The way to re-dredging development placer

 

The invention relates to the mining industry and can be used in the development of resources placers worked previously dredging method. The way to re-dredging development placer involves removal of the upper layers of the placers in the blade and joint dredging of the remaining man-made layers with layers prilotkovoj zone. According to the vertical limit of the content of useful component in rock mass produce separation placer on conforming and non-conforming layers, removing the last external piles, excavation and preexcavation conforming pebble-evalnih layers are initially in the interim and then permanent mound, located on the conforming layer in prilotkovoj zone for subsequent joint dredging. As a result of increased content of extracted component in DragonWave rock mass. 3 C.p. f-crystals, 4 Il., table 1.

The invention relates to the mining industry and can be used in the development of resources placers worked previously dredging method, floating mining machines, such as dredges, and Stripping technique, for example walking the Noah mass with subsequent storage pebbly layers in the pile adjacent to the industrial Board, and evalnih to the outside [1].

This method does not provide selective extraction of enriched layers of the blade due to gross dredging all layers and is associated with a large dilution of the mineral.

There are also known ways of re-dredging development placers using drag and excavating equipment, where after testing each section of the field on the acoustic fields in the dumps again working Gale-evalnih layers produce the removal of peat from the next site [2, 3].

The disadvantage of these methods is gross dredging of conforming and non-conforming layers pebble-evalnih dumps, which dramatically reduces the content of useful components in the leached rock mass, increases technological losses of gold and makes re-development placers generally unprofitable.

The closest in technical essence and the achieved result is a way of re-dredging the development of technogenic placers, including the removal of the upper layers in the blade and joint dredging remaining anthropogenic layers together with priportovym layer [4]. This method is adopted for the prototype of the claimed invention.

The disadvantage of the prototype is the investment evalnih layers, consisting mainly of waste rock.

The invention is aimed at improving the content of extracted component in DragonWave rock mass.

The technical result is achieved by dividing the pebble-efilego blade on conforming and non-conforming layers, removing the last to external dumps, and conditioned - initially in the interim and then permanent mound with its placement in prilotkovoj area placers for subsequent joint dredging with priportovym layer. While conforming pebble-Eveline layers are mixed and loosened during excavation and preexcavation, pre-drained scattering of deep water. The formation constant of the mound produced during the positive external air temperature, and removal of nonconforming layers in the blade - year-round.

The proposed method is illustrated by drawings, where Fig.1 shows the original cross-section of placer, waste before the dredge the two passages; Fig. 2 - state placer after removal of substandard top shingle layer; Fig.3 - induced scattering after preexcavation conforming pebble-efilego layer and removal of the blade efilego is authorized to dredging.

In the drawings shown substandard pebble layers 1, conforming pebble-Eveline layers 2, substandard Eveline layers 3, conforming layers 4 prilotkovoj area placers, Avelino-silt fraction 5 and blade 6. External dumps 7 substandard pebble layers and external dumps 8 substandard evalnih layers placed on the sides of the placers. Intermediate mound 9 conforming pebble-evalnih layers is conditioned on the pebble-Evelina layer based on substandard athelny layer. Permanent mound 10 pebble-evalnih conforming layers placed on privatecom the conforming layer. The drawings show a 0, I, II, III, IV - sequential moves Stripping equipment such as dragline, in the process of implementing the claimed invention.

The method is as follows. According to the vertical limit of the content of extracted component, such as gold, rock mass pebble-athelny the blade is divided into conforming, for example gold, pebble-Eveline layers 2 and substandard pebble 1 and Eveline layers 3, and the conforming layers 4 in prilotkovoj zone. 0 the first course of the dragline is draining placer deep lowering of the water level due to R is th distance from the goaf (Fig.1). Longitudinal return passages I and II dragline removes substandard pebble layers 1 to their placement in external dumps 7 on the sides of the placers (Fig.2). Course III in the first half of the placers of the dragline produces a recess conforming pebble-efilego layer 2 with its storage in the intermediate mound 9, located on the conforming pebble-Evelina layer 2, based on substandard athelny layer 3 in the second half of the deposits (Fig.3). This course dragline removes the first half of the placers substandard athelny layer 3 with its storage in the external dump 8 (Fig.3). Course IV dragline shall preexcavation intermediate mounds 9 and handling conforming mixed and loosened shingle-evalnih layers 2 and priportovogo conforming layer 4 from the second half of the placers in the first with the creation of a permanent embankment 10, located on the conforming layer 4 in the first half of prilotkovoj zone (Fig.4). This course dragline produces destruction of the second half of placer substandard efilego layer 3 and its placement in the blade 8. At low power, dredging spoil preparation placers can be carried out in three moves with combining operations 0 and I and also II and III moves. Prepared IBEC's direct preexcavation, concentrated in the permanent embankment 10, are processed dredge together with the conforming layer 4 located in prilotkovoj area placers (Fig.4).

To avoid freezing, causing loss of extracted component, the formation of a permanent mound 10 is performed in the period of positive temperatures. Remove substandard pebble layers 1 and evalnih layer 3 is produced year-round.

An example of induced scattering deep after dredging development of two moves again developed a 380-liter dredge MD-431 and excavator-dragline ESH 20.90. Initially, according to the vertical limit of the content of gold in the rock mass pebble-athelny the blade is divided (contrived) conditioned on 2, 4 and substandard layers 1, 3 .

To exclude irrational underwater excavation of rocks, providing high-quality mixing and loosening gold pebble-evalnih layers in preparation for dredging and removal of substandard evalnih layers pre-zero the course of dragline - 0 is draining placer deep dewatering by clearing one of the dredging sinuses to raft with storage Avelino-silt fraction 5 in the blade is ain reveals substandard pebble layers 1 with placing them in external dumps 7. The course IIl dragline shall collect gold pebble-efilego layer 2 with storage in the intermediate mound 9 gold pebble-athelny layer in the second half of the placers. This course dragline produces destruction of the first half of the deposits underlying substandard efilego layer 3 with storage in an external blade 8. Course IV dragline shall preexcavation mounds 9 and the underlying gold mixed and loosened shingle-evalnih layers 2 and priplatkovych conforming layer 4 of the second half of the placers in constant internal mound 10 up on gold Evelina layer 4 in the first half of the placers. This course dragline produces destruction of the second half of placer substandard efilego layer 3 by placing it in the outer blade 8 on Board placers. This is followed by extraction of priportovogo layer 4 by stacking layers in a permanent mound 10.

Prepared for the dredging of gold pebble-Eveline layers 2 (qualitatively mixed together, well loosened when preexcavation concentrated in a single space) together with gold platinovym conforming layer 4 are processed dredge single move.

For iscleared positive temperatures.

The expected annual economic efficiency from the future implementation of the proposed method are presented in the table.

The calculation is made according to [5-8] in the prices of the years 1975-1978. Considering prices 2001 annual economic effect will be eg= Kp320000 = 20320000 = 6400000 RUB, where KP is the conversion factor prices 1975-1978 years in the rates of 2001.

Sources of information 1. A. c. The USSR 1694901, MKI5E 21 41/30. The method of dredging placer developments /A. N. Makhnev and B. L. Thalhimer, 4460433/03 declared 13.07.88, publ. 30.11.91, BI 44.

2. A. C. the USSR 1097797, MKI3E 21 45/00, E 21 41/00. The way to develop the fields in terms of re-dredging. Century Century Chemezov, 3560964/22-03 declared 10.01.83, publ. 15.06.84, BI 22.

3. A. C. the USSR 1263849, MKI4E 21 41/00, E 21 45/00. The way to develop the fields in terms of re-dredging. Century Century Chemezov, 3846512/22-03 declared 17.01.85, publ. 15.10.86, BI 38.

4. Bogdanovich Century A. To the question of the distribution of gold dredging in the dumps. -Kolyma, 1974, 7, S. 45 and 46.

Claims

1. The way to re-dredging the development of technogenic placers, including the removal of the upper layers of the placers in the blade and joint dredging remaining Thea useful component in the rock mass produce separation placer on conforming and non-conforming layers, removing the last to external dumps, excavation and preexcavation conforming pebble-evalnih layers are initially in the interim and then permanent mound, located on the conforming layer in prilotkovoj zone for subsequent joint dredging.

2. The method according to p. 1, characterized in that the recess and preexcavation conforming pebble-evalnih layers produced their mixing and loosening.

3. The method according to p. 2, characterized in that before mixing and loosening the conforming layers dry placer deep dewatering by clearing one of the dredging of the sinuses to the raft.

4. The method according to p. 1, characterized in that the formation constant of the mound produced during the positive external air temperature, and removal of nonconforming layers in the blade - year-round.

 

Same patents:

The invention relates to the mining industry and can be used for open development of permafrost alluvial deposits with internal dumping
The invention relates to the field of mineral processing, in particular to the enrichment of diamond ores, and can be used in the processing of other types of metallic and non-metallic materials

The invention relates to the field of extraction of gold from placer deposits drag way

The invention relates to mining, in particular to integrated devices for the development of placer mineral deposits

The invention relates to a device for developing channel diamond placers

The invention relates to the mining industry, in particular to the development of placer mineral deposits

The invention relates to the extraction of valuable minerals from placer deposits containing heavy clay, limestone and Sandstone

The invention relates to the mining industry and can be used in open-cast mining in the development of ore blocks, plots which vary significantly in quality ore

The invention relates to the mining industry and can be used during mining operations on the open alluvial deposits

The invention relates to mining and can be used for the development of placer deposits, as well as technogenic deposits

FIELD: mining industry.

SUBSTANCE: device has screw, having transporting spiral ribbon held on the shaft. Equipment is provided with U-shaped chute and perforated drum with armature in form of screw ribbon, having curvilinear shape in cross-section, arched in the direction of movement. Drum is mounted in upper portion of U-shaped chute. In its lower portion a screw is mounted.

EFFECT: higher productiveness.

3 dwg

FIELD: mining industry, particularly for open-cut steeply dipping or inclined deposit development.

SUBSTANCE: method involves excavating pit up to design depth reaching by sliced benches; moving the benches as ore deposit is developed; cutting ore and debris; loading thereof on conveyance means to move ore to ground surface, wherein as pit is deepened conveyer systems are used; on reaching the design pit depth deposit is divided into slices and the slices are developed with minimal ore losses in triangular zones with negligible interaction in peripheral face by developed slot raise technology usage; reinforcing slopes with anchors and metal mesh at deep horizons where berm cleaning is difficult; performing slice cutting though the full ore body thickness at design pit bottom and conveying the cut ore to surface by steeply inclined conveyers and combined transportation means. In the case of ore development in slices having lesser thickness below pit bottom steeply dipping and vertical side part are built, concrete wall and metal mesh adapted to hold wedge-like lumps in the presence of potential caving, wherein in this case mining equipment is used and ore cut from underground layer is crushed in crushing mills located on main loading and transportation horizons and delivered to ground surface by conveyer or skip shaft. Mined-out space is filled with rock refuse at terminal stage.

EFFECT: increased efficiency of mineral extraction, reduced cost of deposit development.

8 dwg, 1 ex

FIELD: mining industry, as well as hydraulic, road, agriculture and other building, particularly to perform open cast mining and other woks by rock loosening.

SUBSTANCE: method involves obtaining information concerning main and structural-and-strength rock properties on the base of estimation of data of primary and post-authorization prospecting, as well as production prospecting; detailed rock zoning to separate production blocks and unit blocks characterized by uniform rock at borders thereof; writing computer program; automatically loosing rock of each unit block by most effective method, namely by mechanical, pneumatic, blast drilling or physical one performed with the use of all-purpose mobile rig tools. Above rig includes computer system, device provided with one, two or three replaceable teeth, with plate-like metal pins and with hydraulic cylinders. The rig also has device adapted to create holes in unit block and wedge out thereof, drilling device and charging device, laser charge initiation system, local shelter with damping means, device for rock cutting by applying pressurized air and impacts to rock and auxiliary excavation device.

EFFECT: increased efficiency of rock preparation for further cutting and loading and for solid mineral field development as a whole.

1 dwg

FIELD: mining industry, particularly to develop watered placer deposits and technological mineral deposits under permanent negative temperatures of ambient air.

SUBSTANCE: method involves performing preparation and production works, mineral processing and refuse stacking operations. To implement above method dam is built around mining equipment and deposit to be developed prior to air temperature reduction to negative value; installing sled-mounted hangar having transparent heat insulated roof over the dam and performing all above mentioned works and operations inside the hangar.

EFFECT: increased efficiency of production and processing equipment.

2 cl, 1 ex

FIELD: mining industry, particularly for co-developing salt and platinum deposits.

SUBSTANCE: method involves detecting presence of platinum in non-soluble salt residue salt during salt deposit development; performing geological mapping of salt-bearing cavity and determining sand distribution in stratum above salt layer; drilling wells and bore pits and taking samples to determine platinum content; contouring sand deposits bearing platinum with concentration suitable for industrial development; cleaning surface; blocking out and excavating platinum-bearing sand; directing above sand to gravity separation plant; tying thereof with water in gravity separation plant to separate platinum therefrom.

EFFECT: increased complexity of deposit development.

FIELD: methods of surface mining, particularly for following natural stone treatment by covering or impregnating thereof with liquid or other flowable substances on surface.

SUBSTANCE: method involves gunning salt pit surface with waterproofing agent; covering salt pile surface with clay-and-salt mud layer in dry and hot season after salt pile hardening in at least 1.0-1.5 months after pile filling with salt. The clay-and-salt mud is sylvinite ore-dressing waste obtained from chemical factory. The clay-and-salt mud layer has 10-20 mm thickness and is formed by gunning salt pile surface with above mud material. The clay-and-salt mud is supplied into pneumatic pump receiver, wherein solid/liquid phase ratio is 1:2 - 1:3.

EFFECT: increased efficiency of salt pile waterproofing.

FIELD: agricultural; devices for treatment.

SUBSTANCE: the invention is pertaining to the field of clarification of water at the industrial development of the placer deposits with utilization of the wastes of the timber loggings and extraction of the finely dispersed gold from the water runoffs of the gold mining. In the bed of the diversion channel they form the firebreak out of the filtering material containing the wood sawdust mass subjected to the preliminary sorting at the vibration installation and having the ratio of the fractions from 1 to 5 mm up to the fraction from 5 up to 15 mm as 1:3 and packaged in the netted forms made out of the wire skeleton. After the water clarification the wood sawdust mass is subjected to dehydration by pressing and to drying and incineration for extraction of the fine fractions of gold. The technical result of the invention is the increased efficiency of the water clarification and extraction of gold.

EFFECT: the invention ensures the increased efficiency of the water clarification and extraction of gold.

1 dwg

FIELD: mining industry, possible use during extraction of natural and man-made gravel deposits of both mineral resources of high density (gold, platinum, etc), and valued minerals of low density.

SUBSTANCE: method for softening and disintegration of argillaceous sands of gravel deposits includes driving a water-feeding trench, driving a water-collecting trench in 80-100 meters along direction of fall of deposit bed in parallel to water-feeding trench, depth of water-collecting trench providing for difference of bottom levels in trenches 1,5-3 meters, filling water-feeding trench with water and recharging it to maintain constant water level by means of gate and spillway with raised spillway gate, building walling dam 1-1,5 meters high, limiting the part of deposit being processed in plan, with spillway, after that outputs of filtration flow into water-collecting trench are constructed which are fixed by wetting of upper slope for height of 1-2 meters, then spillway gate is lowered onto spillway spine, and that part of deposit is flooded with water for depth of 0,8-1,3 meters and this level is maintained for initial softening of argillaceous sands of gravel deposits, after that dredger plant is assembled, consisting of suck-in line with suction device, dredger itself and force sludge duct. At the end of force sludge duct, vortex generator is mounted together with hydrodynamic cavitator, due to which during launch of operation of dredger plant argillaceous sands of gravel deposits along the way from face and suction device of dredger to hydrodynamic cavitator are subjected to second stage of softening and disintegration, and in hydrodynamic cavitator - to third-stage final disintegration, and then are dispatched to dressing plant.

EFFECT: increased productiveness and extraction efficiency during extraction of natural and man-made gravel deposits due to efficient softening and disintegration of argillaceous sands of gravel deposits and release of valued components during hydro-transportation of sands to dressing equipment.

2 dwg

FIELD: mining industry.

SUBSTANCE: said geotechnological complex incorporates a trestle with a tumbling bucket, a tumbling module with a chute located inside the closed loop of trench for disintegrated rock accumulation. The chute is directed along the rock inflow. The tumbling bucket installation provides for possibility of linear and angular displacement in the vertical plane; the bucket has slots and L-shaped rippers.

EFFECT: improved efficiency of mining due to intensification of disintegration of rock with complex physical and mechanical properties during dredging and placer mining.

5 dwg

FIELD: mining industry.

SUBSTANCE: said complex is provided with a supported trestle and an ultrasonic and mechanical tumbling module. Rotatable ultrasonic radiation module is connected to movable carriage rim by means of a hub and sliding supports. The movable carriage is provided with a drive for moving it along the trestle cross beam and a drive for turning the ultrasonic radiation module around the movable carriage yoke axis. The rotatable ultrasonic radiation module has drives for moving the ultrasonic sources in the vertical plane, a dual drive for moving the ultrasonic sources in horizontal plane, sensors to determine the rock physical and mechanical state, and communication links with functional module of disintegration process automatic control system.

EFFECT: improved efficiency of mining due to intensification of disintegration of rock with complex physical and mechanical properties during dredging and placer mining.

2 dwg