Method to perform survey of well provided with sucker-rod pump

FIELD: oil industry, particularly to perform running wells provided with flow strings and sucker-rod pumps.

SUBSTANCE: method involves stopping rocker-machine operation during work performing at well head and sucker-rod pump operation for not more than 20 min; lowering instrument into well; lowering instrument connected to logging cable through cable head for 2 meters; bringing rocker-machine in operation and continuing instrument lowering in well; repeatedly brining sucker-rod pump in operation up to working level reaching during instrument lowering and after instrument lowering; performing survey during sucker-rod pump operation when sucker-rod pump reaches working mode of operation; lifting the instrument to well head after survey termination; stopping the tool at height spaced 100 meters from well head; bringing rocker-machine and sucker-rod pump out of operation; removing the instrument from well and repeatedly bringing rocker-machine and sucker-rod pump in operation.

EFFECT: increased operational reliability due to prevention of logging cable loop forming about flow string and increased reliability of survey results due to measurement performing in working well operation regime.

 

The invention relates to the oil industry and can be used for surveys of existing wells.

There is a method of research wells equipped with push rod pumps, including the descent of logging tools on wireline in the borehole to determine the intervals of flow in the tubing after extracting the plug-in pump with filter, with the call flow exercise swabbing or compressing via a valve node unilateral action (Application RU # 2003112724 AND class. E 21 In 47/00, publ. 2004.12.10).

The known method does not allow to analyze the situation in the annular space of the well.

The known method of descent of the device in the borehole, including the equipment of the well sucker rod pump, the descent into the well liner and tubing and a pass device in the annular space. The shank down through the fishing device of the column tubing and install it in the casing before placing nodes downhole sucker rod pump (RU # 2029079 C1, CL E 21 In 47/00, 20.02.1995).

The closest to the proposed invention the technical essence is a method of study of a well equipped with a column tubing and sucker rod pump comprising a stop work of art is NSV-rocking when working on the wellhead and pump the descent into the well through the annular space on the cable of the device, the start of the pumping unit and sucker rod pumps in operation, after conducting exit to the operating mode of operation of the pumping unit and sucker rod pump and removing the device from the well(RU # 2052089, CL E 21 In 47/00, 10.01.1996).

The known method does not allow a full range of research in the well.

The disadvantage of this method is the difficulty associated with the descent of the equipment in the well, the low reliability of its installation in the borehole, the complexity, the possibility of kinking of the cable.

The invention solves the problem of improving reliability by preventing loops geophysical cable around the column tubing when conducting lowering and lifting of the depth of the device, improving the reliability of research results through definitions in operating mode wells.

The task is solved in that in the method of study of a well equipped with a column tubing and sucker rod pump, including the shutdown of the pumping unit when working on the wellhead and pump descent into the well through the annular space on the cable of the device, the start of the pumping unit and sucker rod pumps in operation, conduct after entering the mode of study well, the last stop is conducting research on the operation of the pumping unit and sucker rod pump and removing the device from the well, according to the invention for the descent of the device the operation of sucker rod pump is stopped for a time not more than 20 min, then the device on the cable down through the cable head to two metres after the start of pumping unit and sucker rod pump device continue to be taken down, while restoring the work of the pump to the working level during and after the descent of the instrument in the borehole, when lifting the unit to the wellhead after research it stop at 100 meters to the mouth of the well, then the operation of the pumping unit and sucker rod pump stops, remove the device from the well and restore the operation of the pumping unit and sucker rod of the pump.

The invention consists in the following.

Reliable research well prevents a number of reasons, such as determining the parameters in idle mode pumping equipment, the hanging device in the annular space, the loops of the wireline and other Known technical solutions eliminate these reasons only partially. In the proposed method solves the problem of improving reliability by preventing loops geophysical cable around the column tubing when conducting lowering and lifting of the depth of the device, improving the reliability of research results through the definition of the s when the operating mode of the well. The problem is solved as follows. When researching well-equipped column tubing and sucker rod pump down into the well through the annular space on the wireline device and conduct research. As the wireline use thick wireline diameter > 14 mm This cable, having sufficient rigidity and thickness, is not subject to paleobotany, easily passes through the seal at the wellhead and easily pushed into the hole and retrieved from the well.

As the device uses a small-sized device with a diameter not exceeding 32 mm, This device easily fits into the annular space up and down.

Appropriate devices OWL-3/28, OWL-C3-28-60, AMDT-MP, AGATE-28. The connection cable can be used cables brands KG3×0,75-60-180; KHS×1,5-150-150-4; KG×0,75-75-150.

Cable type CGS×1,5-150-150-4 has the following characteristics:

Feature cable KHS×1,5-150-150-4:

Breaking strength not less than 150 kN.

Outer cable diameter of 14.4 mm

The diameter of the upper part of the cable 10,2-16,4 mm

The diameter of the lower part of the cable 20-38 mm

For descent device to stop the operation of the pumping unit at the wellhead. Accordingly stops the operation of the sucker rod pump. This stop is associated with the safety precautions of the work involves stopping the pumping unit when working on the wellhead. Open the seal, put the device on the cable is two meters in the annulus of the well. Close the seal covering the cable, start the machine-the rocking chair and put the device on the cable down. In the process of descent of the device and after restore a sucker rod pump to the working level. Studies conducted at operating rod pump after working mode. Due to this, achieve data reliability of operation of the well, increasing the information content. In addition, this work remains the productivity of the well. After conducting studies raise the device to the mouth of the well and stop it for 100 meters to the mouth of the well, then stop pumping unit and, accordingly, sucker rod pump, remove the device from the well and restore the operation of the pumping unit and sucker rod pumps.

Such studies may also be performed when swabbing the well, when the stop column tubing in the well (after removing the pump and tubing slid over laboulbeniales). Geophysical studies in the annular space and when swabbing solve the following tasks:

- Determination of the flow profile of fluid from the exploited layers.

- Determination of the integrity of the casing string.

- Determine which of the integrity of the column tubing.

- The definition of cross-flows.

- Positioning of the dynamic level in the annulus.

- Determination of the thickness of the walls of the column, the amount of wear, areas of corrosion, longitudinal and transverse rupture, buckling, swelling.

- Define vodonagrevatel.

- Determination of the temperature of the reservoir and around the wellbore.

- Determination of the effective capacity of the reservoir.

- Determination of the specific gravity of the liquid in the column pointervalue.

- Determination of depth of bottom.

- Determination of the couplings of the production casing and tubing.

- Definition of the natural gamma-ray activity of rocks.

- Determination of the water content of the reservoir with bottom water (radio effect).

Specific example

Conduct research of the oil wells with the following characteristics: the depth of 1730 m, diameter of casing 146 mm, the diameter of the column tubing 73 mm, the depth of the suspension column tubing 1300 m, used pump rod 20-125-RHAM-12-4-3, cable type KTc1×1,5-150-150-4 thickness of 14 mm, the device OWL-3/28 (purpose underlying instrument: to oversee the development and maintenance of oil and gas wells, including surveys through annulus GGP) with a diameter of 28 mm Bore operates in the mode of the number of swings per minute 3,7, the length of policeman is on stock 2.1 m, the flow rate of 6.4 m3/day, the dynamic level 230 m

For descent device to stop the operation of the pumping unit at the wellhead. Accordingly stops the operation of the sucker rod pump. Through the cable cylinder, connect the cable and the device. Open the seal, put the device on the cable 2 m annulus of the well. Close the seal covering the cable, start the machine-the rocking chair and put the device on the cable down. The device is placed at a depth of 1730 m In the process of descent of the device and after restore a sucker rod pump to the working level. Studies conducted at operating rod pump after working mode of the well.

If research determines that the profile of the fluid flowing from the exploited strata, the integrity of the casing, the integrity of the column tubing, annulus fluid flows, the provisions of the dynamic level in the annulus, the thickness of the walls of the column, the amount of wear, areas of corrosion, longitudinal and transverse rupture, buckling, swelling, vodonagrevatel, the temperature of the reservoir and the wellbore, the effective capacity of the reservoir, the weight of liquid in the column pointervalue, the depth of the bottom hole, the coupling of the production casing and tubing, natural gamma-activity of rocks, the water content of the reservoir with bottom water(radio effect).

After conducting studies raise the device and stop 100 meters away from the wellhead. Stop pumping unit and, accordingly, sucker rod pump, remove the device from the well and restore the operation of the pumping unit and sucker rod pumps.

The studies achieve data reliability of operation of the well, increasing the information content, which consists in the brief stop of the pumping unit and as a consequence saving operating mode of the system "reservoir-well" (depression, the steady-state thermal regime in the well) in the research process, the smooth descent of the depth of the device on microbio, while research around the well bore to the bottom without loops geophysical cable due to its rigidity and small size of the depth of the device (no additional weight). By the usual method of descent of the device is Solest underlying instrument and geophysical cable, the machine-rocking forced ostanavlivaut for "rasagiline" device to extract and re-descent, which takes additional time and results are distorted.

The application of the proposed method will improve the reliability and accuracy of results.

Way to research well about Dowanol column tubing and sucker rod pump, including the shutdown of the pumping unit when working on the wellhead and pump descent into the well through the annular space on the cable of the device, the start of the pumping unit and sucker rod pumps in operation, conduct after entering the mode of study well, stop after conducting research on the operation of the pumping unit and sucker rod pump and removing the device from the well, wherein the release device operation rod of the pump is stopped for a time not more than 20 min, then the device on the cable down through the cable head to two metres after the start of pumping unit and sucker rod pump device continue to be taken down, while restoring the work of the pump to the working level during and after the descent of the instrument in the borehole, when lifting the unit to the wellhead after research it stop 100 meters away from the wellhead, then the operation of the pumping unit and sucker rod pump stops, remove the device from the well and restore the operation of the pumping unit and sucker rod pumps.



 

Same patents:

FIELD: oil and gas industry, particularly devices for well survey and oil or gas sample taking.

SUBSTANCE: method involves lifting lubricator; inclining lubricator through 40-45° to vertical line and retaining thereof in inclined position during bottomhole apparatus insertion; lowering lubricator in well and vertically installing thereof on connection unit of well production tree. The simultaneous lifting, inclination, retaining, as well as simultaneous lowering and installation operations are carried out with the use of mechanism. The mechanism comprises two cantilever arms connected one to another by worm gear type screw adapted to bring together and pull apart above arms under handle rotation.

EFFECT: extended possibilities of well survey in difficult-to-access areas characterized by severe climate and geographical environment without the use of hoisting equipment, increased efficiency or work performance due to reduced costs and decreased time of technological operation performing.

2 dwg

FIELD: earth and rock drilling, particularly means for transmitting measuring-signals from the well to the surface.

SUBSTANCE: method involves spooling communication element on a reel; connecting the first end of the communication element to the first user at the first end of the pipe assembly; moving the communication element inside the pipe and connecting the second end of communication element to the second user arranged at the second end of the pipe assembly. The communication element is moved in several stages simultaneously with pipe assembly enlarging or disassembling by displacing the reel inside a pipe under force applied to the reel from the second pipe end and with simultaneous winding or unwinding of the communication element for length equal to reel displacement distance without communication breakage. Continuous communication is provided by linking of the second end of communication element to the second user through traction member during reel displacement or through parallel channel to be temporarily linked up during traction member movement without the reel, which is fastened to pipe assembly at the second end thereof. During pipe assembly enlargement communication element having length exceeding pipe assembly length is provided. The communication element is spooled on the reel. Traction member is inserted in the pipe to be connected and the reel is moved from the first pipe end to the second end thereof. During pipe assembly disassembling the reel is pushed in reverse direction. Device for above method realization includes lifting mechanism and reel. The reel comprises body in which frame with communication element wound on the frame is installed so that the first end of the communication element is provided with means to connect thereof to the first pipe assembly and the first connector to link thereof to the first user. The second end of the communication element is fastened to the reel frame and has the second connector to link thereof with the second user. The device is provided with traction member having length exceeding length of each separate pipe and having members to connect thereof with lifting mechanism from one side and with the reel from another traction member side. The device also has additional branch of communication member to connect the second reel connector to the second user through lifting mechanism. The reel has sealed body and fastening members to secure the reel to the pipe. Outer transversal dimension of the reel body does not exceed inner diameters of pipes included in the assembly. The lifting mechanism has control unit connected with reel body by above communication element branch through traction member.

EFFECT: provision of continuous communication between well head and well bottom during drilling string assembling or disassembling.

17 cl, 2 dwg

Cable adapter sub // 2267002

FIELD: drilling equipment, particularly cable television system used to perform navigational control of directional and horizontal oil and gas well drilling from ground surface and to guide borehole cable rope from inner cavity out of drilling string.

SUBSTANCE: sub comprises threaded connection pipe with thrust end, body with straight and peripheral inclined channels, bush and annular sealing member arranged in straight body channel. Straight body channel is central and provided with cup with inner and outer longitudinal grooves. The bush is installed so that the bush may cooperate with thrust end of threaded connection pipe and has longitudinal extensions arranged in inner longitudinal cup grooves. Annular sealing member comprises extension having orifice and cut for cable introduction into the orifice. The extension is arranged in peripheral inclined channel of the body. Safety means formed as reinforcing member facing straight channel and as elastic member with orifice and cut for cable introduction and arrangement is installed at inclined channel inlet.

EFFECT: increased service life, ease of sub operation and repair.

3 cl, 4 dwg

Uniting device // 2266407

FIELD: survey device to survey wells during drilling and operation, particularly to unite modules during cooperation thereof.

SUBSTANCE: device comprises body including two parts and ball finger. The ball finger has spherical surfaces mating upper body part. The ball finger is fastened by pressing nut. Lower part of ball finger is screwed in lower body part to which sleeve performing limited axial movement is connected. The sleeve movement is limited by retaining nut. Uniting device air-tightness is provided by sealing ring and pressing nut installation.

EFFECT: increased degree of uniting device movement freedom, improved air-tightness.

1 dwg

FIELD: mining industry.

SUBSTANCE: device has post with mounting holes along circle, forks with aperture for holding fork relatively to post, roller and stopper. Upper portion of post and lower portion of fork are made in form of disc, are combined by axes and have mounting apertures along even circle along axis in a way, that angle between post apertures was different from angle between fork apertures.

EFFECT: higher durability, higher precision, higher efficiency, broader functional capabilities, higher personnel and equipment safety.

1 ex, 3 dwg

FIELD: oil industry.

SUBSTANCE: all equipment-hoisting operations are performed during underground well maintenance prior to lowering pumping equipment. Equipment is mounted in tail piece lowered into well. After extraction of pumping equipment from the well, end piece with closed end is lowered, having calculated length, dependent on depth of perforation range. Then specially made branch pipe is lowered into well with slit outlet for geophysical cable. Branch pipe with slit outlet is rigidly connected to pipe pumping filter. Then equipment is lowered into tail piece in such a way, that geophysical cable was inserted through slit outlet into behind-pipe area of well. Further, pumping equipment is lowered, including tubing string, well sucker-rod pump and bars column suspension. In such a way, equipment is effectively positioned in tail piece, and connection to secondary equipment is maintained through geophysical cable, connected to tubing string by braces.

EFFECT: higher safety.

FIELD: oil and gas industry.

SUBSTANCE: device is made with possible use in conjunction with scraper for removal of paraffin precipitations. Device includes end piece for connection to well device and metallic rod with variable cross-section. Rod is made in form of at least three serially placed truncated cones. Cones have double relation of greater diameter to lesser diameter.

EFFECT: higher efficiency.

4 cl, 2 dwg

FIELD: oil and gas extractive industry.

SUBSTANCE: method includes selection of cable of required rigidity and fixing devices on it. Transporting of devices into well is performed under effect from weight of cable and devices. Cable also contains inner hermetic pipe, which is plugged on both sides prior to lowering cable into well. Liquid is pumped into pipe under pressure through locking valve in upper plug and is kept in pipe under constant pressure during operation. After that cable is lowered with devices fixed to it. Value of pressure of liquid in pipe is determined from formula Ppipe≥ Pwell(Scable/Spipe-1)-QcablexLcable/Spipe<Ptear, where Ppipe - pressure of fluid in pipe, kg-wt/sm2; Scable - cross-section of cable with pipe, sm2; Pwell - hydrostatic pressure of well liquid column at depth of planned delivery of devices on cable, kg-wt/sm2; Spipe - cross-section area of pipe aperture and plug area equal to it in contact with liquid in pipe, sm; Qcable - weight of 1 km of cable with pipe, kg-wt; Lcable - length of cable to depth of planned delivery of devices, km; Ptear - pressure of liquid in pipe leading to tear of cable, kg-wt/sm2, determined from formula: Ptear=Ftear/Spipe, where Ftear - tear force for cable according to documentation, kg-wt.

EFFECT: higher efficiency.

3 cl, 1 dwg, 1 tbl

The invention relates to the oil industry and can find application in the operation of horizontal and inclined oil-producing and injection wells

The invention relates to measuring apparatus and can be used in the oil and gas industry and Geophysics to control the spatial position of the wellbore while drilling

FIELD: survey of boreholes or wells, particularly gas well operation control.

SUBSTANCE: signaling device is made as vertical pipe installed in gas pipeline (gathering line or gas well manifold). Upper pipe part has orifices arranged from approach flow side, lower part thereof extends from gas pipeline and provided with ball shutoff valve. Feed pipe is secured from another tap side. The feed pipe is provided with netted flap secured to the pipe and provided with drive linked to two-position regulator along with signaling means, namely lamp or light-emitting diode. Regulator input is connected to pressure drop sensor.

EFFECT: increased reliability and reduced time of information obtaining.

1 dwg

FIELD: oil and gas industry, particularly to stimulate oil production.

SUBSTANCE: oil production is performed along with controlling of oil production parameters and speed of submersible pump electromotor rotation to maintain optimal values of oil production process parameters. Liquid level in well is chosen as the main oil production process parameter. Volume of liquid to be produced is chosen as parameter to be optimized. Control operation is carried out in several stages in automatic mode. At the first stage initial liquid level in well corresponding to calculated level, which provides maximal liquid inflow into well, is specified in pump motor control unit and pump operational mode is selected so that volume of liquid extracted from well is equal to volume of liquid flowing into well for the predetermined time period. Then liquid level corresponding to above situation is recorded and stored in memory. At the second stage predetermined initial liquid level in well is determined and then influx flow and extracted flow are equalized by pump mode of operation. Obtained value of extracted flow is compared with that at previous stage. If above value exceeds that obtained at previous stage predetermined liquid level is also increased and influx flow and extracted flow are equalized by pump mode of operation to increase predetermined liquid level in well in several stages up to corresponding extracted flow volume reduction. After that one backward step is executed, predetermined extracted liquid level corresponding to above step is taken as optimal level and above level is maintained during well operation. If extracted liquid volume decreases at the second stage predetermined liquid level change direction is performed in reverse order and then all above operations are repeated beginning from the second stage. Device for above method realization comprises electromotor to activate pumping jack, which is connected with submersible pump, extractable liquid volume sensors, well liquid pressure sensors connected to electromotor control unit. The control unit comprises serially connected memory means, frequency regulator and voltage changer. Control device is also provided with acoustic depth finding sensor, which determines liquid level in well and is installed at well head. The acoustic depth finding sensor is connected to one frequency regulator input. Extracted liquid volume sensor is connected to one input of memory means having the second input connected to command operator's console. Well liquid pressure sensor is connected to the second input of frequency regulator having output connected to electromotor through voltage changer.

EFFECT: increased oil output.

1 dwg

FIELD: means for transmitting measuring-signals from the well to the surface, for instance for logging while drilling.

SUBSTANCE: device comprises downhole telemetering system with downhole instrument installed in drilling string or in casing pipe, as well as land-based receiving-and-transforming assembly. Connected to downhole instrument are power source and transmission coil. Transmission coil is wound on outer surface of drilling string or casing pipe made of magnetic material and threadedly connected with downhole telemetering system body. Transmission coil is connected with downhole instrument output by the first coil end and with drilling string or casing pipe by the second end thereof. Receiving coil is installed in upper flow string part. Land-based receiving-and-transforming assembly includes receiving coil installed in upper part of drilling string, receiving device having input connected with the receiving coil and output linked to computer. Transmission coil may be enclosed with protective cover or case. Protective cover is formed of dielectric material.

EFFECT: provision of information transmission through shielding layers with high conductivity without information garbling.

3 cl, 1 dwg

FIELD: oil and gas industry, particularly devices for well survey and oil or gas sample taking.

SUBSTANCE: method involves lifting lubricator; inclining lubricator through 40-45° to vertical line and retaining thereof in inclined position during bottomhole apparatus insertion; lowering lubricator in well and vertically installing thereof on connection unit of well production tree. The simultaneous lifting, inclination, retaining, as well as simultaneous lowering and installation operations are carried out with the use of mechanism. The mechanism comprises two cantilever arms connected one to another by worm gear type screw adapted to bring together and pull apart above arms under handle rotation.

EFFECT: extended possibilities of well survey in difficult-to-access areas characterized by severe climate and geographical environment without the use of hoisting equipment, increased efficiency or work performance due to reduced costs and decreased time of technological operation performing.

2 dwg

FIELD: oil and gas well drilling and operation, particularly to transmit down-hole information.

SUBSTANCE: connection device comprises body made as sub with transversal and longitudinal orifices in sub body. The sub is connected with radiator and provided with centering means fixed from axial and radial displacement in the sub. The centering means has cavity and radial ribs. Orifice mating transversal sub orifice is created in one rib. Transmitting coil lead extends through longitudinal and transversal sub orifices and through orifice made in centering means rib and is linked to down-hole instrument connector. Transversal sub orifice is sealed with plug from outer orifice side. The plug is provided with sealing collar. To restrict centering means from axial and radial displacement hollow bush may be used. Hollow bush is inserted in transversal orifice made in centering means rib. The orifices and centering means may be filled with sealant.

EFFECT: provision of signal passage through screening layers having high passability and via casing pipe string.

3 cl, 1 dwg

FIELD: oil production, particularly systems to maintain formation pressure during oil deposit development.

SUBSTANCE: device comprises flow string with downhole pumping plant made as multistage centrifugal pump with submersible electrical motor, power cable, land-based power supply and control unit, packer to separate water receiving and water releasing formations of well unit to reduce mechanical impurities content. Device also has well flow transducer, which comprises composite through body with two channels, flow rotation means and flow straightening means with hill-shaped annular groove adapted for ball receiving formed in-between. The well flow transducer also has control unit, which controls annular ball movement along annular toroidal groove. Well flow transducer body is composed of at least two parts. Outer body part comprises seat for detachably central part receiving. Locking means, which retains body parts in mutually connected state is arranged in outer body part. Flow rotation and straightening means are secured to the central part. Annular groove is made in outer part directly over the seat.

EFFECT: improved use properties due control of water volume to be transferred and mechanical injury content in water, possibility to use flow meter included in water transfer device inside well.

2 cl, 3 dwg

FIELD: oil production, particularly to activate equipment used for productive formation perforation and isolation, rock sample taking and accident elimination.

SUBSTANCE: method involves lowering perforating equipment connected to pipes in well and triggering charge initiation means by connecting above means to current source. The current source is self-contained current source located in down-hole equipment. To connect self-contained current source to initiation means corresponding command is given by discrete pipe string rotation with different angular velocities. Initiation means actuation is carried out along with predetermined depth control. Device for above method implementation comprises land-based module and down-hole module. Down-hole module comprises charge initiation means, for instance glowing filament, self-contained current source connected to initiation means, communication means, indicator, microprocessor, pressure relay, motion sensor, three electronic keys and two voltage changers. Self-contained power source is linked to input of the first voltage changer and input of the first electronic key. Outputs of the first voltage changer are connected with inputs of microprocessor power supply units, motion sensors and pressure relay. Output of motion sensor is linked to the first microprocessor input. Pressure relay output is attached to input of the first electronic key control. Output thereof is connected to input of the third electronic key through serially connected the second electronic key and the second voltage changer. Two microprocessor outputs are linked correspondingly to inputs of indicator and the third electronic key control. Output of the third electronic key is connected with initiation means input.

EFFECT: increased reliability of perforating equipment activation inside well.

2 cl, 2 dwg

FIELD: mining, particularly electric spacers adapted to transmit drilling direction information.

SUBSTANCE: covering comprises steel substrate, damping layer, insulation layer and glass tissue layer, which are overlapped and connected to the substrate. The damping layer has nickel-aluminum base and is applied by gas-thermal spraying method. Insulation layer is formed of metal oxides, for instance of aluminum oxide, is impregnated with enamel or varnish and is applied by the same method. Glass tissue layer is impregnated with mixture including epoxy resin and metal oxide filler.

EFFECT: increased reliability and service life.

1 dwg

FIELD: oil and gas industry, particularly well operation.

SUBSTANCE: method of air-tightness determination involves measuring background pressure in tubing-casing annulus; providing gas-dynamic connection at well head between hole annuity and tubing-casing annulus at moment of background pressure stabilization in tubing-casing annulus; increasing background pressure in tubing-casing annulus in several stages to reach maximal possible test pressure , wherein the pressure increase is 1 MPa for each stage, along with performing time-delay at each stage to relax and stabilize tubing-casing annulus pressure. If tubing-casing annulus pressure is time-stabilized at last stage well head conductor or extension pipe part air-tightness is assumed to be perfect. If tubing-casing annulus pressure is reduced at one stage after relaxation operation the pressure value is recorded in relaxation termination period. Then time-delay is carried out until pressure stabilization in tubing-casing annulus, time-delay duration and pressure values are recorded and compared with background pressure value. If tubing-casing annulus pressure exceeds background pressure one may make a decision that the well may be operated under above tubing-casing annulus pressure, which does not exceed recorded stabilization pressure value. If tubing-casing annulus pressure is equal to background pressure one may make a decision that well head conductor or extension pipe part has not sufficient air-tightness. Then gas is discharged from tubing-casing annulus to obtain value of 0.9Pst with taking into consideration time and volume of gas to be discharged and with time delay, which provides pressure release and stabilization in tubing-casing annulus. The last values are recorded and residual gas is released from tubing-casing annulus. Then constant inflowing gas yield is measured and tubing-casing annulus gas leakage value is determined from a given relation. If gas leakage value is lesser than 70 m3/day one may make a decision that well may be operated along with tubing-casing annulus gas bleeding for gas combustion in flare when pressure value reaches value equal to background pressure value. If gas leakage value is greater than 70 m3/day one may make a decision that well operation must be stopped to perform well isolation works.

EFFECT: increased information validity.

3 dwg, 2 ex

FIELD: well drilling, particularly to change bottomhole characteristics during well drilling.

SUBSTANCE: telemetric system comprises land-bases receiving and processing equipment, electric string separator, alternating current generator installed below the separator and downhole equipment with measuring sensors and with electronic transmission unit. Electronic transmission unit is linked to the alternating current generator from above through electrical connector for power cable. Self-contained power supply module and measuring downhole equipment modules are connected to the generator by low-power wires through lower electric connector.

EFFECT: simplified structure and increased reliability of bottomhole telemetric system.

1 dwg

FIELD: mining industry.

SUBSTANCE: invention can be used in case of gas-lift operation of wells equipped by free piston-type installations. Invention envisages stopping well, connecting tube space and annular space in wellhead, recording bottom zone and wellhead pressures in tube and annular spaces, and computing well operation parameters using inflow curve plotted according to differences of bottom zone and wellhead pressures. Volume of produced fluid is found from potential output of formation and from condition of output of free piston. When comparing these volumes, parameters of well are computed in the base of minimum volume value.

EFFECT: optimized well operation.

2 dwg