage of this arrangement is the complexity of the operation for the replacement of this module in case of its failure, as well as installation of additional modules.

Other well known drilling rigs also contain blocks-modules with the drilling equipment: cable hoist block, block circulation system, unit drilling pumps, cementing unit, compressor unit and the unit of electrical equipment that are mounted on a common guide with the possibility of lateral movement on two rails. While the equipment units of the receiving bridge with shelving for working with pipes located on the side generally perpendicular to the direction of movement of the drilling rig, which when moving train to another well blocks placed at the side of the train have to be removed.

A similar design has, for example, well drilling rig BU 5000/320 EUK-I ("a New generation of drilling rigs Uralmash plant in Western Siberia" Vggallery and other reference book. 2002).

The location of blocks of well drilling rig on two General guides to move has su is the natural enemy weaknesses. The process equipment in the blocks sequentially in a single line (echelon) excludes the possibility of installation in the immediate vicinity of the wellhead, which degrades the performance of technological operations (for example, the cementing unit is located at the end of the echelon part of the well drilling rig), makes it impossible for the extra blocks, which reduces the efficiency of operation of the installation.

Partially the drawbacks are solved in the famous "Well drill rig" (Patent of RF # 83280, priority date 23.10.2008, the patentee "closed joint stock company "Uralmekhanooborudovanie", EN). Well drilling rig includes cable hoist block, block circulation system, block mud pump, compressor unit, the unit of electrical equipment, cementing unit, which are arranged in echelon, with each unit made in the form of a module that is installed on the guide beams can travel on them. For more efficient operations well-drilling installation design allows you to install additional units. This analog is the closest to the problem at hand and therefore taken as the prototype of the claimed invention.

The disadvantage of the prototype is that when installing additional blocks well drilling set the WHC increases significantly in length (100 meters or more), that increases the length of the linking technological and electrical communications, increases the energy cost of pumping solutions and space heating, complicates the maintenance of the rig. Moreover, the arrangement of blocks echelon leads to a significant increase in the area for well drilling rig, consuming additional space for its placement and operation that increases the operating costs of the installation and makes it ineffective.

The technical objective of the claimed invention is to increase the efficiency of operation of well drilling rig in the construction of wells in remote Northern regions.

Technical result is achieved by the claimed fundamentally new simplified layout of well drilling rig, which contains blocks made in the form of modules, consisting of frames with technological equipment: block cementing, block circulating system, the pump block with drilling pumps, power equipment, compressor unit, as well as cable hoist unit and the receiving bridge with drilling pipes that are installed on the rails with the possibility of lateral movement, according to the invention the installation are arranged in two rows of four parallel rails, p. and this blocks the modules connected to the communication system and is installed with the possibility of changing their mutual provisions and receiving bridge with drilling pipes made with shelter and installed in the space between the rows, and the receiving bridge is connected with a cable hoist unit, which is installed on the inner rails with the nomination for the overall line layout formed by the blocks-modules, in addition, the receiving bridge with drilling pipes are also installed on the inner rails with the possibility of lateral movement or can be mounted on the frame units and to connect with them, in addition, the receiving bridge with drilling pipes provided with one or more racks, made in the form of units with shelter, and the racks can to be installed in any number of layout with the possibility of connecting them with the foster bridge.

The invention is illustrated by drawings.

Figure 1 shows a simplified schematic layout of well drilling rig.

Figure 2 shows a side view of the layout of well drilling rig.

Figure 3 shows a top view layout of well drilling rig.

Figure 4 shows the site for the well drilling rig with a simplified layout (declared).

Figure 5 shows a site for the well drilling rig (prototype).

The claimed invention "Well drilling rig with a simplified layout" (IG, 2), which contains blocks made in the form of modules, consisting of frames with technological equipment (figure 3): the unit of cementing 1, block circulation system 2, the pump block with drill pumps 3, unit 4 electrical, compressor block 5, as well as cable hoist unit 6 and the receiving bridge with drilling pipe 7, the rack 8, mounted on the rails with the possibility of lateral movement. The installation is arranged in two series: series a and series B in four parallel rails 9, 10, 11, 12. With this arrangement, the guide is formed of a Central pair of rails 10. 11. In each row blocks-modules are interconnected helical rods and axes, and also connected to the communications system and is installed with the possibility of changing their relative position.

The receiving bridge with drilling pipe 7 is made with a cover (not shown) and installed in the space between the rows a, B on the guides 10, 11, when receiving the axle is connected with a cable hoist unit 6, which is also mounted on the guides 10, 11 nominations for the overall line layout In the generated blocks-modules. The receiving bridge with drilling pipes can be installed on the surface of the guides 10, 11 with the possibility of lateral movement or on the surface of the RAM block-modules, between which it is installed. Receiving the OST drill pipe provided with one or more racks 8, made in the form of units. Racks can be installed in any number of layout, this should be made a connection of the racks with the foster bridge. All blocks with technological equipment, including receiving bridge and racks to him, have shelter from unwanted exposure to climatic conditions.

The job description

In the well construction cycle consists of preparatory work, the installation of the drilling rig, pre-drilling, the drilling process, the strengthening of the well casing, the strengthening of well cementing.

Before installation, well drilling rig prepares courts, Playground shown conventionally in figure 4, and for comparison, figure 5 shows the relative space of the prototype. On the ground (figure 4) establish parallel to each other 4 guides 9, 10, 11, 12 (figure 3). Then make installation design well drilling rig. Blocks-modules, consisting of frames with technological equipment, placed in two rows a And B on the guides 9, 10, 11, 12 in accordance with their functional purpose. Cable hoist block is placed between two rows of blocks of the modules on the Central pair of rails 10, 11. For cable hoist unit sets the receiving bridge with drilling pipes, while near the receiving bridge in any number of link sets CTE is lazhi. Followed by the connection of the racks with the foster bridge and establish shelter 13 (2) on the receiver bridge and shelves.

After installation of all blocks of well drilling rig on the shelves and receiving bridge stack drill pipe to supply them directly on the drilling floor. Drilling produces a lowering of the drilling tool on a drill string with a simultaneous flow of drilling fluid along the contour of its circulation. After drilling the first well drilling string is removed from the wells are dismantled on candles (folded pairs of drill pipe) and installed on the rig floor. On the shelves and receiving bridge place casing pipe for lowering into the borehole. Casing serves on the drilling floor, where they rolled and column lowered into a drilled well. The annulus between casing and borehole wall concreted using equipment unit cementing. Having finished cementing, well drilling rig moves within the wells four guides from hole to hole along with the technological and electrical equipment located on the blocks module without disassembly of all units, including the receiving bridge and pipe racks. In the prototype when moving the drilling rig to the next SLE is Gina have to dismantle the block-modules and pipe racks, which are located on the sides of the train on additional guides.

This placement of the blocks well drilling rig provides the reduction of communication to 30%, the reduction in the area to service the rig up to 40% (figure 4, 5) and reduce heat loss from the surface of a cover of the entire drilling system up to 30%. In addition covered and installed heating of work areas receiving bridge with shelving that allows you to increase the mechanization of working with pipes, and to improve the performance and security of these works, to ensure ease of maintenance and repair unit installation. Decreased distance from the installation to the barn, which increased the efficiency of the process of removing drill cuttings from the barn.

The use of declared well drilling rig with a simplified layout:

- reduced footprint and size of the drilling rig service, which reduced the costs of producing wells;

- decreased the time needed for shifting the equipment from hole to hole;

- optimized the location of technological equipment of the drilling rig and improved quality of work;

- created a favorable climate pipes and drilling tool, see who was the opportunity to automate the execution of these works, therefore enhancing the quality and productivity of work;

- reduced heat loss to the environment by optimizing geometric forms well drilling rig.

Stated well drilling rig with a simplified layout in "two rows" instead of known composition "echelon" can improve the safety and productivity of the staff, to reduce the number of "dismissed from the labor army days" (downtime)associated with adverse climatic conditions, to improve the working conditions of personnel during the operations, thereby enhancing the efficiency of operation of well drilling rig when Bush exploration and production of oil and gas wells, particularly in remote Northern regions.

1. Well drilling rig with a simplified circuit layout containing blocks, made in the form of modules, consisting of frames with technological equipment, the unit cementing, block circulating system, the pump block with drilling pumps, power equipment, compressor unit, as well as cable hoist unit and the receiving bridge with drilling pipes that are installed on the rails with the possibility of lateral movement, characterized in that the installation are arranged in two rows of four parallel what's guides, when this blocks the modules connected to the communication system and is installed with the possibility of changing their relative position, and the receiving bridge with drilling pipes installed in the space between the rows, while the receiving bridge is connected with a cable hoist unit, which is installed on the inner rails with the nomination for the overall line layout formed by blocks of modules.

2. Well drilling rig according to claim 1, characterized in that the receiving bridge with drilling pipe is installed on the inner rails with the possibility of lateral movement.

3. Well drilling rig according to claim 1, characterized in that the receiving bridge with drilling pipes installed on the frame units and connected them with the possibility of lateral movement.

4. Well drilling rig according to claim 1, characterized in that the receiving bridge with a drill pipe provided with a rack, made in the form of units with shelter, and racks can be several, and they are installed in any number of layout with the possibility of connecting them with the foster bridge.

5. Well drilling rig according to claim 1, characterized in that the receiving bridge with drilling pipes made with shelter.



 

Same patents:

FIELD: mining.

SUBSTANCE: drill rig is frameless and comprises the first manipulator link and the second manipulator link, between which there is a connecting accessory that provides for manipulator links movement relative to each other. A support at a rock is connected to the connecting accessory for resting against the rock after rough positioning of the drilling line near the line of blast holes. Accurate positioning of the drilling rig along with the direction of the blast holes line is arranged by means of joints available in the connecting accessory. Positioning onto the blast holes is carried out by rotation of the second manipulator link along the arched trajectory and by rotation of a drilling unit towards the rock to be drilled.

EFFECT: accurate manipulator positioning.

11 cl, 8 dwg

FIELD: construction.

SUBSTANCE: jacket for a perforator moving along a guide in a longitudinal direction attached to the perforator guide on its two sides and making, together with the guide, a substantially closed space, where there is a perforator and at least the main part of a drilling rod located outside a well. At least a part of the sound-absorbing jacket is formed of two shells, i.e. an internal shell located in an external shell and attached to it to form substantially a single stable structure and a space that contains air or other gas or a gaseous mixture.

EFFECT: invention ensures stiffness and lightness of the jacket structure, improved sound-absorbing capacity.

21 cl, 4 dwg

FIELD: construction.

SUBSTANCE: mobile drilling rig comprises a tower with folding sections, a lifted sectional folding base, modules of the main blocks on a transport base, a power unit, variable-frequency electric drives of the main mechanisms. Easily transportable quick-assembly sectional tower is arranged with an open front face, with inbuilt upper drive to work with drilling pipe stands of 24-25 m nominal length. The rig comprises a universal lifted base, which is raised into a working condition with the help of hydraulic cylinders to the height of up to 10 m, with the mechanism used to move a tower-hoist unit of an industrial drilling rig in the area of a well cluster with the help of the electric drive of load trolleys, moving along a rail track, a variable-frequency AC electric drive with a digital control system for the main equipment of a mobile drilling rig and a soft start device at electric drives of auxiliary mechanisms.

EFFECT: high power efficiency and erecting capacity, higher safety of drilling works and major overhaul of wells.

20 dwg

FIELD: oil and gas production.

SUBSTANCE: axial line of driven tunnel is determined with, for example, curve fitting. Data on location of drill platform on axial line of the tunnel are transmitted to the control panel; navigation plane of the blast holes placement layout is arranged on axial line of the tunnel. The initial point of set of the blast holes is positioned on the axial line of the tunnel considering length (L) of the blast holes set. Additionally, the final point of the blast holes set is arranged at distance corresponding to length of blast holes set from the initial point; the coordinate system of blast holes placement layout is directed to facilitate one of its axes running from the initial point to the final point. Finally, various systems of coordinates are utilised.

EFFECT: new and improved procedure for directing layout of blast holes placement in curvilinear tunnel, also development of soft ware for implementation of procedure and drill rig.

19 cl, 8 dwg

FIELD: oil and gas production.

SUBSTANCE: device consists of feeding girder, one end of which corresponds to drill end, of case for sound absorbing, enveloping feeding girder, perforator and part of drill rod, of first protective part, stationary arranged on drill end of feeding girder, as end of case for sound damping, and of second protective part travelling in lengthwise direction relative to feeding girder. Protective parts have an orifice; the drill rod travels in this orifice during drilling; also, the drill rod is connected to perforator moving during drill operation on the feeding girder. The device is equipped with a tubular protective part, flexible at least in its lengthwise direction and positioned between orifices of the first and second protective parts; with its ends it is tightly attached to the first and second protective parts so, that it forms a closed space between the orifices of the first and second protective parts. Also, the device is equipped with a guide in lengthwise direction of the feeding girder. The second protective parts is connected to the guide and travels relative to it. There is a cylinder with a medium, operating under pressure between the first and the second protective parts to move protective part to the first protective part and away from it.

EFFECT: raised efficiency at sound damping.

9 cl, 3 dwg

FIELD: construction.

SUBSTANCE: system for well drilling comprises base, mast, injector of flexible pipe and starter tip mounted on the mast so that it may move along it. At the same time starter tip provides for transfer of rotation torque for connection and disconnection of string components and may be used to drill with composite pipes. At the same time starter tip may be used to prevent unwanted rotation of drilling string in process of drilling, using well engine with the help of rotary cartridge capable of blocking. Drilling method is also disclosed with application of proposed system.

EFFECT: improving drilling plant operation reliability.

19 cl, 7 dwg

FIELD: construction.

SUBSTANCE: invention relates to the field of construction engineering, in particular to drilling rigs, and may be used to drill wells in various soils. Installation comprises self-propelled chassis and suspended equipment, which consists of mast, carriage, rotator, stem, mechanism of stem displacement, mechanism of feeding, drilling tool, installation of braces, support bracket and casing equipment. Mast is made of two parts - lower main and upper movable, installed on carriage with the possibility to move carriage with upper part of mast along lower part of mast with the help of feed mechanism.

EFFECT: simplified design with reduction of dimensions, improved functioning of units.

2 cl, 2 dwg

FIELD: oil and gas production.

SUBSTANCE: configuration comprises design functional elements: a cable hoist, a hoist brake, an auxiliary hydromatic brake, an emergency hydroelectric drive, a hoisting tackle mounted on a base of self-propelled wheeled tote pivotally connected to an A-frame folding tower with a crown block. A configuration is supplied with a sloping ramp whereon there are mounted the tote, tower and wellhead platform provided with a barrier railing. The tower consists of two interpenetrations. Each structure of the tower consists of two sections, upper and lower, and is meshed. Between the upper sections of the tower, there is a stabbing board of a derrick man which is also provided with is executed with the barrier railing.

EFFECT: higher performance efficiency and enhancement of the unit.

2 cl, 2 tbl, 4 dwg

FIELD: oil-and-gas industry.

SUBSTANCE: method and arrangement of improved horizontal-inclined drilling assembly for well drilling through underground rocks formations using a drill pipe, includes the drill pipe or a drill string descending into the well and its later lifting up. The drilling assembly includes a power aggregate for its power supply, a support frame, which can move between in parallel to the rock and in perpendicular to the rock positions, and the support frame moving device. A rotor block and a carriage aimed to transfer rotation, axial and return towing (lifting) forces to the drill pipe. The drilling assembly aimed for wells drilling with use of the drilling pipe through underground rocks formations, with any angle relatively to the underground rocks, between in parallel to the rock and in perpendicular to the rock positions. The method includes the drilling pipe dislocation on the drilling assembly, the support frame movement in setting it in the required drilling angle, the rotor block and carriage movement till it have contact with the drilling pipe, transfer rotation, axial and return towing (lifting) force to the drill pipe and underground rocks formations drilling with the drilling pipe.

EFFECT: invention provides power increase for the rotation drive and easy transportation.

21 cl, 17 dwg

FIELD: oil-and-industry.

SUBSTANCE: aggregate contains vehicle track with stiffly connected on it frame with equipment, including tackle system mast, main one-drum and auxiliary hoists, mechanisms drives, operator cabin, back support, hydraulic jacks, height adjustable wellhead platform. The mast foundation hinge connected with mast's back support, around which the mast is rotating at its vertical (operating) position or descends into horizontal - transportation position. At that at the mast top part located force stretching elements, and the wellhead platform additionally equipped with front bars, which connecting it to the aggregate frame.

EFFECT: aggregate design simplification, the aggregate adjustment on the wellhead simplification, keeping its functionality at well deep boring, service and maintenance.

7 dwg

FIELD: oil and gas extractive industry.

SUBSTANCE: method includes use of device providing for manufacturability of assemblage of casing and drilling columns and concurrent drilling by two columns, provided with independent drives, and drilling, by casing column, of non-stable rock solids performed with frequency no greater than one calculated from formula

where Vmec - mechanical drilling speed, m/min, Fr - friction forces against rotation, Ften - friction forces against linear displacement, R - casing column radius, m, α - angle between vectors of directions of linear and rotating movements.

EFFECT: higher effectiveness, higher productiveness, higher reliability.

2 cl, 5 dwg, 1 ex

Drilling device // 2245982

FIELD: mining industry.

SUBSTANCE: device has slanting frame with lower rotation drive and localizer, clamps of drilling pipes, stacks for storing drilling pipes. Conveyor is mounted on slanted frame, having adjustable drive, while clamps of drilling pipes having elevator links are fixed to conveyor branches, as well as open localizers and upper drive-swivel, and stacks for storing drilling pipes are placed along movement of conveyor in its upper portion. Upper end of drilling column is placed in well pipeline. At the end of stacks for storing drilling pipes a vehicle is placed with clamps for pipes to provide additional traction force and performing hoisting operations for drilling stalks consisting of several drilling pipes.

EFFECT: higher efficiency.

3 cl, 3 dwg

Drilling plant // 2247210

FIELD: mining industry.

SUBSTANCE: device has transporting base, post with guides and moveable stops, jointly connected via axes to post and placed in upper link of post for rods of force cylinders, which are fixed perpendicularly to support surfaces of moveable stops at moveable rotator, mounted with possible axial displacement along guides of post, and made with possible axial displacement along guides of post, and made wit possibility of their output from area of effect of rods of force feeding cylinders by means of control cylinder, placed on post, drilling stand, hoisting winch, rope and rope blocks. Moveable stops are made with possible rotation around axes in direction of action of rods of force feed cylinders. Their axes are placed in hollow parallel to support surfaces of moving supports and connected to rod of control cylinder, and between each other, via rotation lever, mounted between moveable stops. Cylinder for control is jointly connected to rotation lever and plant post.

EFFECT: higher productiveness.

3 dwg

Drilling plant // 2247211

FIELD: mining industry.

SUBSTANCE: device has transporting base, post with stops in upper connection, moveable rotator with guides, on which corbels are made and control cylinders are fixed, connected by their rods to force support cylinders, which via fixing elements are connected to rotator guides via axes, placed perpendicularly to longitudinal axis of post and surface of guides, directed by their rods for interaction with stops of upper link of post and have opportunity o displacement relatively to rotator guides and output of rods beyond stops of upper link of post, drilling stand, hoisting winch, rope and rope blocks. Axes and elements surfaces mated thereto of force feeding cylinders are made conical. Rods of control cylinders are rotated in direction of stops of upper link for angle equal to half of slanting angle of conical surfaces.

EFFECT: higher productiveness.

3 dwg

Drilling plant // 2247213

FIELD: mining industry.

SUBSTANCE: drilling device includes a rotator and hoisting gear, consisting of two force hydraulic cylinder with separator ring between them, through which rod passes, provided with pistons mounted in cylinders. Hoisting mechanism also includes fixed and moveable rollers and flexible links. Moveable rollers are placed inside the hollow of force cylinders and are fixed on outer surfaces of pistons, and fixed ones - on outer surfaces of end covers of cylinders. Force cylinders are made of different diameters, while cylinder for hoisting drilling columns greatest diameter. Plant is provided with two bars, fixed on upper and lower end covers and made in form of guides for rotator, separator ring and end covers are provided with fixing assemblies on front and back supports of post and hydraulic cylinder for raising the post to working position.

EFFECT: higher efficiency, simplified construction.

3 dwg

Drilling device // 2248437

FIELD: mining industry.

SUBSTANCE: device has platform and on the platform it has oil station with drive, mast and mechanism for feeding drilling tool drive, made in form of hydraulic cylinder, body of which is fixed at platform, and on free and of rod of which a carriage with two rollers is mounted, which are placed along length of rod, two rollers, mounted in upper and lower portion of mast and flexible link, fixed by its ends in place of extreme position of each of carriage rollers with retracted and extended rod of hydraulic cylinder and skirting rollers of carriage on inner side, and rollers of mast - on outer side. Device is provided with additional two coaxially mounted rollers, mounted in zone of connection of end of flexible link, skirting side roller of carriage, and single roller, mounted in zone of connection of second end of flexible link. One of branches of flexible link after carriage roller skirts single roller and each branch of flexible link skirts coaxially mounted rollers on opposite sides.

EFFECT: higher reliability.

1 dwg, 2 cl

Drilling device // 2249665

FIELD: geology.

SUBSTANCE: device has base, mast, jointly mounted thereon, telescopic element for changing its angular position, carriage with engine and rotator, moveably placed on mast posts, hydraulic cylinder for moving carriage, directed downwards by its rod, and hydraulic system. Hydraulic cylinder is placed between upper and lower mast bars, its shell is rigidly fixed in carriage, and rod is connected to lower bar. Upper bar and/or carriage body are made in form of tank for working liquid of hydraulic system. Hydraulic system pump is placed on rotator, while cinematic link of engine to pump and/or rotator is made in form of wedge-belt transfer link, and connections of leading and following sheaves with their shafts are made threaded with oppositely directed thread. Between rotator and hydraulic cylinders for protection of rod a skirt is placed in form of ribbon, fixed on ends of mast.

EFFECT: lesser dimensions, higher mobility.

4 cl, 8 dwg

Drilling plant // 2250342

FIELD: construction industry.

SUBSTANCE: device has base moving carriage with frame, driving actuators, volumetric hydraulic drive with pumps and driving engines for actuators of left and right boards and stopping brakes with mechanism for controlling these, and also of, mounted on frame of moving carriage via manipulator, feeder frame with rotation gears and traction of drilling base along well axis with hydraulic engines of drives of these mechanisms, while hydraulic rotation engines of drilling base and its feeding gear during drilling are connected to pumps of right and left board instead of actuator drives hydraulic engines, via two-positional holders, which are controlled together with stopping brakes. If brakes are made with braking hydraulic cylinders and control holder for these, two-positional holders are made with hydraulic control, and inputs into chambers for control thereof are connected by mains to input into braking cylinders of stopping brakes. To combine possibilities of drilling vertical and/or horizontal well suspension gear is made in form of four-assembly device, on joints, with hydraulic cylinder for slanting feeder frame, which device is supported by means of transverse beam. To provide for possible drilling at corners of rectangular pit, feeder frame is fixed in intermediate guide of support gear with possible longitudinal displacement, and transverse beam of suspension gear is made symmetrical relatively to longitudinal symmetry plane of carriage.

EFFECT: higher efficiency.

4 cl, 6 dwg

FIELD: oil production industry, particularly for development, repair and drilling oil and gas wells.

SUBSTANCE: facility has frame, drill derrick and drawworks with drilling and bailing drums assembled on the frame, power-driven reduction gear, drive transmission of drilling and bailing drums connecting them with power-driven reduction gear and provided with leading and driven members. Each transmission is arranged in rigid one-piece oil-filled body. Driven member of the transmission has hollow shaft put on shaft cantilever of corresponding drawworks drum. Shafts of leading and driven member are mounted in above body by bearings. Body is provided with hinged unit arranged from leading member side and adapted to support thereof by the frame. Leading member shaft is connected to power-driven reduction gear through double cardan joint.

EFFECT: multiple decreasing of side loads applied to drawworks drum shaft cantilevers, increased life of transmission members and simplified transmission assembling and disassembling.

4 cl, 9 dwg

FIELD: deep-hole drilling and well repair, particularly for rotary drilling and repairing oil and gas wells.

SUBSTANCE: facility includes transportation base with drilling derrick, draw works and draw works and rotor drive transmission. Facility also has rotor with built-in wedge grip arranged on separate mobile base and including rotary table and main gear wheel fixedly secured to rotary table. The main gear is cylindrical and arranged between two radial-thrust bearings inside body of rotary table provided with replaceable and detachable driving attachment arranged in separate body and fixedly connected with rotary table body. The attachment includes cylindrical satellite and drive gear put on drive shaft.

EFFECT: reduced size and extended range of suitable drives.

4 cl, 5 dwg