Method of mounting long pipe

FIELD: pipe line transport; major repair of pipe lines.

SUBSTANCE: proposed method includes introducing the front end of pipe into damage pipe and forming hermetic cavity in inter-pipe space; then, pressure air (gas) is charged into hermetic cavity for motion of new pipe inside damaged pipe, after which piston is fitted at end of new pipe and detachable flange is connected to rear end of damaged pipe; motion of new pipe is effected by periodic charging of air into hermetic cavities; each hermetic cavity is bounded by piston and seal.

EFFECT: reduction of tractive force.

5 dwg

 

The invention relates to pipeline transport of oil and gas.

Overhaul of oil and gas pipes carried out in different ways. There is a method of capital repairs of the pipeline, where digging a trench at the site deteriorated pipe, remove it and replace with new pipe [Goferman and other Repair of gas pipelines. M.: Nedra, 1973, page 107].

This method is more expensive than the construction of a new pipeline, as well as works associated with the installation of the new pipe, includes works by removing the deteriorated pipe. While earthworks represent a significant portion of all works.

Famous considered as a prototype method of repair of the pipeline, including laying new pipe inside the worn part of the pipeline.

The new pipe choke from the front and rear ends, introducing worn pipe. The driving force to move the installed pipe creates internal pressure of the air on the front of her cap [a Patent for the invention № 2195598. , Moscow, December 27, 2002].

The disadvantage of this method is the limited length of the installed pipe, since the driving force is created here by the pressure of the air (gas) only for one piston. The increase of the driving force by increasing the pressure of the air (gas) is limited by the strength of the IPMS is elevated pipe.

The objective of the invention is a method of capital repairs out-of-date oil and gas pipes by installing inside the new long tube, create to move rather more effort provided a significant reduction in the works to install new pipe and excavation operations.

This is achieved by the proposed method of installing long tube inside the worn out oil and gas pipes.

In figure 1, figure 2, figure 3, figure 4, figure 5 shows the device and the implementation of the proposed method of installation of long pipes.

The device (1) contains the piston 1, is fixed on the front end of the installed pipe 2, a detachable flange 3 attached to the rear end of the deteriorated pipe 5. On detachable flange 3 is fixed to the seal 4, the split flange 6 connects intermediate the ends of the deteriorated pipe. To supply air (gas) are the pipes 8 and 9.

When installing the pipe 2 to the original position to move in the pipe 5 is used pipelayer 7 and tables 10 and 11.

The method of installing long tube new inside the deteriorated pipe is as follows.

On the road deteriorated pipe 5 (Fig 1) dig a trench 12 and the wells 13 and 14. The trench 12 is located at the beginning of the deteriorated pipe, the well 14 at its end, and the well 13 is intermediate intermediate position relates is correctly worn-out pipe 5. Areas of deteriorated pipe 5 located in the pit 12 and the wells 13 and 14, are removed.

Prepared for the installation of a new pipe 2 through pipe layer 7 is placed on the tables 10 and 11. On the front end of the new pipe 2 is fixed to the piston 1 (Fig 1), detachable flange 3 with the seal 4 is installed on the piston 1 and the pipe 2 and attach it to a worn pipe 5. The ends of the deteriorated pipe 5 located in the well 13, connect the detachable flange 6, fixing it on the ends of the tube 5. To split flanges 3 and 6 are attached respectively to the nozzles 8 and 9.

The pipe 8 serves the air (gas) under pressure to start and continue movements of the pipe 2 under the action of air pressure (of gas) on the piston 1, is mounted on the pipe 2. The pressure of the air (gas) discharged when the piston 1 with the pipe 2 positions at the front in the direction of the end of the demountable flange 6 (figure 2 )and the piston 1 and the installed pipe 2 is stopped.

Then prepare the next stage of the movement of the pipe (figure 3). Detachable flange 3 is removed and the pipe 2 installing the piston 16, and then split flange 3 seal 4 return to its original position. At the same time remove the detachable flange 6 and set in it the seal 15 and return it to its former place, fastening with worn-out pipe 5. The result is a new pipe 2 prepared for the next move.

H is cut the pipe 8 serves the air (gas) into the cavity of the annulus, limited seal 4 and the piston 16, and at the same time through the pipe 9 serves the air (gas) into the cavity of the annulus bounded by the piston 1 and the seal 15 (figure 3). This creates pressure on the pistons 1 and 16, resulting in the movement of the pipe 2 and supporting it to the exit of the piston 1 into the well 14 and to move the piston 16 in a detachable flange 6 (figure 4), the air pressure dropped.

This completes the move to a new tube. For the final installation of the new pipe remove the split flanges 3 and 6 (figure 4) vested in them respectively seals 4 and 15 and remove the pistons 1 and 16. The ends of installed pipe 2 (figure 5)extending into the well 14 and the trench 12, connect the transitional pipes 17 and 18 with the ends 19 and 20 of the working tube 2. The pit and wells buried, the repair is finished.

In the considered case of implementation of the method of installing long tube shows the use of two wells (13 and 14) and two pistons 1 and 16, the determining force of the moving set of the new pipe, which is created by the pressure of the air (gas) in two of the piston. This limits the length of the installed pipe. For the General case of installation of a longer pipe resistance force to movement of the pipe increases. This necessitates an increase in the driving force, and therefore, increase the number of pistons and wells at the condition of the pressure, d is ha (gas).

Set dependence, which defines the number of pistons and wells from the length of the floating pipe. The power of resistance to movement of the pipe Qcis determined by the expression

Here

L is the length of the installed pipe (length deteriorated pipe);

g1- weight per unit length of the installed pipe;

fCR- the coefficient of sliding friction roaming pipe on the inner surface of the deteriorated pipe.

The driving force behind the movement of the pipe is determined by the pressure of the air (gas) on the pistons.

Here

n is the number of wells (pistons);

p - pressure air (gas) in the annular cavity (pressure on the piston);

Dn- the outer diameter of the deteriorated pipe

dn- outer diameter of the installed pipe,

δ the wall thickness of the deteriorated pipe.

The length of a section of worn-out pipes subject to major repairs, determines the length L of the new pipe, which is in the process of repair, move, using pistons to be installed on the new pipe in wells. The number of wells (pistons) from the condition of equality of the forces driving and resisting attached to a floating tube with a constant velocity, will be:

For example, consider the installation of a new pipe under the conditions: L=104m, Dn=1420 mm, ´ =20 mm, dn=1220 mm, fCR=0,05,

Using the dimension of t and m, we get

Therefore, you must use the pistons 11 and 11 wells.

Traction force is required to move the tube length of 10 km will be 350 tons

Earthworks on the length of 10 km, with the digging of wells in length each 3...4 m and one of the pit length 50...60 m will be about 100 m, then there is no more than 1% of the length of the track, which is worn-out pipe, the distance between the wells is about 1 km. This will be determined by the small excavation in the overhaul of oil and gas pipelines, low energy consumption and efficiency of the proposed method of installation of long pipes.

The method of installing long tube, which consists in the introduction of the front end of the installed pipe in worn-out pipe that is created in the annular space sealed cavity, the injection of air (gas) pressure in the sealed cavity to move the installed pipe inside the deteriorated pipe placement on the front end of the installed pipe piston and accession to the rear end of the deteriorated pipe plug flange with fixed therein by a seal, characterized in that the movement of stacked pipes carried out periodically Sukachev is an air tight cavity, limited each piston and seal.



 

Same patents:

FIELD: construction engineering; erection of pipe lines in permafrost soils at alternating terrain.

SUBSTANCE: trench in smooth terrain and in sections cut by hydrographic net is dug in active layer at depth sufficient for location of upper generatrix of pipe line above level of daily level. Prior to laying the pipe line, bottom walls and berms of trench are lined with cloth of non-woven synthetic material. backfill soil is placed in ballasting polymer panel-type devices or in ballasting polymer container-type units suspended from pipe line. Anti-erosion partitions made from non-woven synthetic material are formed in sloping sections together with funnel whose neck is located downward of water flow embracing the pipe line at specified clearance between neck and pipe line. Funnel is formed by covering the natural slope of backfill soil by free lower edge of non-woven synthetic material with ballasting polymer panel-type or ballasting polymer container-type devices placed on lower portion of funnel followed by subsequent removal of embankment protecting the pipe line. As far as sections of route cut by hydrographic network are concerned, anti-erosion partitions are formed in trench at transients with opposite slopes of microterrain; anti-erosion partitions are made from anti-erosion cloths and backfill soil is placed n soil-filled weighting materials attached to pipe line. At low points where opposite sections cross, water pass or water bypass structure is formed in trench.

EFFECT: enhanced reliability; reduced scope of earth-moving work; enhanced stability of pipe line in horizontal plane.

9 cl, 8 dwg

FIELD: construction engineering; erection of pipe lines in thawing permafrost soils and in flooded areas.

SUBSTANCE: proposed method includes ditching at trench with widened areas located at definite distances and pipe line is laid on bottom of trench. Pipe line is covered with flexible rugs and bottom of trench at widened areas is also covered with rugs; edges of rugs are fastened in widened areas and trench is filled. Used as anchor member are cylindrical textile containers placed in lugs of flexible rugs in parallel with pipe line and filled with soil. Prior to fastening the edge sections of flexible rugs, each of them is tightened at fixation of tension; preliminary tension of edge sections is effected during filling the widened areas and trench soil ensuring contact of flexible rugs with bottom of widened areas and trench. Filling the widened areas and trench is performed in direction towards pipe line, symmetrically relative to it.

EFFECT: enhanced reliability of attachment of pipe line at 0required marks.

13 cl, 4 dwg

FIELD: construction, applicable for trenchless laying and replacement of underground pipe-lines.

SUBSTANCE: a reciprocating striker is positioned in the casing of the pneumatic percussion mechanism. The air-distributing system of the mechanism includes the front and rear working chambers, inlet and exhaust valves and a fixture for closing and opening of the exhaust channels made in the form of a spring-loaded end face stopper coupled to a tractive member. At actuation of the pneumatic percussion mechanism, before the supply of compressed air, the exhaust channels are closed, they are opened after the inner cavities of the pneumatic percussion mechanism are filled with compressed air.

EFFECT: provided automatic cyclic action of the pneumatic percussion mechanism.

3 cl, 3 dwg

The invention relates to construction and is used for trenchless installation and replacement of underground pipelines

The invention relates to the construction and relates to underground pipeline installation for areas with active seismotectonic zones

The invention relates to pipeline transport and used for the construction and operation of pipelines

The invention relates to the construction work

The invention relates to the construction and operation of pipelines in difficult climatic conditions of the North, in ndonesian giving erratic rainfall soils

The invention relates to the construction and can be used for the passage of the trench pipeline in frozen soils

The invention relates to the construction and can be used in the construction of trunk pipelines by alloy

FIELD: construction, applicable for trenchless laying and replacement of underground pipe-lines.

SUBSTANCE: a reciprocating striker is positioned in the casing of the pneumatic percussion mechanism. The air-distributing system of the mechanism includes the front and rear working chambers, inlet and exhaust valves and a fixture for closing and opening of the exhaust channels made in the form of a spring-loaded end face stopper coupled to a tractive member. At actuation of the pneumatic percussion mechanism, before the supply of compressed air, the exhaust channels are closed, they are opened after the inner cavities of the pneumatic percussion mechanism are filled with compressed air.

EFFECT: provided automatic cyclic action of the pneumatic percussion mechanism.

3 cl, 3 dwg

FIELD: construction engineering; erection of pipe lines in thawing permafrost soils and in flooded areas.

SUBSTANCE: proposed method includes ditching at trench with widened areas located at definite distances and pipe line is laid on bottom of trench. Pipe line is covered with flexible rugs and bottom of trench at widened areas is also covered with rugs; edges of rugs are fastened in widened areas and trench is filled. Used as anchor member are cylindrical textile containers placed in lugs of flexible rugs in parallel with pipe line and filled with soil. Prior to fastening the edge sections of flexible rugs, each of them is tightened at fixation of tension; preliminary tension of edge sections is effected during filling the widened areas and trench soil ensuring contact of flexible rugs with bottom of widened areas and trench. Filling the widened areas and trench is performed in direction towards pipe line, symmetrically relative to it.

EFFECT: enhanced reliability of attachment of pipe line at 0required marks.

13 cl, 4 dwg

FIELD: construction engineering; erection of pipe lines in permafrost soils at alternating terrain.

SUBSTANCE: trench in smooth terrain and in sections cut by hydrographic net is dug in active layer at depth sufficient for location of upper generatrix of pipe line above level of daily level. Prior to laying the pipe line, bottom walls and berms of trench are lined with cloth of non-woven synthetic material. backfill soil is placed in ballasting polymer panel-type devices or in ballasting polymer container-type units suspended from pipe line. Anti-erosion partitions made from non-woven synthetic material are formed in sloping sections together with funnel whose neck is located downward of water flow embracing the pipe line at specified clearance between neck and pipe line. Funnel is formed by covering the natural slope of backfill soil by free lower edge of non-woven synthetic material with ballasting polymer panel-type or ballasting polymer container-type devices placed on lower portion of funnel followed by subsequent removal of embankment protecting the pipe line. As far as sections of route cut by hydrographic network are concerned, anti-erosion partitions are formed in trench at transients with opposite slopes of microterrain; anti-erosion partitions are made from anti-erosion cloths and backfill soil is placed n soil-filled weighting materials attached to pipe line. At low points where opposite sections cross, water pass or water bypass structure is formed in trench.

EFFECT: enhanced reliability; reduced scope of earth-moving work; enhanced stability of pipe line in horizontal plane.

9 cl, 8 dwg

FIELD: pipe line transport; major repair of pipe lines.

SUBSTANCE: proposed method includes introducing the front end of pipe into damage pipe and forming hermetic cavity in inter-pipe space; then, pressure air (gas) is charged into hermetic cavity for motion of new pipe inside damaged pipe, after which piston is fitted at end of new pipe and detachable flange is connected to rear end of damaged pipe; motion of new pipe is effected by periodic charging of air into hermetic cavities; each hermetic cavity is bounded by piston and seal.

EFFECT: reduction of tractive force.

5 dwg

FIELD: construction engineering; erection of underground pipe lines in permafrost soils, in bogs and in flooded and marshy areas.

SUBSTANCE: proposed polymer container ballasting unit has two distance rigidity frames located on both sides from pipe line, reservoirs made from polymer commercial cloth and filled soil which are secured to said frames, anti-erosion partitions and upper and lower weighting belts. Distance rigidity frames are curvilinear in form and their height exceeds diameter of pipe line being ballasted. Bend of each frame is made at obtuse angle and lower part of each frame is inclined towards pipe line relative to trench bottom. Polymer commercial cloth laid along pipe line makes distance frame rest against ground of trench bottom both in filling the reservoirs with soil and at action of pushing-out load.

EFFECT: extended functional capabilities.

3 cl, 1 dwg

FIELD: laying or reclaiming pipes.

SUBSTANCE: method includes removing upper layer of spoil, developing side trench with disposal the spoil by damping. The development of side trenches is performed step-by-step. The stripped trench is provided with stripping machine, the side trench are deepened by the working members of the stripping machine below the bottom of the pipeline and pipeline is continuously stripped by trenching machine and stripping machine when it moves forward. The stripping machine has frame with running carriages, clamps, supporting members and mechanism for forward motion.

EFFECT: enhanced efficiency.

3 cl, 4 dwg

FIELD: construction.

SUBSTANCE: pipeline is laid on the concave part of the longitudinal section of the trench bottom on the layer of soft soil and is locked by filling one or two layers of soil with compacting. Screw vertical anchors and load-carrying belts are then mounted. Before filling the trench, the space between the belt and pipeline is provided with a cloth of unwoven synthetic material.

EFFECT: enhanced reliability of pipeline locking.

4 dwg

FIELD: pipeline transport.

SUBSTANCE: flexible pipeline comprises several pulp lines provided with chambers with ball check valves and interconnected through piping diaphragms. The outer surface of the pulp line is provided with a displacement device for movement along the pipeline. The sections of pulp lines receive shell made of layers of syntactic and polyurethane, the ratio of thicknesses of which is (10-4):1. The displacement device affects the piping diaphragm, pumps hydraulic mixture from the bottom section to the next one which is arranged above the check valve, and moves along the outer side of the pulp line to the next piping diaphragm mounted above.

EFFECT: expanded functional capabilities.

3 dwg

FIELD: construction.

SUBSTANCE: pipeline has triply connected supports mounted on the stable sections above and under the slope subject to creep, one connected supports arranged over the subject to creep slope, and deformation compensator. The distance between the upper support and site of the deformation compensator arranged below the slope subject to creep is determined from the formula proposed.

EFFECT: enhanced reliability of the pipeline.

2 dwg

FIELD: construction.

SUBSTANCE: working member comprises rotors provided with teeth arranged symmetrically with respect to the axis of pipeline and provided with drive and mechanism for bringing the rotors together and moving them apart. Each rotor is provided with cleaning device which is arranged behind the rotor and secured to the unmovable segment of the working member for keeping it unmovable or permitting rotation. The cleaning members permanently co-operate with the outer side of the rotor.

EFFECT: enhanced efficiency.

1 dwg