Well operation method

FIELD: oil and gas industry.

SUBSTANCE: in well operation method involving pumping of composite material to the formation to the interval below oil-water contact, process exposure and operation of the well, there preliminarily performed is forcing of water from inter-tube space with oil to the interval below oil-water contact; in order to prepare composite material the thickener is filled to inter-tube space of the well on the basis of 1-5 kg per 1 m3 of oil located in inter-tube space, and mixing of thickener with oil in inter-tube space by oil circulation with thickener via tubing string and inter-tube space, and pumping of solution of oil and thickener from inter-tube space to the interval below oil-water contact is performed in pulse mode under pressure exceeding hydrostatic one by not more than 10%; at that after process exposure the well operation is performed during the first 5-15 days in moderate mode with flow rate of not more than 50% of the operating one.

EFFECT: reducing associated water production.

1 ex, 1 dwg

 

The invention relates to the oil industry and can find application in the operation of the oil wells.

There is a method of oil and gas-liquid mixtures through the pump unit with separate admission of oil (oil mixture) and water (APCS), which pumped water through the shank, below the level of the oil-water contact in the reservoir and connected with the lower suction valve cylinder APCS, and oil (gas mixture) for the annular space through the side suction valve cylinder APCS (SU 1323743, published. 15.07.1987).

The disadvantage of this method is the large selection of water, often a multiple of exceeding the selection of oil, the actual extraction of water for the destruction of the cone of water, preventing the flow of oil from oil-saturated part of the reservoir, and the reduction effect in the production of oil.

The closest to the proposed invention the technical essence is a way of putting pressure on the bottom area of the well field with underlying or bottom water and oil pump rod-compressor with separate reception hydrocarbon and water. For the implementation of the way down into the well column tubing (tubing) with the retainer and the shank. Served through the shank in the drill pipe is heated to 70-80C a mixture of anhydrous oil from oil-soluble and is and macrovomitorium surfactant in the amount sufficient to displace the cold and the cooled oil from the shank in the annulus of the borehole in the zone of the reservoir and placing the heated mixture in front of the perforations. Overlap the packer annulus of the well and pumped under pressure to a heated mixture of oil, surfactant below installation of the packer into the reservoir, maintain the pressure for a time sufficient to decompose water-oil emulsion in a cone of water in a well bore zone, then rip off and retrieve the packer. In the well down rod pump-compressor with separate reception and install it so that the inlet shank was located below the middle line of oil-water contact for cone watering, and are pumping produced water through the shank, and oil in the annular space through the side valve pump compressor (RF patent No. 2293214, published. 10.02.2007 - prototype).

A known method can be implemented only in specific applications of insulated pipes, allowing to deliver the heated fluid in the interval of the reservoir, the method is accompanied by a large selection of associated water.

In the proposed invention solves the problem of reducing the production of associated water.

The task is solved in that in the method of operating a well comprising pumping a composite material in place is in the interval below the oil-water contact, conducting technological exposure and operation of wells, according to the invention previously conducted pushing water from the annulus of oil in the interval below the oil-water contact, for the preparation of a composite material are filled in the annular space of the well thickener based 1-5 kg per 1 m3the oil in the annular space, and mixing the thickener with the oil in the annular space by the circulation of oil with a thickener of the column tubing and the annular space, and the injection of a solution of oil and thickener annulus in the interval below the oil-water contact are in pulsed mode at pressures greater than hydrostatic pressure of not more than 10%, while after the process of aging well operation in the first 5-15 days. hold in the power saving mode with a flow rate of not more than 50% of the worker.

The invention

In the development of oil, gas and gas condensate fields with plantar water inevitably have to deal with the phenomenon of consobrina when the underlying water rises to the perforation holes and overlaps all or part of the access oil in the well. Existing technical solutions solve the problem of consobrina only partially. Mostly fighting what consobrina boils down to the preferential selection of water from the underlying water and generate zero or even inverted cone of water. However, you have to take a huge amount of associated water. Well from the oil actually becomes vododobyvayuschih. In the proposed method solves the problem of reducing the production of associated water. The problem is solved as follows.

During operation of the oil wells that discover the producing formation with the underlying water supply well depth equipment for lifting to the surface and replacement of individual elements to the selection of oil from the interval above the oil-water contact, the injection of the annulus fluid in the interval below the oil-water contact and circulation of liquid through the column tubing and the annular space.

Typically, the interval of the well from the productive formation to pump filled the reservoir with water. In our case, this water is undesirable element. To remove it from the well spend pushing water from the annulus of oil in the interval below the oil-water contact. Then make the fill annulus of the well thickener, such as polyacrylamide, hydrolyzed polyacrylonitrile, methyl cellulose and the like, at the rate of 1-5 kg per 1 m3the oil in the annular space, and mixing the thickener with the oil in the annular space by the circulation of oil is the thickener of the column tubing and the annular space. Perform the injection of the solution of oil and thickener annulus in the interval below the oil-water contact in pulsed mode at pressures greater than hydrostatic not more than 10%. The pulse mode, do the following. Download solution to increase the pressure injection to hydrostatic +10%, stop the injection and hold the shutter speed to reduce the pressure to the hydrostatic +(2-6) %. Again injected to increase the pressure to hydrostatic +10%, again carry out the specified shutter speed, etc. to download the full volume of the solution of oil and thickener. Push the solution in the oil. Conduct technology exposure for structuring a solution of the oil with a thickener. After the process of aging well operation in the first 5-15 days. hold in the power saving mode with a flow rate of not more than 50% of the worker.

A possible variant of the underground layout shown in the drawing.

In the drawing, producing well 1 is equipped with a casing 2, a perforated interval of the productive layer 3 with the oil-water contact 4. In the well 1 down the column tubing with 5 oil pump 6, the packer 7 above the roof of the productive layer 3, a spring-loaded non-return valve 8 and perforations 9 in the lower part. Lower spring-loaded check valve 8 within the colon is s tubing 5 has a nozzle 10, which is reported on the top above the packer 7 with the annular space of the borehole 1, and the bottom is equipped with a packer 11 mounted in the interval of oil-water contact 4, and a spring-loaded non-return valve 12, capable of flowing fluid from the interior of the pipe 10 in the interval below the oil-water contact 4. At the wellhead 1 is made binding column tubing 5 for connection with the discharge line 13, line connection with the annular space of the borehole 14 and the discharge line 15. The valve 16 is designed to overlay flow lines 14, the valve 17 to overlap the line of connection with the annular space, the valve 18 to overlap the discharge line 15.

The device operates as follows.

In working condition, open the valve 16 and closed valves 17 and 18.

Select fluid from the interval above the oil-water contact 4 by the pump 6 through the tubing pipe 5. In this case, valve 16 is opened, the valves 17 and 18 are closed. During the formation of the cone watering and significant flooding of the produced products stop the operation of the pump 6, close the valve 16 and open the valves 17 and 18. On the discharge line 15 in the annular space of the borehole 1 separate pump (not shown), for example, from the retainer Assembly pump in the oil from the well pump to packer 7. Then without interruption of the injection pump thickener based 1-5 kg per 1 m3the oil in the annular space. The flow of fluids in the tubing tube 5 prevents the valves in the pump 6 (not shown). The valve 15 is closed and when closed, the valve 16 and open the valve 17 start the pump rod 6. Perform mixing of the thickener with the oil in the annular space by the circulation of oil with a thickener of the column tubing 5 through piping with valve 17, the annular space of the well 1, the holes 9 and the column tubing 5. Pre-spring of a spring-loaded valve 8 is set so that when the circulation valve 8 was closed. Circulation perform to obtain a homogeneous mixture (solution) of the thickener and oil. Then upload the resulting mixture of oil and thickener annulus in the interval below the oil-water contact in pulsed mode at pressures greater than hydrostatic not more than 10%. To do this, stop the pump 6, open valve 18 and open valve 17 and the closed valve 16 is injected into the annular space of the borehole 1 in the oil well 1, which expels the mixture of oil and thickener annulus of the borehole 1 in the Patra is OK 10 and through the spring loaded check valve 12 below the packer 11 in the interval below the oil-water contact and further into the reservoir. Close all valves and stop all injection and extraction at the well. Conduct technology exposure for 1-3 days. for the formation near the well bore space in the area of the cone watering reliable insulation of the screen. After the process of aging well operation in the first 5-15 days. hold in the power saving mode with a flow rate of not more than 50% of the worker.

In the result it is possible to reduce the water content of products produced by 30-40% and reduce the amount of water in the well.

Specific example

Exploit oil well according to the drawing, which is provided with a casing 2 with a diameter of 245 mm(9||), perforated in the interval 1710-1720 m productive layer 3 with the oil-water contact 4 on the depth 1714 m well 1 down the column tubing 5 with a diameter of 168 mm (6||with sucker-rod pump 6, the packer 7 above the roof of the productive layer 3, a spring-loaded non-return valve 8 and perforations 9 in the lower part. Lower spring-loaded check valve 8 inside the column tubing 5 has a pipe 10 with a diameter of 60 mm (2||).

In working condition, open the valve 16 and closed valves 17, 18 and 19.

Select a liquid with a rate of 16 m3/day. from the interval above the oil-water contact 4 by the pump 6 through the column pump to pressornyh pipe 5. In this case, valve 16 is opened, the valves 17 and 18 are closed. During the formation of the cone watering and irrigation of products produced up to 80% stop operation of the pump 6, close the valve 16 and open the valves 17 and 18. On the discharge line 15 in the annular space of the borehole 1 single pump cementing unit CA-320 pumped oil in the amount of 14 m3i.e. the volume of the well from the pump 6 to the packer 7. Then without interruption of the injection pump thickener - polyacrylamide in the form of a 5%dispersion in oil at the rate of 3 kg per 1 m3the oil in the annular space of 40 m3. The valve 15 is closed and when closed, the valve 16 to open the valve 17. Start the pump rod 6. Perform mixing of the thickener with the oil in the annular space by the circulation of oil with a thickener of the column tubing 5 through piping with valve 17, the annular space of the well 1, the holes 9 and the column tubing 5. Pre-spring of a spring-loaded valve 8 is set so that when the circulation valve 8 was closed. Circulation perform to obtain a homogeneous mixture (solution) of the thickener and oil. Then upload the resulting mixture of oil and thickener annulus in the interval below the water-oil to the of intacta in pulsed mode under pressure, exceeding the hydrostatic pressure of not more than 10%. To do this, stop the pump 6, open valve 18 and open valve 17 and the closed valve 16 is injected into the annular space of the borehole 1 oil in the amount of 40 m3well 1, which expels the mixture of oil and thickener annulus of the borehole 1 in the pipe 10 and through the spring loaded check valve 12 below the packer 11 in the interval below the oil-water contact and further into the reservoir. Close all valves and stop all injection and extraction at the well. Conduct technology exposure for 2 days. for the formation near the well bore space in the area of the cone watering reliable insulation of the screen. After technological exposure operation of the well in the first 10 days. hold in the power saving mode with a flow rate of not more than 50% of the worker.

In the result it is possible to reduce the water content in crude production by 35% and reduce the amount of water in the well.

A method of operating a well comprising pumping a composite material in the reservoir in the interval below the oil-water contact, conducting technological exposure and operation of wells, wherein the previously conducted pushing water from the annulus of oil in the interval below the oil-water contact, for making a composite material p is avodat fill in the annulus of the well thickener based 1-5 kg per 1 m 3the oil in the annular space, and mixing the thickener with the oil in the annular space by the circulation of oil with a thickener of the column tubing and the annular space, and the injection of a solution of oil and thickener annulus in the interval below the oil-water contact are in pulsed mode at pressures greater than hydrostatic pressure of not more than 10%, while after the process of aging well operation in the first 5-15 days spend in a sparing mode with a flow rate of not more than 50% of the work.



 

Same patents:

FIELD: oil and gas industry.

SUBSTANCE: method involves use of the well and flow column lowered to it, pumping to productive formation of liquid or liquid-gas mixture prepared by using the mixing device the discharge of which is interconnected with flow column, and low and high pressure chambers - with gas and/or liquid sources. According to invention, the pumping of liquid or liquid-gas mixture is performed periodically to the watered-out interval of productive formation. On bottom hole of the well, in annular space between flow column and casing string in the interval above and within the limits of the watered-out part of productive formation there installed are not less than two packers. Annular space in the packer installation interval is filled with non-newtonian fluid. Two circulation valves are installed in flow column. One is installed in watered-out interval of the formation, and the other one - above the upper packer.

EFFECT: increasing operating efficiency of wells at hydrocarbon deposits, the operation of which is complicated with water penetration into deposits.

5 cl, 1 dwg

FIELD: oil-and-gas production.

SUBSTANCE: it is implemented preparation of injection well in insulated area by path close to roof cladding configuration of insulated area of stratum. Then it is pumped into it solution of foam maker with following feeding of gas for foaming. It is defined minimal horizontal lateral dimension of screen from conditions of filtration through the screen of gas and/ or water considering pressure gradient at the boundaries of screen at the period equal to period maximal pumping into gas storage or maximal permissible withdrawal of gas from particular storage. Minimal vertical dimension if screen is considered equal to value which is not less than maximal dimension from roof of formation up to gas-water contact in the area of screen creation. In preference it is implemented injection well making, path of which is normal to vector of average speed of formation fluid in isolated area of stratum. Preferentially it is also implemented making of inclined and/or horizontal injection well.

EFFECT: reliability growth of operating characteristics of screen, reduction of foam former consumption and gas amount, used for foaming and consumptions for wells drilling.

3 cl, 3 tbl, 1 ex, 3 dwg

FIELD: oil-and-gas industry.

SUBSTANCE: invention relate to oil exploration industry and can be used for formation water in-flow limitation. Composition producing method includes mixing of a water solution with carbon black, at that preliminary disperse carbon black in the methyl cellulose diluted water solution, at component ratio wt % : carbon black 15.0, methyl cellulose 0.05, the rest is water. Then mix received concentrated suspension with methyl cellulose water solution and carbamide at the following component ratio wt %: methyl cellulose 0.5-2.0, carbamide 2.0-20.0, carbon black 0.5-5.0, the rest is water. The composition of oil recovery rate increase characterised with the mentioned above method.

EFFECT: oil wells oil recovery rate increase due to reservoir physico-chemical treatment.

2 cl, 1 tbl, 24 ex

FIELD: oil-and-gas industry.

SUBSTANCE: invention related to oil-and-gas industry and can be used for water inflow into well limitation methods. According to the method execute high viscosity oil and cement heated mixture pumping via thermal insulated pipes, driving with low viscous oil and process ageing. According to the invention kill the well with well killing fluid, execute works until well specific intake capacity value is equal 0.5-3.0 m3/(hMPa), pump into the well not less then 8 m3, with density equal well killing fluid density. Execute pumping though thermal insulated pumps of the high viscosity oil and cement heated mixture with consumption rate 2-10 m3/hour.

EFFECT: production wells water inflow insulation efficiency increase.

1 ex

FIELD: oil-and-gas industry.

SUBSTANCE: method of efficiency recovery and stand by wells, with collector of complicated design in abnormally low formation pressure conditions and production string bottom part collapse includes execution of repair-isolation works and reservoir opening. Sweep up the string, repair its compressed bottom, wash in a sand plug till depth of the nearest to a gas-water contact - GWC clay sub layer, descend in to the string a tail from casing pipes of a smaller diametre up to the sand plug head, with the tail head dislocation 20 m above of the reservoir roof, cement the tail with a cement slurry, leaving a cement barrel 1-2 m higher the tails shoe. After cement fixing - CFT drill the cement barrel, wash the sand plug up to the current GWC, through perforation holes with perforation interval 15-20 m3 of the water sealing composition, press it through 3-5 m3 of the cement slurry in to the reservoir, creating water sealing screen and stop over the defined height cement barrels sand plug. After the CFT execute perforation - hydro-sand-jetted or with powerful cumulative perforator - of the production string and the tail in interval over cement barrel head up to the reservoir roof and gas flow activation. The cement slurry contains portlandcement, superplastisiser C-3, polyvinyl alcohol, and polypropylene fiber.

EFFECT: well efficiency recovery and stand by wells operation start up reliability increase.

1 ex, 4 dwg

FIELD: oil-and-gas production.

SUBSTANCE: invention related to oil-and-gas production, particularly to production efficiency increase. The method includes pumping into reservoir, through injection wells system, into zones around wells tall oil with filler - dispor in amount 5-10% of the tall oil and continue watering.

EFFECT: reservoir input profile aligning, oil withdrawal reservoir watering efficiency increase.

2 tbl

FIELD: oil and gas production.

SUBSTANCE: invention is related to gas production industry, in particular to methods for isolation of bottom water influx in gas wells. In method for isolation of bottom water influx in gas wells, including lowering of oil well tubing (OWT), pumping of blocking polymer compound with previously identified value of structural viscosity in annular space, cement isolating substance along OWT, their pushing through with process fluid, lowering of OWT is done down water entry bed, additionally prior to pumping of blocking polymer compound, a low-viscous gel-forming compound is supplied into annular space, which contains the following components, wt %: sodium silicate of "Sialit 30-50" grade 50, liquid waste from process of electrochemical metal coating 0.8, water - the rest, adding the latter to water entry bed, and blocking polymer compound is added to gas-bearing bed, then they are pushed through by pumping of process fluid along OWT with annular space closed, blocking polymer compound is used with a value of structural viscosity that exceeds at least thrice value of structural viscosity of low-viscous gel-forming compound, for headers with high permeability they use polymer compound as blocking polymer compound with organic filler, containing the following components, wt %: lignosulphonate 5, calcium chloride 15, gas condensate 20, peat-alkaline filler 7, technical water - the rest, and for headers with low permeability - polymer compound with condensed solid phase, which contains the following components, wt %: calcium chloride 9, twice-substituted ammonium phosphate 11, water-soluble polymer 2, surfactant 1, technical water - the rest, at the same time volume of blocking compound is defined according to given calculation formula, and pumping of cement isolation compound along OWT is done in volume that exceeds volume of operational pipe in interval of water entry bed by 20%, at the same time pushing of cement isolation compound is started to be done with annular space open, and after it reaches bottom of gas bearing bed, it is pushed with annular space closed with pressure that exceeds pressure of absorption.

EFFECT: development of efficient method for isolation of bottom water influx in gas wells.

2 ex, 2 tbl

FIELD: oil and gas production.

SUBSTANCE: method of recovery of yield and bringing to operation of temporarily shut-in wells with complicated structure of collectors under conditions of abnormally low bed pressure including repair, insulating, and exposure of producing bed consists in following: initially, sand plug is washed for depth 2-3 m below current gas-water contact (GWC); producing string is callipered, shank end out of casing tubes of smaller diametre is lowered into producing string up to head of washed sand plug; head of shank end is arranged 20 m above top of producing bed. The shank end is cemented with cement grout; upon waiting-on-cement completion (WCC) two columns, the producing column and the shank end are perforated in interval below the first over current GWC clay interlayer to depth 2-3 m below current GWC. Water insulating composition at volume 15-20 m3 is pumped through perforated openings made for water insulation; composition is forced through into depth of the producing bed creating a water insulating screen with cement grout of volume 3-5 m3; a cement sleeve 1-2 m above the first over the current GWC clay interlayer is left at the bottomhole. Upon WCC perforating is performed for operation of two columns, the producing column and the shank end in interval above the second over the current GWC clay interlayer up to the top of the producing bed; gas discharge is initiated. Composition containing Portland cement, super-plasticiser C-3, polyvinyl alcohol and polypropylene fibre is used as cement grout; while for perforation either a high-power cumulative perforator or hydraulic jet are used.

EFFECT: insulating fluid entry, ensuring pressure tightness of producing column and additional gas withdrawal from earlier shut-in wells.

1 ex, 4 dwg

FIELD: oil-and-gas production.

SUBSTANCE: invention relates to the oil industry, particularly to methods of processing strata of oil-fields, and can also be used for waterproofing oil wells and for regulating intake profile of intake wells. The method of processing oil-field strata involves pumping a composition into the strata, containing aqueous solution of an anionic polymer, water soluble inorganic or organic acid or a mixture of acids, aliphatic or aromatic alcohol or a product containing it, and a polyvalent metal salt. The said composition also contains a surface-active substance or a mixture of surface-active substances, fine-grained hydrophobic material FGHM and an inhibitor. Before adding polyvalent metal salt to the aqueous solution of anionic polymer, the said alcohol or product containing it, surface-active substance or mixture of surface-active substances, FGHM and inhibitor are added and pH of the reaction mixture is brought to 0.5-3.0 by adding the said acid or mixture of acids with the following content of components, wt %: water soluble anionic polymer 0.004-5.0, alcohol or product containing it 0.50-50.0, surface-active substance or mixture of surface-active substances 0.50-10.0, FGHM 0.1-3.0, polyvalent metal salt 0.003-0.30, inhibitor 0.1-3.0, water - the rest. The invention is developed in a subclaim.

EFFECT: more efficient processing of strata due to improvement of rheological and hydrophobisation properties of pumped compositions, as well as their oil-sweeping properties.

2 cl, 4 tbl, 4 ex

FIELD: oil and gas production.

SUBSTANCE: invention refers to oil producing industry, particularly, to procedures of isolation and restraint of water production in horizontal boreholes of producing wells. The procedure consists in polymer pumping, in driving polymer solution, and in well shut-down for the period of polymer structure formation. Prior to pumping polymer solution into each interval, blocking fluid with optimal period of "life" is pumped into the well; further, specified volume of polymer is pumped into an isolated interval during this period of "life"; after the expiration of the period blocking fluid self-decomposes in volume required for filling the horizontal borehole from the bottomhole of the well to the nearest from the bottomhole boundary of interval of polymer solution treatment. Upon conditioning, decomposer of polymer is pumped into the well for the period of polymer structure formation in the latest treated interval; with water decomposer is further driven through into a reservoir to the nearest near-well zone and is conditioned there for the period of polymer decomposition.

EFFECT: increased efficiency of isolating water production in horizontal wells.

5 dwg, 1 ex

FIELD: oil and gas production.

SUBSTANCE: invention relates to insulating formation water inflow in gas and gas condensate wells with the aid of coltubing techniques. In particular, flexible conduit is descended through the tube space of well operated under pressure to the bottom with the aid of coltubing installation. Latches on tube and annulus spaces are opened. Well hole is filled through flexible conduit with gas condensate. Grouting mortar is prepared in preparation block by mixing cement mortar with setting retardant and mortar flowability enhancer in a calculated amount needed to prevent formation water inflow. Further, flushing fluid, e.g. methanol, is pumped through flexible conduit in amount constituting 0.3-0.6 volume of flexible conduit. Annulus space is closed and grouting mortar is pumped through flexible conduit in amount required to fill well hole in interval of water-inflow part of formation. When grouting mortar in hole rises to specified height, tube space is closed and grouting mortar contained in flexible conduit is forced into water-inflow part of formation by in series pumped flushing fluid and displacing solution: for example first methanol in amount 1.0-1.3 volumes of flexible conduit and then gas condensate in required amount, which however does not exceed internal volume of flexible conduit, until grouting mortar begins being pumped in amount of 0.3-0.5 volumes of flexible conduit. Then tube and annulus spaces of well are opened and gas condensate begins being simultaneously pumped into tube and annulus spaces in order to prevent rise of grouting mortar therein above interval of the water-inflow part of formation. Thereafter, bottom of flexible conduit is raised by 1 m above indicated interval and excess of grouting mortar is cut and washed away with gas condensate passed through flexible conduit into tube space, where excess grouting mortar remains in fluid state. After cement setting expectation time, flexible conduit is descended to the top of cement column and tests the latter for strength applying 4.0-5.0 kN loading by means of injector of coltubing installation through flexible conduit. Finally, cement bridging is subjected to hydraulic pressurization and flexible conduit is removed from well.

EFFECT: enabled formation water inflow insulation without killing of well and restricted pollution of water-inflow part of formation.

3 cl, 1 dwg

FIELD: oil and gas chambers construction.

SUBSTANCE: method includes pumping of portion of water-absorbing acryl polymer, exposure of it in a well, pumping of second portion of same polymer, tempered on fresh water with concentration 1-20%, buffer of fresh water dries up, and before and after pumping of second portion of water-absorbing polymer, tempered on hydrocarbon liquid with concentration 10-20%, buffer of hydrocarbon liquid is pumped in, besides, said 2-portion systems are pumped into well multiple times.

EFFECT: higher efficiency.

1 ex

FIELD: oil and gas production.

SUBSTANCE: bottom area of formation is treated with hydrophobic agent, in particular solution of ethylene/vinyl acetate copolymer expressed by general formula [-CH2-CH2-C(CH3COO)H-CH2-]n, where n=7000-10000, in hydrocarbon solvent.

EFFECT: increased source of inexpensive hydrophobic agents with improved adhesion properties, intensified oil recovery due to increased depth of penetration of hydrophobic agent into formation, improved environmental conditions in development of oil formations, and reduced oil production expenses.

2 tbl, 2 ex

FIELD: oil and gas production.

SUBSTANCE: composition is made up of 90.0-95.0% sodium silicate solution with concentration 1.36 g/cm3 and silica modulus 3.0, 3.0-8.0% alkali metal silicofluoride, 1.0-4.0% wood flour, and 1.0-4.0% triacetine. Composition can be used during repair operations on oil production stings, when disabling formations, and when confining water inflow.

EFFECT: increased insulation capacity of grouting compositions.

1 tbl

FIELD: oil extractive industry.

SUBSTANCE: method includes pumping, in carrying liquid - waterless mixture of oil products containing waterless oil, of powder-like water-soluble polymer and connector in amount of 0.05-0.2% for mass of carrying liquid or 30-100% for mass of power-like water-soluble polymer, as said mixture a mixture of waterless oil and light oil products processed in relation 0.1:9.9-9.9:0.1 is used, and as connector - dry aluminum nitrate, chrome nitrate, iron nitrate, magnesium nitrate, barium nitrate, calcium nitrate or their mixtures.

EFFECT: higher efficiency.

2 tbl

FIELD: oil extractive industry.

SUBSTANCE: method includes pumping, in carrying liquid - waterless mixture of oil products containing waterless oil, of powder-like water-soluble polymer and connector in amount of 0.05-0.2% for mass of carrying liquid or 30-100% for mass of power-like water-soluble polymer, as said mixture a mixture of waterless oil and light oil products processed in relation 0.1:9.9-9.9:0.1 is used, and as connector - dry aluminum acetate, chrome acetate, iron acetate, magnesium acetate, copper acetate, barium acetate, manganese acetate, calcium acetate or their mixtures.

EFFECT: higher efficiency.

1 tbl

FIELD: oil extractive industry.

SUBSTANCE: method includes pumping, in carrying liquid - waterless mixture of oil products containing waterless oil, of powder-like water-soluble polymer and connector in amount of 0.05-0.2% for mass of carrying liquid or 30-100% for mass of power-like water-soluble polymer, as said mixture a mixture of waterless oil and light oil products processed in relation 0.1:9.9-9.9:0.1 is used, and as connector - dry aluminum sulfate, chrome sulfate, iron sulfate, magnesium sulfate, copper sulfate or their mixtures, or their alums with common formula MIMIII(SO4)

.2
12H2O, where MI-Na,K,Pb,Cs,NH4, and MIII-Al,Cr,Fe,Mn.

EFFECT: higher efficiency.

2 tbl

FIELD: oil and gas extractive industry.

SUBSTANCE: method includes forming a screen of viscous-elastic mass in well via interaction of working liquid pumped into well in form of alkali waste of kaprolaktam production or its solution, with influx liquid. Necessary speed of transformation of viscous-elastic mass and intensiveness of filling of well adjacent area with it is adjusted by mode of pressing of working liquid into influx zone. For this purpose pressure increase is alternated with pressure decrease. Pressure is decreased for 10-50% from achieved maximum pressure. Relation of exposure time for increased pressure to decreased pressure time is taken in limits 1.1-5.0.

EFFECT: higher efficiency.

7 cl, 1 ex

FIELD: oil industry.

SUBSTANCE: compound has carbomide, urotropine and water, additionally has chlorine iron with following relation of components in percents of mass: carbomide 6.0-16, urotropine 5.0-8.0, chlorine iron 5.0-10, water the rest.

EFFECT: higher efficiency.

8 ex, 2 tbl

FIELD: oil and gas industry.

SUBSTANCE: method includes adjustment of pumping and dosing equipment on basis of amounts of components and their feeding time. Multi-component technological system is forced into well. Adjustment of pumping and dosing equipment is performed by means of frequency converters. Frequencies, set at frequency converter of forcing pump electric engine, at frequency converter of linker-feeding pump electric engine and at frequency converter of powdered polyacrylamide dosing pump electric engine are determined from mathematical formulae. Plant has drift dosage means for powdered polyacrylamide, drift dosage means for powdered components, two ejector mixers, mixing tank, forcing pump, linker tank. Electric engines of forcing pump, linker pump, first and second drift dosage devices are provided with frequency converters. First and second ejector mixers are provided with replaceable nozzles, with diameter 4.5-8.0 mm to provide for 150-250 m3/day plant productiveness.

EFFECT: higher precision.

2 cl, 2 dwg, 1 ex, 1 tbl