The method of mining tailings

 

(57) Abstract:

The invention relates to mining, in particular to the development of the tailings processing plants. The method is characterized by the fact that contoured within the reclaimed tailings area with conditioned content of useful component work out mechanically using a tunneling shield used for sinking collectors under roads without breaking the surface layer of the earth, and separated conditioned sand hydrotransport sent to processing plant for the extraction of useful components. To prevent dilution of extracted conditioned Sands collapsing substandard sand in the waste chamber temporarily leave the lining which is removed after excavation of sand from the working chamber. After extraction supports stope is filled samoobuchayuschimsya substandard Sands tailings. The invention provides for reducing the cost of extraction of useful components of the conditioned Sands tailings. 3 Il.

The invention relates to mining, in particular to the development of dry tailings processing plants.

Known sposero and trucks (Y. Yu Rukavishnikov, V. Y. Rukavishnikov "Study of anthropogenic sediments and technology for their development," Coal", 3, 1989, pp. 16-20).

The known method development tailing along.with. 1642016, M. CL.7E 21 41/32, B. I. 14, 15.04.1991 adopted for the prototype on which the testing of lead layers from top to bottom stripes of a width equal to two radii of rotation of the body of the excavator with gross notch rich and poor Sands tailings, loading them into the vehicle and sent to the beneficiation plant.

The disadvantages of this method of development of the reclaimed tailings are:

1 - complete mining of the Sands tailings, which are extracted as conforming or not conforming Sands tailings, resulting in significant dilution of conditioned Sands rich areas;

2 - significant cost of extraction of useful components from razboieni Sands in the concentrator;

3 - the need for new tailings to tailings placement after processing of the poor Sands.

The invention aims to remedy these disadvantages, i.e. to reduce the development costs of the tailings.

The task of the tailings storage facility and transported to the beneficiation plant, pre-framing the area with conditioned content of useful components and its extension are mining the trench from which the lead chamber production of conditioned Sands using the tunneling shield, which hydrotransport sent to the concentrator; simultaneously with the production of installing a lining made from a single bonded together partitions; after the work of the working chamber shield extract, leaving the shield and remove the shield from the waste before the camera, which is filled samoobuchayuschimsya substandard Sands, and between it and the working chamber leave one pinned support the camera.

Analysis of the distribution of heavy rich fractions of tailings beneficiation plant within the tailings indicates that the most severe-rich fractions accumulate in places of discharge of tailings from the tailings dam and the farther you are from it the content of useful component in the tails is reduced. Thus within the tailing observed segregation of the material with the formation of local zones of conditioned ore containing useful components higher than the tailings pond. Local zone conditioned ores are deposited in a separate ically incision, Fig. 2. - longitudinal vertical section, Fig.3 is a plan of the drawings shows:

1 - pipeline to supply water to the tunnel complex;

2 - transporting pipeline;

3 - section lining;

4 - jacking station;

5 - working body of the tunneling shield;

6 - Sands with substandard content of useful components;

7 - Sands with conditioned content of useful components;

8 - mining trench;

9 - chamber filled with collapsed substandard Sands;

10 - proven camera with lining;

11 - working with the camera.

The method is as follows. Framing the area of the tailings with the conditional content of useful components 7 and its extension are trench 8 to install the tunneling shield, for example AVN German company Herreknecht GmbH applied for sinking collectors with a diameter of from 450 to 1500 mm and length up to 1.5 km without breaking the surface layer of the earth. The destruction of the Sands are mechanically with a rotating head, reinforced spicami from solid metals, the working body 5 tunnel shield AVN. Tunnel shield crush in the formation of conditioned Sands 7 by a powerful Jack 4, ustanavli the third round cross-section 3.

Simultaneously with nadavlivanie of shields 3 hydraulic jacks 4 produce mechanical destruction Sands working body 5; produced sand get inside the shields, where it is mixed with water coming through the pipeline 1, and the resulting slurry transport pipe 2 enters the concentrator. The shield is pushed onto the length of the shields, then the capacity of the new partition, and the production cycle is repeated. At the end of the testing chamber 10 start testing the next camera 11, and the shields of the previous waste chamber 10 does not retrieve and serve as a support, which excludes dilution Sands with conditional content of useful components. Removing the lining of the previous camera 10 takes place only after full testing of the next chamber 11, after which the mined-out area chamber 10 is filled with collapsed substandard Sands 9 tailings, that is, between the working chamber 11 and the chamber filled with the non-conforming Sands 9, leave one attached to the camera 10.

As a result of application of the proposed method is selective development of sand tailings with conditioned content of useful components that will allow ecosabotage tailings, including mechanical testing drained Sands tailings pond and transported to the beneficiation plant, wherein the pre-framing the area with conditioned content of useful components and its extension are mining the trench from which the lead chamber production of conditioned Sands using the tunneling shield, which hydrotransport sent to the concentrator, simultaneously with the production of installing a lining made from single bonded sections, after the work of the working chamber shield extract, leaving the shield and remove the shield from the waste before the camera, which is filled samoobuchayuschimsya substandard Sands, and between it and the working chamber leave one pinned support the camera.

 

Same patents:

The invention relates to mining and can be used for developing low-power and strong technological fields, in particular for the recovery of valuable components of rare and precious metals from old, reclaimed tailings

The invention relates to the protection of the natural environment and is intended for use in construction of oil and gas wells on land

The invention relates to the mining industry and can be used for backfill worked-out areas and created internal dumps

The invention relates to a method of agricultural use lignicola and coal mine fields resulting from the Stripping

The invention relates to the development of quarrying and can be used for reclamation of upland quarries

The invention relates to the mining industry and can be used in reclamation of disturbed lands

The invention relates to the mining industry and can be used when nutricula enrichment rocks

The invention relates to mining, mainly to open mountain works, and can be used in the reclamation of the quarry hollows

The invention relates to agriculture and can be used for open development of mineral deposits (gravel, sand, clay, etc.,) and reclamation of the formed pits

The invention relates to the mining industry and can be used in the formation of technogenic deposits

FIELD: earth recovery during drilling work performing.

SUBSTANCE: method involves waterproofing sump walls and bottom; filling thereof with used drilling mud; pumping-out liquid phase and filling thereof with peat and mineral ground. Liquid phase is previously accumulated in the sump and cleaned. Mineral ground, peat and used drilling mud are mixed one with another and supplied to bank slope or to road slope. Then grass is planted on slopes. Cleaned liquid phase is used for grass watering.

EFFECT: increased quality of earth sump reclamation.

1 dwg

FIELD: mining, particularly reclamation of surface-mined areas in agriculture and building industry.

SUBSTANCE: method involves selectively excavating, moving and accumulating ground layer and overburden in separate strip dumps; excavating open-pit field; filling and smoothing thereof and ground layer laying. After open-pit field excavation the excavated space is filled with building waste up to high ground water layer. The building waste has composition close to that of natural minerals with different fraction dimensions. The building waste is laid in several layers each having thickness of 40-60 cm. Each layer is compacted with soil compactors or compacting mechanism. Then draining layer is laid. The draining layer has particle dimensions of 150-200 mm and thickness of not less than 0.6 m. The draining layer is compacted by vibratory plates. Draining layer is covered with fertile ground so that fertile ground layer having thickness of not less than 0.3 m is created. Then straw layer in which chemical fertilizers and perennial grass seeds are added is formed over fertile ground layer. The straw layer is smoothed and sprinkled with dispersions containing water-soluble polymeric substances and synthetic water-soluble phosphates, wherein synthetic water-soluble phosphates are taken in amount of 1-4% by ready dispersion weight.

EFFECT: reduced labor inputs and reclamation work costs, improved land protection against wind erosion and scouring.

4 cl, 1 dwg

FIELD: mining, particularly reclamation of surface-mined areas in agriculture and building industry.

SUBSTANCE: method involves selectively mining, moving and accumulating ground layer and overburden in separate strip dumps; excavating open-pit field; smoothing thereof and ground layer laying. After open-pit field excavation the excavated space is filled with building waste up to high ground water layer. The building waste has composition close to that of natural minerals with different fraction dimensions. The building waste is laid in several layers each having thickness of 40-60 cm. Each layer is compacted with soil compactors or compacting mechanism. Then draining layer is laid. The draining layer is layer of gravel-sand ground with particle dimensions of not more than 200 mm and has thickness of not less than 0.6 m. The draining layer is compacted by vibratory plates. Then two parallel spiral channels are excavated along each pit perimeter from slope side. Coil of each channel starts at pit slope top and terminates at bottom thereof at upper ground water level. Both channels are filled with building waste having particle dimensions of not more than 150 mm. After that holes for trees planting are dug out, wherein the holes are arranged between channel coils. Drainage layer is located on hole bottoms so that the drainage layer is connected with building waste of the channels and holes are filled with fertile ground. Then perennial grass, bushes and trees are planted in the reclamated land.

EFFECT: reduced labor inputs and reclamation work costs, improved land protection against wind erosion and scouring.

2 cl, 1 dwg

FIELD: environment protection, particularly to protect nature against dust blown off with wind from man-made massif surfaces.

SUBSTANCE: method involves contouring dust-forming surface and creating protective structures on dust-forming man-made massif surface in two mutually perpendicular directions, namely transversely to and along prevailing wind action directions; determining wind speed Vlim, m/s which provides maximum permissible dust concentration and maximal prevailing wind speed Vmax, m/s at massif sanitary zone boundary; partitioning man-made massif surface into square areas; installing protective barriers along protective barrier perimeters, wherein the protective barriers are formed of cellular material. Each square area has side length Lar determined from mathematical expression.

EFFECT: reduced dust carryover.

2 dwg, 1 ex

FIELD: mining, construction engineering, possible use during technical reclamation of quarry pits.

SUBSTANCE: method includes extracting the quarry field, forming paired stopping walls in extracted space of quarry field, filling the space between paired stopping walls by construction wastes, while preserving full height of draining and ventilation channels, and building a ceiling. After extraction of quarry field, present hanging sides of quarry walls are collapsed to impart required verticality to them, flexible longitudinal links are attached to quarry walls with following guniting of quarry walls with solidifying solution across whole perimeter of extracted quarry space. Then, quarry bottom is evened out with following densification by means of rolling with appropriate machines and devices, after that wells are drilled in soil by means of washout and soil is mixed with solidifying solution, then reinforcing cage is mounted therein with simultaneous feeding of concrete mixture for making iron-concrete pile in soil-cement cover, while diameters of soil-cement covers overlap one another, creating a foundation having increased filtration and hardness characteristics, paired stopping walls are built along perimeter of quarry, letting flexible longitudinal links through them with their following attachment inside paired stopping walls, and columns are set up to make a ceiling.

EFFECT: expanded area of possible use of extracted and reclaimed quarries, for example, for further industrial construction.

3 cl, 1 dwg

FIELD: mining industry, possible use for reclamation of damaged lands in agriculture, power-construction industrial branches.

SUBSTANCE: method includes, after extraction of quarry field is finished, closure of each quarry by reinforced structures made in form of sleeves of geo-synthetic material and filled with milled construction wastes, while ends of sleeves are sewn shut. Reinforced structures are placed one after another, closely to each other. On top of reinforced structures, draining layer is filled, then a layer of stripping rocks and finally a layer of potentially fertile soil with following seeding thereof with perennial grasses, brushes and trees.

EFFECT: decreased laboriousness and costs of restorative operations.

3 cl, 1 dwg

FIELD: mining industry.

SUBSTANCE: method includes separation of fertile layer during opening of mineral resources and stocking of rock during extraction of same, planning of open mines by backfill with rock and application of fertile layer with restoration of vegetation in accordance to land usage direction. During backfill of rocks into open mines, inclined trench is made from earth surface to open part of exposed formation outlet being left in sides of mine, which provides access and following underground extraction of left deposit resources, and is meant to be a part of payable area.

EFFECT: combination of coal extractive processes with reclamation of lands and preservation of access to concealed resources for their later extraction.

4 cl, 5 dwg

FIELD: methods of underground or surface mining, particularly reclamation of surface-mined areas after production of building stone and other surface-sited minerals.

SUBSTANCE: method involves developing open-pit field; caving hanging walls of the pit; forming floor; installing one-sided form and filling the created space with claydite-concrete; arranging heat-insulation and water-proofing screen along pit wall so that the screen extends for the full wall length, wherein the heat-insulation and water-proofing screen includes heat-insulation material combined with waterproofing sheets of surface waterproofing agent; erecting paired support walls provided with natural ventilation system along pit perimeter so that the support walls are spaced predetermined distance from pit wall; covering space between paired support walls and pit wall with surface waterproofing agent and filling the treated space with ice.

EFFECT: extended field of exhausted pit usage, for instance for further freezing facility construction.

3 cl, 1 dwg

FIELD: mining and processing industry, particularly to reclaim soil in agriculture and building and power engineering industries.

SUBSTANCE: method involves performing selective mining, conveying and stacking ground layer and overburden in separate strip dumps; developing pit field; filling exhausted space with building waste in several layers along with rolling of each building waste layer; leveling thereof with overburden and laying ground layer. Pit is filled with building waste up to mid-height pit level, but not under ground water level. After that building waste is rolled and covered with overburden for total pit filling. Then overburden layer is leveled. To prevent ground settlement wells are formed along filled pit surface, wherein the wells are formed up to design depth and are filled with building waste with each building waste portion compaction. Overburden layer, building waste layer, reinforced structure level formed of geo-synthetic sleeves filled with building waste milled to obtain particle dimensions of not more than 150 mm are serially laid on filled pit.

EFFECT: decreased labor inputs and costs.

1 dwg

FIELD: construction and mining, particularly reclamation of pit depressions after building stone and other surface mineral production.

SUBSTANCE: method involves working out pit; filling the worked-out space; leveling thereof and laying ground layer thereon. After pit working-out ditch and water-draining trenches are formed along pit perimeter to impart regular geometrical shape to pit along with pit side flattening to obtain pit sides inclination of not more than 30° along with following pit side compaction by rolling thereof with compaction machines and mechanisms; pouring sand on designed pit slopes; laying impervious screen made of high-density polyethylene on sand layer; pouring ground layer having thickness of not less than 0.5 m on the impervious screen; covering pit bottom with clay layer; compacting clay layer and inclining thereof towards collecting well composed of reinforced concrete rings; arranging radial bed drainage of crushed stone and sand on pit bottom so that the drainage is directed towards collecting well; forming water-removal ditch along pit perimeter; filling the pit with compacted building waste briquettes; arranging clay screen having thickness of not less than 0.3 m over building waste briquettes; arranging plant layer on clay screen.

EFFECT: decreased labor inputs and reclamation work costs.