Method to construct mines and pits at nonterrestrial objects

FIELD: mining.

SUBSTANCE: method includes erection of the main and auxiliary shafts with a drilling rig from a shelter building, installation of sealing and heat-insulating ramps in shaft collars. One of the auxiliary shafts is erected in the form of a microscope, drilled from an exploratory well by means of its expansion from an inner mine tunnel until reaching the surface of an nonterrestrial object and used as a saving shaft, which on the surface via a gate chamber contacts with a landing complex of a spacecraft. In the saving shaft in the area of its connection with the inner mine tunnel there is a sealing heat-insulation ramp installed, drilled solids are distributed into a crater of the nonterrestrial object.

EFFECT: invention makes it possible to carry out salvage operations and to ensure the necessary ventilation in mines and pits, and also to establish a connection between the shafts on the nonterrestrial object surface.

4 cl, 1 dwg

 

The invention relates to mining, in particular to methods of construction of isolated hermetic mines, mines and pornobereich workings used for rescue operations, as well as for exploration and development of mineral deposits on space objects.

There is a method of construction of the trunk of advanced production Technology of underground construction. The construction of vertical openings. - M.: Nedra, 1992, str-240, RIS). The essence of this method consists in the following. Before the construction of the shaft in its Central part is an advanced formulation that is used for draining the rocks from the bottom of the barrel below the tunnel, which exploded breed loaded into trucks and transported to the dump.

The disadvantages of this method are:

- the cost to create a cutting-edge production;

- extension of the barrel is top-down, which limits its use;

- high complexity use in the construction of mines on space objects.

There is also known a method of construction of the mines and the mines on space objects (RU # 2368784, publ. 27.09.2009), including the construction of the main and auxiliary shafts drilling rigs from building shelters, installation germetezirujushie the insulating regiments.

The main disadvantages of this method are:

- the impossibility of carrying out rescue operations, which should be mandatory, and lack of ventilation in mines;

- long construction period of the auxiliary shafts;

- lack of communication on the surface of a space object between the trunks.

The objective of the proposed technical solution is the creation of a method of building mines on space objects, allowing to carry out rescue operations and to provide adequate ventilation in trunks and mines, as well as to reduce the cost and reduce construction time separate trunks, to establish communication between the trunks on the surface of the space object.

The task is solved by the proposed method of construction of mines on space objects, which includes the construction of the main and auxiliary shafts drilling rigs out of the building-shelter, at the mouths of the shafts sealing and insulating regiments. Differs from the closest technical solution that:

one of the auxiliary shafts are being constructed in the form of microstoma drilled exploratory well by extension, from the inner workings to the surface of a space object and used as a rescue shaft, is which on the surface through the lock chamber is in contact with the landing complex spacecraft, rescue shaft in place by its connection with the inner mountain development establish sealing insulation shelves, issue drilled rocks produced in the crater of a space object - this solution allows to conduct rescue operations in mines, as well as to reduce the cost and reduce construction time;

inside the rescue shaft move personnel using the appropriate hardware installed and plunged into the barrel, it also allows you to speed up the process of conducting rescue operations in mines;

rescue the trunk is used as an additional ventilation shaft using the appropriate equipment installed in the trunk or in the surrounding mines, allows to increase the safety of the works on the space object;

on the surface of a space object between the mouths of rescue and main trunks communicate in the form of mechanized road, allowing you to move cargo and personnel between the trunks.

The proposed solution is illustrated in the drawing, which shows the stage of construction of mines on the space object.

On the surface 1 a space object construct 2 main and auxiliary 3 trunks with SIP is using drilling rigs from building shelter 4. At the mouths of the shafts establish sealing and insulating the shelf 5. The main 2 and 3 auxiliary trunks inside of the space object are connected to the internal workings on the horizon 6. The auxiliary shaft 3 is converted into a rescue shaft (the drawing shows under the same position 3). For the construction of the rescue shaft 3 from the surface 1 a space object using drilling rigs are drilling exploration hole 7 provided in the chamber 8 on the horizon 6. Exploration well 7 can be performed in both vertical and inclined (as in the drawing) is associated with subsequent transformation into the rescue shaft, and an emergency exit on the surface of a space object in an inclined shaft will be longer, but it may be easier, and thus it is necessary to take into account the geological nature of this space object, the depth of the mine, the transverse dimensions of the shafts.

Rescue the barrel 3 being built in the form of microstoma, i.e. the minimum required in the transverse dimension (diameter) for a given mine or mine. Rescue the barrel 3 being constructed by drilling drill 9 exploration wells 7, with drilled rock down the shaft 3 in the cart 10 and is transported through the lock chamber into the crater of a space object next (not shown). Once uribana well 7 to the output shaft 3 to the surface 1 of the space object, where rescue the barrel 3 through the lock chamber 11 is in contact with the landing complex 12 spacecraft.

Rescue shaft 3 in the place of its connection with the inner mountain development 8 establish sealing insulation shelves 13, allowing in the case of an emergency at the mine or mine to completely isolate rescue the barrel 3 from the inner workings. Depending on the prevailing hydrogeological conditions at a particular space object instead of the proposed shelf 13 may apply airlock on the same spot of the barrel 3.

After the construction of the shaft 3 in its place the equipment to perform rescue operations in the mine, the mine (including for moving staff, or down inside the barrel of such equipment and other). To further address issues of mine ventilation, mine rescue shaft 3 place the equipment to ensure proper ventilation (pumps, valves, filters, etc., but adapted for a given space object), i.e. rescue the barrel 3 is used as an auxiliary ventilation shaft.

On the surface 1 a space object between the mouths rescue 3 and 2 main trunks communicate in the form of mechanized road 14, allowing goods to be moved and serving ersonal between the trunks.

When performing work on drilling exploratory wells 7 monitor drilled breed, and if you get the breed of interest, then they are selected and warehoused for future use.

The proposed solution allows for the construction of mines on space objects, allowing to carry out rescue operations and to provide adequate ventilation in mines, as well as to reduce the cost and reduce construction time separate trunks, to establish communication between the trunks on the surface of the space object.

1. The method of construction of mines on space objects, including the construction of the main and auxiliary shafts drilling rigs out of the building - shelter, at the mouths of the shafts sealing and insulating regiments, wherein one of the auxiliary shafts are being constructed in the form of microstoma drilled exploratory well by extension, from the inner workings to the surface of a space object and used as a rescue shaft, which on the surface through the lock chamber is in contact with the landing complex space ship, rescue the barrel in place by its connection with the inner mountain development establish sealing teploizolyatsii the traditional shelves, the issuance of drilled rocks produced in the crater of a space object.

2. The method according to claim 1, distinguish fact that inside the rescue shaft move personnel using appropriate equipment installed or descent inside of the trunk.

3. The method according to claim 1, characterized in that rescue shaft is used as an additional ventilation shaft using the appropriate equipment installed in the trunk or in the surrounding mines.

4. The method according to claim 1, characterized in that the surface of the space object between the mouths of rescue and main trunks communicate in the form of mechanized road.



 

Same patents:

FIELD: mining.

SUBSTANCE: shaft suspended drilling device consists of mounting plate and two drilling machines (DM) hinged on it. Mounting plate in its middle part has the holes for connection to rigid part of working equipment of shaft loading machine and is equipped with transverse spline intended to fix the position during connection. DMs are connected to mounting plate by means of gimbals or ball hinges and they have the possibility of being rotated and turned in various vertical planes, each by means of two control hydraulic jacks which are located at spatial angles relative to each other. Control hydraulic jacks are connected by means of gimbals or ball hinges to equally spaced posts rigidly mounted on mounting plate.

EFFECT: increasing efficiency of drilling work when making vertical shafts of shallow depth or advance owing to manoeuvrability and independence of operation of individual drilling machines mounted on common base.

3 dwg

FIELD: mining.

SUBSTANCE: according to the proposed method, a film of water emulsion is applied onto surface of mines, which is made on the basis of hydrophilic media, for instance, on the basis of products of tar deasphalting - pyrobitumens.

EFFECT: reduced cost of dampproofing, reduced time of technological operations performance, and also higher reliability of mine dampproofing.

6 cl

FIELD: mining.

SUBSTANCE: mine working lining method involves extension of beams from the area fixed with constant permanent lining to the working face of development opening, and working platform and decking is laid on them, and method also involves permanent lining. At that, in fixed part of the opening the pneumocylinder is laid on decking, and roof beams of permanent lining are laid on it with tightening, beams with decking, working platform, pneumocylinder, roof beams and tightening are extended to working face; compressed air is supplied to pneumocylinder, roof beams with tightening are lifted to the level of roof beams of permanent lining, tightening is lead to permanent lining, strut is made between roof beams of lining and roof of the opening by supplying compressed air to pneumocylinder. Then, to roof beams of the lining there attached are supports; after that, pneumocylinders are unloaded and beams with working platform, decking and pneumocylinder is moved to the fixed area of the opening, and after the mining face has been shifted for a cycle, operations are repeated.

EFFECT: increasing efficiency and safety of lining of development openings.

4 dwg

FIELD: mining.

SUBSTANCE: shaft loading machine consists of radial telescopically extension-type frame of box construction, which consists of middle main part of inverted T-shaped construction and two telescopically extension-type side parts with extension hydraulic jacks arranged inside them. On flanges of middle main part there arranged is self-propelled truck to which telescopically extensible handle is attached with possibility of restricted angular turn by means of two control hydraulic jacks hinged to self-propelled truck and to telescopically extensible handle. Handle consists of main and telescopically extensible parts and connected to each other by hydraulic extension jack arranged inside telescopically extensible part. Controlled grab bucket is hinged on lower end of telescopically extensible part with possibility of angular turn. Self-propelled carriage of angular movement is located on annular monorail mounted on upper part of suspension downhole casing. Independent movement of machine in vertical plane separately from sinking platform is performed by means of two-drum small-size winch mounted on outer side of upper storey of sinking platform, and movable central axis.

EFFECT: increasing drilling rates of vertical shafts, and improving discharge efficiency of rock mass.

7 dwg

FIELD: mining.

SUBSTANCE: method includes filling gaps with the help of flexible curb, which is a tight container sewn from hose of strong watertight cloth, shaped as a sack or bag closed at both ends. Valves with holes are installed in upper corners of flexible curb. One valve is intended to feed cement-containing mixture into the container, and the second one - for air outlet from filled space. The flexible curb is evenly laid behind course strengthening space, and cement-containing material is injected through one of valves, at the same time air is exhausted from filled space via the other valve.

EFFECT: high-quality and efficient filling of gaps in mining courses.

1 dwg

FIELD: mining.

SUBSTANCE: method to eliminate inflows via lining in collectors from high-precision units consists in elimination of water inflow in coupling units of assembly elements of structure by means of sealing gaps and cracks between blocks by installation of injector and injection of sealing compound into seams between blocks. Injection is made in joint of coupling planes of assembly elements. At the same time previously specified area of water inflow is confined by drilling of at least two key holes in plane of coupled joints for depth of block sealant location at the distance from each of key holes to area of injection equal to 1.0-1.5 of distance from surface of block to block sealant. Then sealing keys are installed with material having bearing strength of at least 5 MPa/cm2 into each of key holes, afterwards sealing compound is injected.

EFFECT: increased strength of injected joints and reduced consumption of expensive hydraulic insulation material.

8 cl, 1 dwg

FIELD: mining.

SUBSTANCE: arched yielding support includes joined arched roof bar and telescopic legs with yielding assemblies. At the same time support as a whole is made of box-like section, and roof bar and telescopic legs are connected by means of hinged joint of single-sided action.

EFFECT: improved bearing capacity of support, possibility to fold support structure into transport-assembly position and to move it as a whole without disassembling inside mine from point of dismantling to point of installation, increased force of yielding assemblies actuation in compliance with bearing capacity of support and achievement of their stable operation.

3 dwg

FIELD: mining.

SUBSTANCE: flexibility joint interlock of metal frame yielding support made of mine special profiles consists of plate with holes, "П"-shaped fixing bracket with threaded ends, inner and outer special profiles passing through the plate holes and overlapping, nuts and amplifier-stabilisers installed between the plate and flanges of inner special profile. Amplifier-stabilisers are made in a form of two hollow equal prismatoids, the sides of which are formed as equilateral or rectangular trapezoids that contact each other by the contours of the larger foundation, in the upper foundations there are holes for passing the "П"-shaped bracket through, the side surface of one of the prismatoids contacts the slanted side wall of the special profile. Note that one of the prismatoid foundation surfaces leans upon the interlock plate, and on diametrically opposite side the foundation of the other prismatoid is thrust upon the flange of mine special profile.

EFFECT: security of flexibility joint operation, provision of specified force of interlock tension, low prime cost of interlock manufacturing, reduction of support arrangement pitch, stability of the support working resistance along structural flexibility.

4 dwg

FIELD: mining.

SUBSTANCE: protection method of development entries at development of coal beds by means of long columns with the use of belt roadway of one pillar as ventilation for an adjacent pillar, in addition, at the same time of belt roadway operations, a bench is made along its entire length, mine props with beams are installed parallel to belt roadway, pneumocylinders are installed under the beams. Note that the beams are installed with a shift relative to one another for the width of one beam. Compressed air is supplied to the pneumocylinders beginning from its centre to the ends, the beams are pressed at the seam roof, and when mining an extraction pillar in the opposite direction, a pneumocylinder nearest to the powered roof support of the mining face and the nearest mine props are discharged and taken out to the belt roadway. The upper canopies of powered support sections hold the nearest ends of the beams, "П"-shaped supports are put on the bed soil behind the support of the mining face and the pneumocylinders are placed inside them, the compressed air is supplied to the cylinders pushing apart the supports between roof and bed soil, after shifting of the supports under the influence of the ground pressure and after walls of "П"-shaped supports have contacted with bed soil, pneumocylinders are decompressed and taken out into belt roadway. Note that pneumocylinders are installed in front of the line of mining face at a distance equal to the width of temporary support pressure area, and after the long face there installed are two "П"-shaped supports inserted into one another, one of which is arranged by supports to the seam roof.

EFFECT: more effective protection of development drifts and reduction of expenses for their maintenance in case of reuse.

12 dwg

FIELD: mining.

SUBSTANCE: construction of cement hopper for mining machine is an individual element. Mining machine is intended to drill holes in the rock and to pump cement to the holes, and includes mixer, cement hopper and supply device for supplying cement from lower cement hopper end to the mixer. At that, mining machine is equipped with moving device for moving the cement hopper between the position of being used at the top of the mining machine and the position of filling, which is different from the use position.

EFFECT: easy and simple loading and use of the mining machine hopper by workers.

6 dwg, 21 cl

FIELD: transport.

SUBSTANCE: invention relates to space engineering. Proposed device comprises pipeline 5, assembly to transfer container via pipeline and assembly to prepare and load container. The latter comprises rotary support 8 arranged on fixed support 7, bush 18 to accommodate container 17 and container cover 18. Transfer assembly comprises housing 19 accommodating gas-tight sleeve 20 representing, in initial position, a flat tape. Sleeve open end is tightly jointed with housing 19. Space 22 is communicated via air line 11 and start-and-shut-ff valve 12 with compressed gas source 10. Bush 16 has spring-loaded flange 24 and is locked by pyro cotter 27. Cover 18 is locked by pyro cotter 28. Support 8 is also locked by pyro cotter and provided with spring pusher 31 with rod 32 to displace transfer assembly, together with bush 16 and container 17, to under cover 18. Pyro cotter 27 operated, container 17 is closed by cover 18. Pyro cotter 28 and valve 12 operated, sleeve 20, straightening under gas pressure, displaces container 17 along pipeline 5. Delivery of container into autolander from any direction.

EFFECT: higher versatility of proposed device.

9 cl, 6 dwg

FIELD: mining.

SUBSTANCE: invention relates to mining, particularly to methods of building of isolated sealed mines, grooves and mountain-drilling rooms, used for shelter of people, and also for introduction of exploration work and field development of minerals in geological material of nonterrestrial objects. Building method of mines and grooves on nonterrestrial objects includes opening of top horizons by one of shanks, opening of bottom horizon through main shank and delivering of rock from deepening of each shank and horizon by adjacent shank. Structure of main and auxiliary shanks is implemented by boring machine with headstock from building structure - shelter, connected to spacecraft. After spudding of one or other shank on its mouth there are installed sealing and heat insulating shelves. There is continued construction at the outset of auxiliary shank, opening top horizon, then it is continued construction of main shank, top horizon connects both shanks. Delivery of rock from passing of each shank and horizon is implemented by adjacent shank through building structure - shelter and chamber gate by means of carriage bogie. Top horizon is continued to construct up to inlet to lip of nonterrestrial object, outlet of horizon is equipped by chamber gate.

EFFECT: invention provides safe of drilling activities implementation and to reduce material expenses.

2 cl, 1 dwg

FIELD: mining.

SUBSTANCE: invention refers to processing lunar soil and production of helium-3 (He3) on the Moon, including its back side. The complex of facilities for production of (He3) from the lunar soil consists of a source of micro-waves of super-high frequency installed on the lunar surface, and also of control equipment. The source of micro-waves of super-high frequency radiates waves onto a section of lunar soil surface covered with transparent for radiation elastic pressurised jacket; further He is withdrawn from the zone covered with the jacket, is liquefied and collected. The control equipment is installed in points of libration (Lagrange points) of system the Earth-the Moon and is designed to re-translate a control signal to the back side of the Moon.

EFFECT: simplification of process and equipment for production of helium-3 (He3), and also possibility to produce helium-3 (He3) not only on visible side of the Moon, but on its back side.

3 dwg

FIELD: mining.

SUBSTANCE: complex of development tools fro obtaining He3 from lunar soil includes draft gear, drag head, transporter, and receiving and processing unit. Draft gear is made in the form of two similar devices with removable ground traction boosters attached symmetrically at the opposite sides of the draft gear. Receiving and processing unit is placed beyond excavation zone. Receiving tool comprises a number of lunar soil banks obtained by soil casting from excavation zone to the processing unit. At that, the complex includes receiver-emitter device mounted at the draft gear for preliminary soil heating.

EFFECT: improved equipment operation efficiency and energy savings.

8 dwg

The invention relates to the cosmic energy, as well as ways and means to protect Earth from dangerous space objects: asteroids, comets, and space debris

The invention relates to the development of soils using earthmoving machinery on the moon

FIELD: mining.

SUBSTANCE: complex of development tools fro obtaining He3 from lunar soil includes draft gear, drag head, transporter, and receiving and processing unit. Draft gear is made in the form of two similar devices with removable ground traction boosters attached symmetrically at the opposite sides of the draft gear. Receiving and processing unit is placed beyond excavation zone. Receiving tool comprises a number of lunar soil banks obtained by soil casting from excavation zone to the processing unit. At that, the complex includes receiver-emitter device mounted at the draft gear for preliminary soil heating.

EFFECT: improved equipment operation efficiency and energy savings.

8 dwg

FIELD: mining.

SUBSTANCE: invention refers to processing lunar soil and production of helium-3 (He3) on the Moon, including its back side. The complex of facilities for production of (He3) from the lunar soil consists of a source of micro-waves of super-high frequency installed on the lunar surface, and also of control equipment. The source of micro-waves of super-high frequency radiates waves onto a section of lunar soil surface covered with transparent for radiation elastic pressurised jacket; further He is withdrawn from the zone covered with the jacket, is liquefied and collected. The control equipment is installed in points of libration (Lagrange points) of system the Earth-the Moon and is designed to re-translate a control signal to the back side of the Moon.

EFFECT: simplification of process and equipment for production of helium-3 (He3), and also possibility to produce helium-3 (He3) not only on visible side of the Moon, but on its back side.

3 dwg

FIELD: mining.

SUBSTANCE: invention relates to mining, particularly to methods of building of isolated sealed mines, grooves and mountain-drilling rooms, used for shelter of people, and also for introduction of exploration work and field development of minerals in geological material of nonterrestrial objects. Building method of mines and grooves on nonterrestrial objects includes opening of top horizons by one of shanks, opening of bottom horizon through main shank and delivering of rock from deepening of each shank and horizon by adjacent shank. Structure of main and auxiliary shanks is implemented by boring machine with headstock from building structure - shelter, connected to spacecraft. After spudding of one or other shank on its mouth there are installed sealing and heat insulating shelves. There is continued construction at the outset of auxiliary shank, opening top horizon, then it is continued construction of main shank, top horizon connects both shanks. Delivery of rock from passing of each shank and horizon is implemented by adjacent shank through building structure - shelter and chamber gate by means of carriage bogie. Top horizon is continued to construct up to inlet to lip of nonterrestrial object, outlet of horizon is equipped by chamber gate.

EFFECT: invention provides safe of drilling activities implementation and to reduce material expenses.

2 cl, 1 dwg

FIELD: transport.

SUBSTANCE: invention relates to space engineering. Proposed device comprises pipeline 5, assembly to transfer container via pipeline and assembly to prepare and load container. The latter comprises rotary support 8 arranged on fixed support 7, bush 18 to accommodate container 17 and container cover 18. Transfer assembly comprises housing 19 accommodating gas-tight sleeve 20 representing, in initial position, a flat tape. Sleeve open end is tightly jointed with housing 19. Space 22 is communicated via air line 11 and start-and-shut-ff valve 12 with compressed gas source 10. Bush 16 has spring-loaded flange 24 and is locked by pyro cotter 27. Cover 18 is locked by pyro cotter 28. Support 8 is also locked by pyro cotter and provided with spring pusher 31 with rod 32 to displace transfer assembly, together with bush 16 and container 17, to under cover 18. Pyro cotter 27 operated, container 17 is closed by cover 18. Pyro cotter 28 and valve 12 operated, sleeve 20, straightening under gas pressure, displaces container 17 along pipeline 5. Delivery of container into autolander from any direction.

EFFECT: higher versatility of proposed device.

9 cl, 6 dwg