Thermal power station operating process

FIELD: thermal engineering; power generation.

SUBSTANCE: proposed operating process of thermal power station is characterized in that full-flow condensate is heated in low- and high-pressure regenerative heaters by steam extracted from turbines and back-pressure steam is cooled down in circulating-water turbine condenser. Part of full-flow condensate is additionally heated in heat-pump plant condenser connected in parallel with low-pressure heater second along full-flow condensate path; circulating water heated in turbine condenser is used as low-potential heat source in heat-pump plant.

EFFECT: enhanced economic efficiency of thermal; power station.

1 cl, 1 dwg

 

The invention relates to the field of power engineering and can be used at thermal power stations.

Known equivalent ways of working of thermal power stations, for which the regenerative preheating of the main turbine condensate is in the regenerative heaters low and high pressure extraction steam turbine. The spent cooling steam produced by the circulating water, the warmth which disperses into the atmosphere (see the book Ejaculate "district Heating and heat networks". - M: Publishing house of MPEI, 2001, rib on s). This analog adopted as a prototype.

The disadvantage of analogs and prototypes is the low efficiency of thermal power plants due to the loss of heat removed from the condenser circulating water.

The technical result achieved by the present invention is to improve efficiency in thermal power plants by reducing the heat loss of the heated circulating water and improve the efficiency of the regenerative preheating of feedwater flow.

To achieve the technical result, a method of operating thermal power station, at which the main turbine condensate is heated in the regenerative heaters low and high pressure extraction steam turbine,the exhaust turbine the steam is cooled in the turbine condenser circulating water.

The difference of the proposed method of operating thermal power station is that part of the main turbine condensate is additionally heated in the condenser heat pump installation, included on a course parallel to the second main condensate regenerative heater low pressure, and as a low-grade source of heat in heat pump installation use heated in the turbine condenser circulating water.

New hallmark describing the method of operation of a thermal power station, allows you to increase the profitability of its operation.

Next, consider the information, confirming the ability of the invention to provide the above technical result.

The drawing shows a schematic diagram of thermal power station, explaining the proposed method.

Thermal power plant includes a steam boiler 1 steam turbine 2 to the capacitor 3 connected to the piping chilled 4 and heated 5 circulating water, and the pipeline of the main condensate turbine 6, which included condensate pump 7, and regenerative heaters low 8, 9, 10, 11, and high 12 pressure connected to the regenerative pair selections. The station is equipped with a heat pump system, consisting of a capacitor is 13, throttling device 14, an evaporator 15 and the compressor 16. On the cold side of the evaporator heat pump installation 15 included in the piping hot water circulation 5. In the heated environment, the condenser heat pump installation 13 included in the pipeline of the main condensate after the first 6 in the course of the condensation of the regenerative heater low pressure 8 parallel to the heater low pressure second stage 9.

The method of operation of a thermal power station consists of the following operations.

For realization of regenerative preheating of condensate in the exhaust turbine 2 steam the entire flow of feed water condensate pump 7 served in the regenerative heater low pressure first stage 8. Then feed water is divided into two streams, the heat which is produced in parallel using different operations. The first stream is heated by extraction steam turbine 2 in the regenerative heater low pressure second stage 9. The second stream is heated in the condenser of the heat pump unit 13 the heat taken away by the evaporator of the heat pump unit 15 from the heated circulating water from the pipeline 5. After this, the flow of feed water successively heated in the regenerative heaters low 10, 11 and high 12 pressures.

Thus, the proposed method of operating thermal power station allows isit profitability of its operation through efficient use of the heat of the heated circulating water in the regenerative system of the station.

The method of operation of a thermal power station, at which the main turbine condensate is heated in the regenerative heaters low and high pressure extraction steam turbine, the exhaust turbine the steam is cooled in the turbine condenser circulating water, characterized in that the part of the main turbine condensate is additionally heated in the condenser heat pump installation, included on a course parallel to the second main condensate regenerative heater low pressure, and as a low-grade source of heat in heat pump installation use heated in the turbine condenser circulating water.



 

Same patents:

FIELD: heat power engineering.

SUBSTANCE: invention can be used for heating system water. Proposed thermal power station contains return and feed system water pipelines between which lower and upper system heaters of extraction turbine are connected, turbine condenser is connected with pipelines of cooling and heated circulation water, heat pump plant with condenser and evaporator, the latter being connected to pipeline of heated circulation water. Thermal power station includes heat pump plant whose condenser is connected to system water pipeline after lower system heater.

EFFECT: increased economy of thermal power station.

1 dwg

FIELD: heat power engineering.

SUBSTANCE: invention can be used for heating system water. Proposed thermal power station contains extraction turbine with heating steam extraction, heating system feed and return pipelines, heating system heaters connected by heated medium line between feed and return pipelines of heating system and connected by heating medium lines to heating extractions, heat pump plant with evaporator placed in heating system return pipeline, and condenser. Condenser of heat pump plant is connected to heating system feed pipeline after heating system heaters.

EFFECT: increased economy of thermal power station.

1 dwg

FIELD: heat power engineering.

SUBSTANCE: invention is designed for heating system water. According to proposed method, system water getting from consumers is directed to evaporator of heat pump plant for use as low-potential heat source, it is heated in condenser of heat pump plant and in system heaters of extraction turbines. Heating of entire flow of system water in condenser of heat pump plant is carried out after heating of water in system heaters of extraction turbines.

EFFECT: increased economy of thermal power station in operation.

1 dwg

FIELD: heat power engineering.

SUBSTANCE: proposed thermal power station contains steam turbine with condenser to which cooled and heated circulation water pipelines are connected, and also turbine main condensate pipeline which includes low-pressure regenerative heaters connected to regenerative steam extractions. Heat pump plant evaporator is included into heated circulation water pipeline. Condenser of heat pump plant is connected through heated medium line into main condensate pipeline after first condensate low-pressure regenerative heater in direction of condensate flow in parallel with low-pressure heater of second stage.

EFFECT: improved economy of heat thermal power stations.

1 dwg

FIELD: heat-and-power engineering.

SUBSTANCE: thermoelectric power plant intends for warming of heating-system water. Thermoelectric power plant has heating-system water delivery line and return line, steam turbine provided with heating water withdrawal and capacitor. Capacitor is connected with circulation water delivery conduit and rundown pipe; circuit heaters are connected between heating-system water delivery and rundown conduits. The capacitors are connected with heating devices through heating medium. Station also has thermal pump assembly which has evaporator connected to rundown conduit of circulation water. Capacitor of thermal pump assembly is connected to heating-system water delivery line through medium to be warmed behind circuit heaters.

EFFECT: improved economy of thermoelectric power station.

1 dwg

FIELD: power engineering and refrigerating facilities.

SUBSTANCE: according to proposed method, part of water cooled in tower is cooled in evaporator of absorption lithium bromide refrigerating machine and it is then mixed with main water flow from tower to condenser of power-generating unit. Mechanical draft tower is used for cooling condenser and absorber of refrigerating machine.

EFFECT: reduced temperature in turbine condenser contributing to generation of additional electric energy in interheating periods.

1 dwg

FIELD: heat supply systems.

SUBSTANCE: proposed steam power plant with additional steam turbines includes power-and-heating plant with open power and heat supply system, gas-turbine plant with recovery boiler and make-up water heating and deaerating unit including at least two additional steam turbines with contact condensers which are placed in softened make up water line. Output of power and heating plant unit is connected by pipeline with input of contact condensers of additional steam turbines of make up water heating and deaerating unit. Output of steam recovery boiler unit of gas-turbine plant unit is connected by steam line with input of additional steam turbines. Input of steam recovery is connected by feed water pipeline with make up water heating and deaerating unit. Output of make up water heating and deaerating unit is connected by make up deaerated water pipeline with system heaters of power and heating plant unit and by feed water pipeline, with input of recovery boiler of gas-turbine plant.

EFFECT: facilitated deaeration and reduced cost of make up water deaeration system of heat supply system increased power and economy of power and heating plant.

2 dwg

FIELD: power and heat generation.

SUBSTANCE: proposed power and heating plant with open power and heat supply system including boiler unit, steam turbine, deaerator and feed pump includes steam-gas turbine plant unit with low-pressure afterburning chamber, steam gas mixture heat recovery unit containing recovery boiler with high-and-pressure steam generators, spraying device, gas cooler-condenser and separated water utilization unit. Separated water utilization unit is connected with input of low-pressure steam generator of recovery boiler through water softening set and deaerator. Spraying device is connected with raw water softening device of power and heating plant. Input of high-pressure steam generator of recovery boiler is connected with output of steam-gas-turbine plant. Low-pressure steam generator of recovery boiler is connected with additional afterburning chamber of steam-gas turbine plant. Separated water utilization unit is connected by pipeline of softened and deaerated low-pressure feed water with steam-gas mixture heat recovery unit and pipeline of softened, heated and deaerated make-up water with open power and heat supply system. High-pressure steam generator is connected by feed water and steam pipelines with power and heating plant.

EFFECT: provision of effective modernization of steam turbine power and heating plants with increase of power and economy.

2 dwg

FIELD: heat power engineering.

SUBSTANCE: according to proposed method system water is heated in system heaters by steam of heating extractions of extraction turbine. Make up water of heat supply system is deaerated before delivering into return pipeline. For this purpose source and overheated water is delivered into deaerator. Maintaining of preset concentration of oxygen dissolved in deaerated make up water is provided by successive regulation of temperature of source water and rate of flash steam. If concentration of dissolved oxygen exceeds preset value, first, temperature of source water is raised and then, if necessary, rate of flash steam is increased and on the contrary, if concentration of oxygen is lower than preset value, first rate of flash steam is reduced and then temperature of source water.

EFFECT: increased efficiency and economy of thermal power station.

1 dwg

FIELD: power engineering.

SUBSTANCE: method includes utilization of heat exhausted from additional steam-gas turbine plant for generation of high pressure steam and additional low pressure steam. High pressure steam is sent to and expanded in thermal steam turbine. Low pressure steam is fed to additional low pressure combustion chamber of steam-gas turbine plant, additional fuel is sent same way as steam, and temperature of steam-gas mixture is set mainly at level close to 900°C and it is expanded in low pressure steam-gas turbine. Nutritious water for generation of high pressure steam is fed from deaerator of high pressure heating and electrical line. Into steam-gas mixture, cooled down during generation of low pressure steam, irrigation water is injected, steam component of this steam-gas mixture is condensed, formed condensate is separated and drained into tank for separated water, from which cooled down irrigation water is fed for condensation of steam in steam-gas mixture. Least portion of separated water is used as nutritious water for generation of low pressure steam. Heat of most portion of separated water is used to heat a portion of network water from closed thermal system of main electrical and heating line.

EFFECT: higher efficiency.

2 dwg

FIELD: heat power engineering.

SUBSTANCE: invention can be used in thermal power stations for economic automated control of steam-turbine power-generating units under nominal and sliding pressure conditions. According to invention, regulative valves on lines delivering steam to turbine are kept fully open under all operating conditions of power-generating unit. To change over from one steady-state mode to the other within the limits of rated load, fuel feed regulating valves and feed water regulating valves delivering fuel and water into boiler are acted upon. To change over for load exceeding rated one, regulating valves on lines of steam extraction for regeneration, which are also fully opened, are partially closed. Valves delivering steam to turbine are partially closed for a short period of time when frequency in power supply network deviates from tolerable value, with subsequent return of valves in initial fully open state after setting of frequency within preset limits.

EFFECT: provision of operation of steam-turbine power-generating unit under all loads with minimum losses for steam throttling, materially increased economy of operation.

2 cl, 1 dwg

FIELD: heat power engineering.

SUBSTANCE: proposed thermal power station contains steam turbine with condenser to which cooled and heated circulation water pipelines are connected, and also turbine main condensate pipeline which includes low-pressure regenerative heaters connected to regenerative steam extractions. Heat pump plant evaporator is included into heated circulation water pipeline. Condenser of heat pump plant is connected through heated medium line into main condensate pipeline after first condensate low-pressure regenerative heater in direction of condensate flow in parallel with low-pressure heater of second stage.

EFFECT: improved economy of heat thermal power stations.

1 dwg

FIELD: heat power engineering.

SUBSTANCE: according to proposed method, steam from turbine extractions is fed to regenerative high and low pressure heaters in which main condensate, after turbine condenser, and feed water are heated successively, and primary makeup water is delivered to heat supply system makeup water preparation plant and is deaerated in vacuum deaerator. Primary water is heated in lower low-pressure regenerative heater nearest to condenser before heat supply system makeup water preparation plant, and regenerative heating of main condensate of turbine is started in low-pressure heater, second from turbine condenser.

EFFECT: increased economy and improved reliability of thermal power station owing to heating of primary water to technologically required temperatures by highly economic low-potential extraction of turbine steam at minimum capital layouts for reconstruction of circuit of thermal power station without fitting special primary water heater.

1 dwg

FIELD: heat power engineering.

SUBSTANCE: invention can be used for creating superposed gas-turbine plants to form steam-gas plants in operating thermal power station by equipping it with higher efficiency steam-turbine units. In proposed steam-turbine units regeneration system of steam turbine is partially bypassed with replacement of steam heating of water in this part of regenerative heat exchangers by gas heating. Steam-turbine unit is made in form of higher efficiency unit with bypass of steam turbine high pressure regeneration and part of heating boiler surfaces. Said bypass with included heating surfaces is arranged in convection gas conduit and is connected by its inlet part to part of high-pressure duct of said steam boiler of corresponding parameters. Gas heater of condensate of steam-turbine unit can be installed additionally in separate convection gas conduit in direction of gas flow after surfaces bypassing high pressure regeneration.

EFFECT: simplified design and control of plant, reduced overall dimensions and weight of heating surfaces of separate convection gas conduit at increased power rating of steam-turbine plants.

2 cl, 1 dwg

FIELD: power engineering.

SUBSTANCE: proposed thermal power station has fuel combustion set, tank with fuel, pipelines to feed fuel into furnace chamber, cocks, injectors, furnace chamber, steam turbine and reservoir with droppings connected by pipeline through cock with pipeline delivering fuel into furnace chamber.

EFFECT: improved efficiency of operation of thermal power station.

1 dwg

FIELD: power engineering and refrigerating facilities.

SUBSTANCE: according to proposed method, part of water cooled in tower is cooled in evaporator of absorption lithium bromide refrigerating machine and it is then mixed with main water flow from tower to condenser of power-generating unit. Mechanical draft tower is used for cooling condenser and absorber of refrigerating machine.

EFFECT: reduced temperature in turbine condenser contributing to generation of additional electric energy in interheating periods.

1 dwg

FIELD: power engineering.

SUBSTANCE: in proposed thermal power station containing steam generator, steam turbine, electric generator, and condenser, well tubes are arranged in vertical plane in lower layers of Earth's crust and are made to release thermal energy from lower layers of Earth's crust and receive renewable thermal energy. Tubes of well are installed under sea or ocean bottom in deep water chutes or cracks of Earth's crust or cavities on sea bottom or land. Well tubes can be arranged on sea bottom or land in parallel rows or in form of rectangular rings or spirals, shuttle, stars or radially. Tubes are connected in pairs at angle. Tubes connected to each other form together with pumps, turbine, condenser and deaerator, a closed system. Pump, turbine, generator, vacuum pump are installed on platform under bell housing. Platform is rigidly and hermetically connected with belt housing. Outer surfaces of turbine and condenser are provided with thermal elements of thermoelectric generator. Condenser is combined with platform, being made in form of vertical and horizontal communicating tubes connected with vacuum pump and vacuum regulator. Deaerator is provided with liquid level regulator.

EFFECT: reduced cost and consumption of materials at production of cheap renewable fuel, conversion of heat into electric energy.

8 dwg

FIELD: heat power engineering.

SUBSTANCE: proposed system consists of steam turbine 1, turbogenerator 2 and boiler. Turbine 1 is opened by acting onto valves 4 using governor 3 governor 3 is set into operation under action of centrifugal pendulum 5, electric motor 6, electrohydraulic converter 7 and manual control mechanism 8. Sensor 9 improves sensitivity of system actuating members. System is furnished also with control pressure sensor 10, controllable opening setter 11 of turbine 1, amplifiers 14 and 15, limiter 16 and proportional differential converter 17. To decrease nonlinearity of "frequency-power" curve of tubular 1 system is furnished with division unit 18, pressure sensor 19 is control stage of high-pressure cylinder of turbine 1, pressure sensor 20 before turbine 1 and change-over switch 21.

EFFECT: provision of automatic control of power of generating unit at considerable reduction of dead zone in frequency and nonlinearity of "frequency-power" curve of turbine operating in network.

3 cl, 1 dwg

FIELD: atomic technique and heat-exchanging engineering.

SUBSTANCE: in the mode of exploiting of an atomic steam-turbine plant the steam which is going out of a hot-water generator is pressed to get higher pressure at least in one for example in a multi-stage compressor primarily with cooling off its stages with feed water of an installation. The atomic steam-turbine plant has corresponding equipment for execution of declared mode of exploitation. The invention allows to increase efficiency of a single electric( and outlet thermal} power of operating and newly built atomic steam-turbine plants producing with nominal evaporative capacity of their reactor installations of electricity for atomic electric power stations and at necessity of thermal power for atomic thermoelectric power stations. At that besides summary economy of used nuclear and organic fuel and also of reducing summary capital expenditures on building stations improving main index of total effectiveness of electric or thermal stations would be achieved.

EFFECT: reduces cost of an established kilowatt of the energetic installation.

6 cl, 3 dwg

FIELD: thermal engineering; designing new and updating existing steam-turbine units.

SUBSTANCE: proposed steam-turbine unit has boiler communicating through steam line with turbine, regenerative heaters, and condenser, as well as second boiler communicating through steam line with second turbine and incorporating regenerative system and delivery water boiler; pipeline feeding delivery water to second-turbine boiler communicates through piping with condensate feeding line downstream of one of first-turbine regenerative heaters; pipeline passing delivery water discharged from second-turbine boiler communicates through piping with condensate feeding line at inlet of next regenerative heater of first turbine; in addition, gate valve is installed on condensate line between these regenerative heaters. Such cycle arrangement provides for operation of back-pressure turbine irrespective of presence or absence of heat and power loads thereby eliminating long-time outages of equipment.

EFFECT: enhanced economic efficiency compared with arrangements where both turbines operate separately.

1 cl, 1 dwg

FIELD: thermal engineering; thermal power stations.

SUBSTANCE: proposed operating process of thermal power station is as follows. Boiler-generated steam is conveyed to turbine wherefrom it is supplied to condenser for condensing it; full-flow condensate is delivered by means of condensate pump to low-pressure regenerative heaters and then to high-pressure deaerator; makeup water is deaerated in atmospheric-pressure deaerator and conveyed to full-flow condensate path, vented steam being discharged from atmospheric-pressure deaerator into atmosphere. Flowrate of vented steam discharged from atmospheric-pressure deaerator is regulated with respect to desired content of oxygen dissolved in mixed flow of makeup water and full-flow condensate beyond vacuum system of turbine unit, for instance downstream of low-pressure heater second along full-flow-condensate path.

EFFECT: enhanced economic efficiency and operating reliability of thermal power station.

1 cl, 1 dwg