Bridge and utility maintenance sidewalk bridge

 

(57) Abstract:

The invention relates to the field of bridge engineering, in particular to the drainage system in large and medium-sized bridges. Technical result provided by the invention, is the maximum approximation durability of bridge for design and durability due to the quality of drainage improvements in terms of mechanical cleaning, maintenance and repair. The bridge contains the supports of the superstructure with the main beams, slab, deck, sidewalks, pavement, fencing devices and drainage system. The catchment area of the bridge given the slopes of different signs, where a decrease in the provided gap with vodopronitsaemym discharge tray, with the gap set protective visors from the cover to the tray, and the catchment area includes the surface of parapet railings gauge cloth made from the facades of the bridge, and along the gap - a security fence - barrier. The gap with the tray can be made between the slab and one of the sidewalks, which is installed on the consoles, zamonolichennyj in the roadway slab and attached to consoles tray and canopy hanging over the tray. The gap with the tray can bitno maintenance trator contains the flooring, which is made of removable grating sections, mounted on racks barrier enclosing the devices that are installed on the plate on both sides of the gap for water runoff from the roadway provided for in the interval counter for patrol vehicles. 2 s and 5 C.p. f-crystals, 9 Il.

The invention relates to the field of bridge engineering, in particular to the drainage system in large and medium-sized bridges.

The closest in technical essence is the bridge containing the supports of the superstructure, consisting of the main beams with the roadway slab and the deck, with sidewalks, the floor of the bridge, protecting the device and the drainage system, which includes the catchment area covering the bridge, made with gradients of different characters towards each other, where along the line change the sign of the slope provides a gap with vodopronitsaemym discharge tray (ed. St. USSR N 706480, E 01 D 1/00, publ. 30.12.79).

The disadvantages. The gap is the gap width of 4-6 cm, closed from insolation of U-shaped elements and a layer of ballast water in the drip tray Obvodny side surfaces of the slab of the carriageway that at low temperatures close to zero, causing the ice and let the freezing-thawing is not working because the ice that causes the flooding of the concrete for a drip and thawing, leaching. Over time, the tray silting up, but its design and location complicate cleaning and repair of the tray and the side surfaces of the slab of the carriageway.

The present invention solves the issues with drainage of the carriageway of the road bridge and operation of the drainage system, resulting in almost completely eliminates the influence of precipitation and chemically active additives in them to reduce the durability of the bridge. If this resolves the problems of ecology, i.e. the protection of the environment from pollution chemically harmful compounds from the roadway and protection from the noise of passing vehicles. The task, in light of the above, is the maximum approximation durability of bridge for design and durability due to the quality of drainage and of all factors of exploitation: mechanical cleaning, easy access for maintenance and repair.

The problem is solved by a bridge containing the supports of the superstructure, consisting of the main beams with the roadway slab and the deck, with sidewalks, the floor of the bridge, enclosing A different characters towards each other, where along the line change the sign of the slope provides a gap with vodopronitsaemym discharge tray, which according to the invention along the side surfaces of the slab of the carriageway in the gap installed protective visors from cover to vodopriemnogo discharge tray, the catchment area includes the surface of parapet railings made from the side facades of the bridge, and between the driving blade and the space above the tray installed on the roadway slab barrier enclosing the device.

If the bridge clearance from 4.5 m to G-13,5 m, the slope of the same sign it is proposed that the catchment area within the roadway and one of the sidewalks, and the slope of opposite sign catchment area of another sidewalk, sidewalks, made of shaped blocks with consoles, which zamonolichennyj in the slab of the carriageway, thus paving blocks with counter slope to the roadway zamonolichennyj with a gap thereto, to consoles suspended tray between the roadway slab and the pavement, and the visor is hanging over the tray.

If the bridge clearance over G-13,5 m, then it is advisable to change the sign of the slope of catchment areas covering the bridge to perform in the interval for the oncoming patrol transportnyje bridge can be made of sections, corresponding to the length of superstructures and starting from the slab of the carriageway, with bearings installed capacity, and where the open ends of adjacent sections of the tray and containers installed pumps for pumping liquids.

In areas with frequent thaws and ice phenomena in the winter it is advisable vodopriemnye discharge tray to be insulated, for example, heating devices.

It is advisable over vodopronitsaemym discharge tray to install transportable filter containers with a lattice in vodopronitsaem the hole.

Another object of the invention is a service-operational sidewalk. The closest in technical essence is service-maintenance pavement containing the supporting elements and the flooring on the control elements for operating equipment and moving staff (see C. O. Osipov and other Bridges and tunnels on the Railways, Moscow, "Transport", 1988, page 101, paragraph 3), pp. 102-104, 107, 112).

The disadvantages. Known service performance sidewalk is an additional load on the superstructure and at the same time is not included in the work of the bridge, in addition, it is not suitable for operation's funds (W.D. compositions). Equipment operating arrangement on the sidewalk not the place for this, provided the site-seeker, arranged at a distance of 25-50 m from each other.

The objective of the proposed service-maintenance pavement, is the maximum approximation durability of the bridge to project longevity by increasing counteract the destruction of the slab of the carriageway from the impact of vehicle hitting the barrier guardrail drainage tray and due to the high operating capacities of the drainage system.

We offer service and maintenance of the sidewalk in bridge construction is aimed at solving the problem. This pavement contains the supporting elements and the flooring on the control elements for operating the equipment and movement of staff. This flooring is made of removable grating sections, and the base elements are the hours of barrier fencing device clearance for water runoff from the roadway of the bridge under interval for the oncoming patrol vehicles in the roadway slab.

A causal relationship between the set of essential features and Pern fence does not constrain) for water runoff from the roadway compared with known drainage system in conjunction with additional area to catchment area (wall parapet railings), with the efficiency of mechanical impact on cleaning the roadway, the best use of insolation and wind influence cause resolution the invention of the task. For this task focused and service-operational sidewalk. This is due to better operating conditions of the drainage system (provided, in particular, the sidewalk), using existing equipment, approaching that due to the location of the service and maintenance of the sidewalk to the place of service (drainage systems). And increased counter-destruction of the sealing racks barrier fencing in the deck slab due to the Association between the two lines of barrier fencing devices, their increased ability to damp the impact.

The invention is illustrated in the drawings.

In Fig. 1 depicts a fragment of the drainage system in the cross section of the bridge size from 4.5 m to G-13,5 m

In Fig. 2 cross-section 1-1 of the bridge of Fig. 5, depicting the drainage system bridge with a clearance of more than 13.5 m with a dividing strip for oncoming traffic.

In Fig. 3 - node And pipe drainage tray.

In Fig. 4 is a fragment of the roadway with the Parham are located in different levels.

In Fig. 6 - pair sidewalk from the roadway slab.

In Fig. 7 - construction of sidewalk from the lower side (relative to the direction of runoff from the roadway).

In Fig. 8 - design of service-operational sidewalk in section 1.1 of the bridge of Fig. 5 and the tray on the bridge with a clearance of more than 13.5 m

In Fig. 9 shows a node B of the pair of cross-beams flooring to the reception of the barrier fence.

The bridge contains a bearing (not shown), the superstructure, consisting of the main beams 1 and plate 2 of the roadway, the deck having sidewalks 3, the floor 4 of the bridge, protecting devices 5, 6 and the drainage system.

The drainage system includes a drainage area covering 4 bridge clearance 7 for flow of fluid from the watershed and vodopriemnye the discharge tray 8. The floor 4 of the bridge given the biases of different characters towards each other, where the decrease coating, i.e., along the lines of changing the sign of the slope made the gap 7. (The floor of the bridge - upper structural layer of clothing hit the canvas, or sidewalk. Cm. Reference "Road terminology", 1985, page 69).

According to the invention is provided by the increase in the catchment area due to the surface of the wall 5 with both the article is, and return to the surface 4 of the bridge (or in the tray), thereby protecting the sidewalks and the sides 9 (facades) of the bridge from dirt and water contamination of a chemically active liquid. Another function of the wall is the opposition to the Congress of the machines, so structurally they are as parapet enclosing the device. Parapet railings made from the side facades of the bridge, are at the corresponding height property of reducing the force of the wind effects and noise reduction by screens of perforated technical rubber.

The lateral surface of the plate 2 of the carriageway side of the gap 7 protects against water flooding visors 10, made from the cover 4 to vodopriemnogo discharge tray 8. That is, a protective shield on one side hermetically sealed in the floor 4, and the other side attached to the tray 8 (Fig. 2, 8) or hovers over the tray (see Fig. 1).

The space available for the construction of the tray is separated from driving the blade through the barrier fence, which provides the maximum possible drain hole in the tray. Barrier fencing consists of posts 6, attached to the fixtures provided in the slab of the carriageway, and the second material. Strip 12 of flexible material of sufficient magnitude to effect noise cancellation is attached to the parapet railings between the beam 11 and the wall 5, while the perforated strip.

If the bridge clearance from 4.5 m to G-13,5 m, the slope of the same sign bridge floor given throughout the roadway and one of the sidewalks, and the slope of opposite sign to the second sidewalk. The slope of the floor on the road (and pavement) can be given due to the variable thickness of the alignment layers (not shown) driving the blade, different heights of pottermania or wedge-shaped spacers (not shown) under the control parts on the main beams.

Paving blocks, forming a sidewalk, including a counter-draft to the floor on the roadway, are mounted on plate 2 of the roadway and then embedded in it. Item pavement 3 - paving block (see Fig. 7) made of reinforced concrete trough-shaped with ribs 13 that extend into the console 14, and with the wall 5 (parapet). The parapet 5 (horse side) equipped with overhead elastically deformable beam 11 (Fig. 4) attached to the wall 5 (parapet) through the gasket 12 made of elastic material that is designed not only for demirov horse side (relative to the flow direction of the fluid) and grassroots hand made with a small difference in the design of the console 14. Console 14 paving blocks with horse side interconnected (see Fig. 4) unlike consoles 14 paving blocks in Fig. 7, mounted from the lower side. Paving blocks consoles 14 (or 14') zamonolichennyj in the plate 2 of the roadway. For this purpose it is provided by the grooves between the U-shaped blocks (see Fig. 6), of which collected the plate 2 of the roadway. Paving block 3 has a hole 15.

If the bridge clearance over G-13,5 m with an interval of safety between vehicles when opposite the junction, the change of the sign of the slopes covering the bridge is made in the interval to oncoming patrol vehicles, where the resulting decrease, and a gap 7 in the plate 2 of the carriageway vodopronitsaemym discharge tray 8. Protective visors 10 is attached to the plate 2 and through the leaves 16 of variable width (to make the tray slope) fixed V-shaped tray, for example, of metal or, preferably, from chemically resistant plastic (see Fig. 8).

The tray may be insulated. Insulated tray 8 includes, for example, reinforced concrete trough-shaped blocks 17 filled with artificial hardening material 18 with low thermal conductivity (for example, polystyrene is 20 at the lower hole, recessed in the sides 20 of material 18, and heating devices 21 with a reflective screen 22 - electric or oil. On top of the pipe 19 and flanges 20 stacked layer filtration (granular) heat insulating material 23, preferably by means of the reverse filter. Insulating material 18 and 23 saves energy required for heating devices.

Insulated tray is recommended in climates with mild winters, accompanied by frequent thaws, ice phenomena. For icing, usually used salt (chlorides). To drain the salty liquid it is recommended to use the trays with insulation to prevent ice formation in the tray (i.e., to preserve its function in difficult climatic conditions). On the other hand, the tray makes it possible to extract chemically active liquid in a septic tank or sewage system.

In the gap 7 above tray locating transportable filter container 24, each of which contains a perforated body and a removable grating 25 in vodopronitsaem the housing bore. Between the containers 24 in the pipe 19 can be mounted tube 26 for supplying pressure to the implications of his work.

The tray 8 may be of insulating material, and the insulation is provided by only heating devices.

In the bridges of large span length between structures and tray gradually increase the distance, breaking architectural appearance. To prevent this, the tray is interrupted above the supports of the bridge, using with capacity of 27 (Fig. 5) mounted on the support. All vodopriemnye discharge tray 8 bridge made of sections corresponding to the length of superstructures and starting from the slab of the carriageway. The tank 27 is installed on the supports, where the open ends of adjacent sections of the tray. Each tank 27 is supplied by a pump 28. The hose 29 from the pump goes to the next segment of the tray 8, starting from the tank 27 at a higher level than is the end of the previous section of the tray.

On the walls of each tank installed sensors (not shown) of the level of filling them with liquid and connected to the pump to encourage them to work in automatic mode. In the bottom of each tank mounted valves 30 for draining off the liquid, and the top of the tank is equipped with manholes 31 for discharging sludge collectors machines.

Adjacent sections of the tray can be performed both with a slope to the tank 27, then the liquid is a bridge. The slope of the tray, it is recommended to take in the range of 15-20%.

Maintaining the durability (and functions) of the drainage system is made with the service and maintenance of the sidewalk. This includes sidewalk flooring 32 in the form of removable sections lattice strut 33. The cross member 33 connects the rack 6 of barrier fencing, installed on both sides of the gap 7. The gap 7 is provided in the plate 2 in the interval for the oncoming patrol vehicles (security clearance). Rack 6 are support items utility operating sidewalk. The cross member 33 provide in conjunction with the racks 6 damping hitting the fence. In addition, the racks 6 are oval holes, and filled bushings 34 of elastic material. The bolts connecting the rack with cross bars 33, passed through a sleeve 34 (see Fig. 9). On the sidewalk there are all necessary for the operation of the drainage system: guides 35 for truck 36, the carriage 36, the giant 37, mounted on the trolley Bay hoses for connection of the monitor with pressure pipe 38, laid on the supporting elements (rack 6), sidewalk, etc., for example, the air line 39 from the compressor to clear the roadway and tray from mud, snow, debris, N. slab of the carriageway for the main beams of steel and concrete superstructure consists of two parts (solid execution or of the blocks team) with clearance for water flow and placement of the tray there, where should be the interval for passing oncoming traffic;

- on the same supports are mounted spans the distance between the plates of the roadway, is equal to the gap 7, which provides the flow and placement of design vodopriemnogo discharge tray etc.

The work of the bridge. Precipitation in the form of rain falling on the floor of the bridge, flowing over its surface in a direction across the bridge and on the tray is discharged into the sewer network or in the sump.

Precipitation as snow accumulates on the surface of the bridge and removed from bridge special equipment, using technical salt, preventing the formation of ice. In autumn and spring, when the thaw in difficult climatic conditions in winter salt is dissolved in the liquid from the melting snow, forming aggressive towards concrete and metal chemical compound with the chemical elements contained in the exhaust gases of vehicles. Rapid runoff of these aggressive chemically active solutions with the roadway of the bridge, as well as preventing any penetration of these solutions on the unprotected surface of the axle (the front surface of the bridge, the railings, the surface side of the gap) provide the e, than surface 5 (parapet) guardrail, and it returned to the surface, further draining into the tray. Distance to pan across a small bridge, one-half the width of the carriageway bridge with right-hand traffic, the hole for the drain is huge, along the entire length of the bridge with both sides of the tray, almost tasneema racks barrier fencing. The slope of the surface coating of the bridge on the roadway to the gap 7 is unchanged, that already during the manufacture of the coating determines the technology of its manufacture (using screeds) and, therefore, quality is the absence of depressions, causing the formation of puddles. No puddles, Stoke by the shortest distance, maximum hole to drain cause rapid runoff of liquid, and the liquid film dries under the influence of insolation and wind quickly.

The front of the bridge and sidewalks protected parapet railings from moisture spray chemically active fluids. The side surface of the bridge from the side of the gap 7 is protected by the visor 10. When cleaning the surface of the roadway washing machines excluded the possibility of moisture the side surfaces of the bridge construction due vychislitel the Dyje inclusion (garbage) are moved to the design of the tray. Larger items remain on the grid container, smaller fall into the cavity of the container, and the liquid is filtered through a perforation in the tray and it is given, for example, in the sump.

At subzero temperatures in the shade of the flow of fluid along the insulated tray is caused by the heating devices 21 and/or forced flushing of the pipeline 38 jet of water through the tube 26. Filter containers 24 are in the area of insolation and thermal radiation heating devices, which prevents, to some extent, the formation of ice in said container. Containers as contamination are removed from the tray, cleaned up and hauled away. Peeled and washed the containers back into place.

In the bridges of greater length collected in tanks 27 fluid is pumped into adjacent overlying the area of the tray, which reaches the next tank and so on Pumps in this case operate in automatic mode from the predetermined filling level of the tank, measured by sensors (not shown). Or, if adjacent parcels have a counter-slope, collect the liquid descends through the valve 30 in the tank under the bridge (or pumped into the tank truck on the bridge). In usloviahlinim machines through the hole 31.

Service-maintenance pavement, combining barrier fencing tray on both sides, increases the counter load from hitting the car. This saves from destruction slab of the carriageway in places termination racks 6 fences, which also contributes to the ability of the United barriers to damp the impact.

On the other hand, service-operational sidewalk is the place from which the service is available (without interrupting the movement of vehicles) drainage systems. To do this, it have the appropriate equipment and arrangement. For example, using the giant 37 washed off the dirt from the parapet railings, bordering the roadway 2, washed the tray 7, and compressed air is cleaned floor 4 from ice in the application of technical salt. Flooring 32 service maintenance sidewalk folding that provides access to the design of the tray 7 (after removing the filter container 24), repair it, etc. Attached to the fence glare screens 40 protects oncoming traffic.

For inspection tray spans the bottom is provided with a removable inspection trolley 41.

1. The bridge containing supports, the span of the s bridge, enclosing the device and the drainage system, which includes the catchment area covering the bridge, performed with a gradient of different characters towards each other, where along the line change the sign of the slope provides a gap with vodopronitsaemym discharge tray, wherein in the gap along the side surfaces of the slab of the carriageway installed protective visors from cover to vodopriemnogo discharge tray, the catchment area includes the surface of parapet railings made from the side facades of the bridge, and between the driving blade and the space above the tray installed on the roadway slab barrier enclosing the device.

2. Bridge under item 1, characterized in that the change of sign of the slope of catchment areas made for the roadway slab, sidewalks, made of shaped blocks with consoles, which zamonolichennyj in the slab of the carriageway, thus paving blocks with counter slope to the roadway zamonolichennyj with a gap thereto, to consoles suspended tray between the roadway slab and the pavement, and the visor is hanging over the tray.

3. Bridge under item 1, characterized in that the change of sign of the slope of catchment areas is made in the interval for the counter-R. 1 or 3, characterized in that vodopriemnye discharge tray bridge made of sections corresponding to the length of superstructures and starting from the slab of the carriageway, with bearings installed capacity, and where the open ends of adjacent sections of the tray and containers installed pumps for pumping liquids.

5. The bridge according to any one of paragraphs.1 to 4, characterized in that vodopriemnye discharge tray is insulated, for example, heating devices.

6. The bridge according to any one of paragraphs.1 to 5, characterized in that the above vodopronitsaemym discharge tray installed transportable filter containers with a lattice in vodopronitsaem the hole.

7. Service and maintenance the pavement of the bridge containing the supporting elements and the flooring on the support elements, characterized in that the flooring is made of removable grating sections, and the support elements are barrier enclosing device clearance for water runoff from the roadway of the bridge under interval for the oncoming patrol vehicles in the roadway slab.

 

Same patents:

The invention relates to the construction of bridges, protect the bridge from the effects of side winds (blast), which leads to its razrusheniyu

The invention relates to waterproofing concrete structures engineering structures, particularly bridges, and is intended for use in the construction and maintenance of engineering structures,

Known waterproofing construction of the bridge, which as a waterproofing layer applied weenie in a layer of bitumen fabric, made of compositions on the basis of bitumen and polymer, e.g. a copolymer of butadiene with styrene [1]

Motor link // 2120880
The invention relates to crossing-bridge means, and more specifically to a pontoon parks, and can be used to build floating bridges and ferries

Motor link // 2120879
The invention relates to crossing-bridge means, and more specifically to the tugs

The invention relates to the construction of bridges, protect the bridge from the effects of side winds (blast), which leads to its razrusheniyu

The invention relates to the construction of bridges, protect the bridge from the effects of side winds (blast), which leads to its razrusheniyu

The invention relates to the construction and maintenance of engineering structures, in particular for bridges

The invention relates to the field of bridge engineering, in particular to the design of the metal superstructure of the bridge with welded by

The invention relates to the field of bridge engineering and can be used in metallic railway bridges

The invention relates to the field of bridge engineering and can be used in metallic railway bridges

The invention relates to a bridge and can be used mainly in the spans of railway bridges with slab ballastless bridge deck
The invention relates to a bridge and can be used when mounting the superstructure of the bridge

FIELD: pavement building and repair, particularly expansion joint construction.

SUBSTANCE: method involves filling gap between beams above sealing padding with cold mastic comprising at least two liquid dence oil products, namely products of propane oil residue deasphalting, bitumen, tar, mazut, gas-oil, lube fraction and naphtheno-aromatic hydrocarbons taken in amount of 48.0 - 80.0 % by weight, colloidal solution of acrylic acid ester copolymer with butadiene, styrene, acrylonitrile and/or vinylpyridine copolymer with butadiene and styrene and/or vinyl- and vinylidene chloride copolymer with butadiene and/or polyisoprene and/or butyl rubber and/or poly isobutylene and/or styrene and/or butadiene nitrile and/or polyvinylchloride and/or polyacrylamide and/or ethylenpropylene chlorosulphuretted polyethylene and/or carboxylated polymer and/or urethane polymer taken in amount of 10.0 - 26.0 % by weight, remainder - mineral component; hardening cold mastic; filling upper space between beams with hot mastic. Expansion joint includes sealing padding and cold mastic formed of material including at least two liquid dense oil products, namely products of propane oil residue deasphalting, bitumen, tar, mazut, gas-oil, lube fraction and naphtheno-aromatic hydrocarbons taken in amount of 48.0 - 80.0 % by weight, colloidal solution of acrylic acid ester copolymer with butadiene, styrene, acrylonitrile and/or vinylpyridine copolymer with butadiene and styrene and/or vinyl- and vinylidene chloride copolymer with butadiene and/or polyisoprene and/or butyl rubber and/or poly isobutylene and/or styrene and/or butadiene nitrile and/or polyvinylchloride and/or polyacrylamide and/or ethylenpropylene chlorosulphuretted polyethylene and/or carboxylated polymer and/or urethane polymer taken in amount of 10.0 - 26.0 % by weight remainder - mineral component.

EFFECT: increased service life of bridge passing.

3 cl, 4 dwg

FIELD: bridge building, particularly preloaded continuous composite bridge structured of steel and reinforced concrete to connect cast-in-place reinforced concrete panel with metal assembly.

SUBSTANCE: span structure includes reinforced concrete panel connected to steel beam by rests embedded in panel body and welded to steel sheet secured to beam. Steel sheet is connected to steel beam belt by high-strength bolts inserted in belt orifices. Orifices have circular shapes in over-pier zone, remainder orifice parts are oval and located so that major oval axis extends along longitudinal span structure axis. Lengths of oval orifices are variable and depend on degree of elastic deformation due to applying squeezing force to reinforced concrete. The greatest length is in preloaded reinforcement anchoring area and length is reduced towards over-pier zone. Ratio between maximal length a of oval orifice to length b of orifice located in over-pier zone and having minimal length a/b = 1.0 - 4.0. High-strength bolts inserted in oval orifices are closed with protective caps to protect bolts against concrete action. Cap contour mates to oval orifice outline. Method of span structure production involves concreting reinforced concrete panel and applying tensioning force to high-strength reinforcement on steel sheet having rests welded thereto and connected to steel beam, wherein steel sheet is connected to steel beam by high-strength bolts inserted in oval orifices and bolts are slackened before reinforcement tensioning. After that reinforced concrete panel resiliently reduces in length on beam belt under the influence of squeezing force and bolts slide along longitudinal orifice. Then protective caps are taken off and blots are tightened with desired force.

EFFECT: prevention of concrete stretching in over-pier area; increased strength and crack-resistance of reinforced concrete panel; increased service life of span structure.

2 cl, 4 dwg

Bridge pier // 2246574

FIELD: bridge building, particularly to protect bridge piers built on rivers with seasonal ice-movement and having changeable water stream level.

SUBSTANCE: pier has support body, pile cluster with high foundation mat and ice-protective shells having shape mating to that of foundation mat panel. Ice-protection shells are located within area defined by extreme water levels and moving ice levels. Low edge of foundation mat panel is located above the highest moving ice level. Each pile is enclosed by separate ice-protective shell. Space between pile and shell is filled with concrete. Shells are connected by cross-bars along foundation mat perimeter and along the shortest diagonal line. Ice-protective shells located in obtuse angles of diamond-shaped foundation mat are brought together so that distance between tangent lines drawn to outer edges of ice-protective shells located in obtuse and acute angles of diamond-shaped foundation mat is not equal to 0.

EFFECT: reduced material consumption, increased operational reliability and service life of bridge pier.

3 dwg

Bridge pier // 2246574

FIELD: bridge building, particularly to protect bridge piers built on rivers with seasonal ice-movement and having changeable water stream level.

SUBSTANCE: pier has support body, pile cluster with high foundation mat and ice-protective shells having shape mating to that of foundation mat panel. Ice-protection shells are located within area defined by extreme water levels and moving ice levels. Low edge of foundation mat panel is located above the highest moving ice level. Each pile is enclosed by separate ice-protective shell. Space between pile and shell is filled with concrete. Shells are connected by cross-bars along foundation mat perimeter and along the shortest diagonal line. Ice-protective shells located in obtuse angles of diamond-shaped foundation mat are brought together so that distance between tangent lines drawn to outer edges of ice-protective shells located in obtuse and acute angles of diamond-shaped foundation mat is not equal to 0.

EFFECT: reduced material consumption, increased operational reliability and service life of bridge pier.

3 dwg

FIELD: bridge building, particularly for reconstruction and repairing piers of road bridges crossing rivers, boggy flood-plain lands and ravines.

SUBSTANCE: ice-breaking structure comprises upper pier part rigidly connected to cross-bar supporting span structure. Upper pier part is installed in ice-breaking part body made of concrete filler enclosed by shell. Ice-breaking part is supported by foundation mat and creates the single monolithic structure with the mat. Ice-breaking part is provided with shell composed of rectangular part and two end triangular parts connected to rectangular part by bolt connections. Shell is made as integral structure along ice-breaking part height. Shell is formed of metal sheets mating to ice-breaking part outline and air-tightly connected one to another by welding. Outer surfaces of metal sheets are covered with anticorrosive coating. Shell is provided with frames and keelsons made of angle members rigidly connected one to another by inner shoulders of angle members to form rectangular grid welded to shell. Outer shoulders of frame and keelson angle members are embedded in concrete filler. Ice-breaking part top is provided with weir screen made of polymer cement mix.

EFFECT: increased service life, improved crack-resistance and strength, reduced labor inputs and material consumption for pier repair and reconstruction.

4 dwg

FIELD: bridge building, particularly for building motorway bridges and pedestrian overpasses, mainly of wood and metal.

SUBSTANCE: span structure has wooden deck having thickness changeable along span length. The greatest thickness is in span center part and the lesser one is at span edges. Deck forms extensions inclined to transversal deck axis and transversal pre-tensioned reinforcement located inside deck, supporting subdiagonals located under deck and arranged coaxial to longitudinal deck edges. Rigid inclined transversal tie system formed at each deck end part consists of upper and lower belts, struts and post. Upper belt of each tie system rests upon corresponding inclined deck extension, lower belt thereof is pivotally connected to subdiagonals by ends thereof. Post extends in tie system plane along line laying in vertical longitudinal axial deck plane and rigidly secured to tie system belts by ends thereof. Struts are connected by their ends to lower belt and to lower post end and rigidly secured to corresponding end parts of upper belt by another ends thereof. Deck thickness in span is 1.6 - 1.9 deck thickness at deck ends.

EFFECT: increased load-bearing capacity of span structure, its flexural rigidity and torsional rigidity in transversal direction.

2 cl, 2 dwg

FIELD: bridge building, particularly structural or constructional details of bridges.

SUBSTANCE: method involves forming channels in pier and in span structure to be mounted, wherein channel axes face each other; registering channel axes; arranging high-strength reinforcement in channels of span structure and pier so that anchor connections may be installed at least on one reinforcement end and/or demounted from it; connecting another reinforcement end to reinforcement tightening means; tensioning temporary reinforcement and compensating force caused due to span structure cantilevered position on pier; performing span structure securing to pier and connecting longitudinal reinforcement thereof; removing stresses from temporary prestressed bundles; demounting anchor connections and removing temporary stressed reinforcement bundles from channels.

EFFECT: increased building rate, increased connection reliability, reduced labor inputs, possibility to use reinforcement bundles in main bridge structure parts.

11 cl, 2 dwg

FIELD: bridge building, particularly structural or constructional details of bridges.

SUBSTANCE: method involves forming channels in pier and in span structure to be mounted, wherein channel axes face each other; registering channel axes; arranging high-strength reinforcement in channels of span structure and pier so that anchor connections may be installed at least on one reinforcement end and/or demounted from it; connecting another reinforcement end to reinforcement tightening means; tensioning temporary reinforcement and compensating force caused due to span structure cantilevered position on pier; performing span structure securing to pier and connecting longitudinal reinforcement thereof; removing stresses from temporary prestressed bundles; demounting anchor connections and removing temporary stressed reinforcement bundles from channels.

EFFECT: increased building rate, increased connection reliability, reduced labor inputs, possibility to use reinforcement bundles in main bridge structure parts.

11 cl, 2 dwg

Low drawbridge // 2249647

FIELD: bridge-building, particularly for drawbridges building.

SUBSTANCE: drawbridge includes drawn navigation span and non-drawn innavigation span, opening and closing mechanisms, permanent piers and bridge railing. Spans include span structures, wherein span structure in navigation span is of double-wing type. Bridge is low and comprises ice-passing structure. Drawn span is provided with grating with upper part located in water level or under water level. Formed in grating are socket-like depressions. Wings of double-wing structure are composed of beam set beams in which have equal heights, preferably of metal beams, wherein wing ends pivotally rest upon permanent piers. Posts of additional movable piers are pivotally connected to another wing ends. Movable piers are adjustably installed in grating depressions so that piers may be fixed in depressions and wings may operate in launched position as beams on two supports. Wings are connected one to another by flexible ties to prevent wind-caused bridge swinging. Ties may be formed, for instance, of ropes with ends arranged in anchoring depressions. In drawn position rope ands are inserted in longitudinal grooves located under bridge roadway.

EFFECT: extended range of low bridges usage, widened navigation underpass, for instance possibility to increase thereof by 6 - 10 m due to console enlargement along with provision of constant beam height.

2 cl, 4 dwg, 1 ex