The method of development of ore bodies chamber systems with weak pillars

 

(57) Abstract:

The invention relates to the mining industry and can be used in the development of underground ore bodies storey-chamber systems. The essence of the method lies in the fact that during the development of the ore bodies of the chamber systems with weak pillars cutting a slit in the next (adjacent) the camera is doing to create flexibility mezhdunarodnogo pillar (IBC), the malleability of the IBC provided by the conditions on the hanging sideways in IBC triangular prisms alternate short-delay blasting to the goaf previous block hole fans with a decrease in each subsequent fan of its width, and the last hole in the corner thump of hands prisms come from the border IBC by connecting the camera to the distance of the radius of destruction of the explosion of the charge of this well. The mining pressure is close to the limit for ore array of cutting a slit in the adjacent block are from IBC at a distance equal to the thickness of the layer, the thump of hands in one massive explosion together with the breaking of a triangular prism in the IBC. 1 C.p. f-crystals, 5 Il.

The invention relates to the mining industry and can be used in the development of underground Rudnik t is Levi whole, where artificial pliability of the pillars give after extraction chamber stocks, contouring pillars, through education in the array pillar or in the zone of its contact with the host rocks systems parallel alternating charging holes and countervailing wells, loading and blasting holes with an interval of deceleration [1]

The disadvantages of this method include the high complexity and the complexity of performing the compensation of the wells and the charging holes of various drilling equipment, especially if the width of the pillars is more than 3 m, because it is difficult to sustain their direction and there is nothing to drill boreholes of depth, for example, up to 10 m in diameter compensation wells up to 150 mm, which provides existing drilling equipment, compliance will not exceed 10 to 20 mm, and requires 200 to 300 mm or more, the voltage is reduced by only 5 to 10% To drill special boreholes with a diameter of 500 60 mm is practically impossible due to their complexity, especially when unloading long tape pillars.

Closest to the proposed invention to the technical essence and the achieved result is a way to create a supporting pillar, where, after penetration of the cutting gap and the conditions on the sections hour is under entirely formed by drilling, the charging and blasting on compensatory production of a layer of rocks width equal to the width of the base of the pillar and a height equal to the height of compensatory production, and the blasting explosive charge in the specified layer and peripheral sections of the chamber reserves, subject to the pillar, are performed simultaneously [2]

The disadvantages of this method are: the necessity of penetration at the base of the pillar compensatory production, which increases the complexity of works to ensure compliance pillar; when using a combination of pliable patrocinia pillars, where compliance is carried out under the hanging sideways and pliable mezhdunarodnogo pillar (IBC), where the pliability of the base of the pillar exercise in the supine side, there is a need for artificial segment patrocinado pillar from IBC to facilitate their relative displacement, which will lead to the violation of openings passing through the plane sections of the IBC in the ceilings, and SnagIt mine safety; after repayment of the IBC repulsed ore will revert to the workings of issue together with the smitten rock from the area of compliance, i.e., they will be mixed, which will lead to increased contamination and ore losses from the redemption of pillars in relation to the traditional production under the arr is the cookie compliance IBC, reducing clogging and ore losses.

This objective is achieved in that during the development of the ore bodies of the chamber systems with pliable whole, including the division of the field into blocks, carrying out production and cutting slits, the extraction chambers, drilling and blasting hole fans, collapse after the release of ore from the camera and release repulsed stocks pillars under the collapsed rocks, yielding IBC carried out prior to the excavation chamber stocks, but after the sinking of the cutting slits on the border with IBC, by the conditions under hanging sideways in IBC triangular prisms alternate short-delay blasting to the goaf camera previous block hole fans with a decrease in each subsequent fan of its width and the last hole in the corner thump of hands prisms come from the border of the IBC on the distance of the radius of destruction of the explosion of the charge of this well, then start testing chamber stocks and obresult patrocinia pillar IBC previous block.

In Fig. 1, 2 shows a specific example of implementation of the proposed method on prior to the issuance of compliance IBC of Fig. 3 after making compliance IBC of Fig. 4, 5 the same, at the location of the cutting gap is not on the drilling Horta 1, pin 2 and generation 3, razvarivat fans wells 4 for blasting triangular prism beneath the hanging sideways in IBC X-Y, fans wells 5 for repayment squeezable PetroChina 6 in block Y, and fans of well 7 for blasting chamber X, which is followed by cutting the slit 8. After testing the camera Y produce short-delay blasting fans wells 4 and the last blow hole 9, an explosion which generates broken the top of the IBC X-Y, partly wytaliba array in the direction of the chambers X and Y. After registration of IBCS X-Y block Y extinguish the pillars and start breaking the ore in the chamber X.

At the time of registration of IBCS X-Y, he happens convergence (mixing) hanging and lying laterally, resulting in tear his broken top. This convergence and crushing the top of the pillar will continue while blasting chamber X. the result is that the expected high voltage IBC X-Y will decrease to a value corresponding bearing capacity of crushed material in the top. In General, the load on the pillar will be negligible, allowing 2-3 times to reduce its width. At the same time access the collapsed rocks from the block Y in the camera X with MCC X-Y will be closed. To apply such pillars can be combined with pliable patrocinada zadania, where Samoobrona hanging side is not expected, i.e., not have reached the limit of its area employment.

To apply the proposed IBC can be in combination with a pliable supporting pillars that maintain overlapping species.

The proposed method of development allows you to safely and effectively execute the malleability of the IBC under high rock pressure, performing work in two ways:

1) to form a cutting gap on the border with IBC, when her education does not lead to the destruction not yet unloaded IBC;

2) to form a cutting gap at the greatest possible distance from the border IBC, increasing the width of the ore mass between the waste chamber and the cutting slit.

This will reduce the amount of stress in it compared to the first option that gives you the ability to work under higher ground pressure than in the first embodiment. Practically, this method is applicable even when the stress values in the ore array adjacent to the formulation 4, which is close to the upper limit, because the formation of a narrow cutting gap does not increase the stress concentration on a specific section of the ore of masela capacity of 10 to 50 m from 1980 apply pliable patrocinia pillars in combination with a rigid IBCS. Currently, when developing a new horizon as a result of extremely high stresses in the rock mass have been in a situation where hard IBC width of 25 to 40 mm should be destroyed. This is confirmed by the fact that in the ultimate state is already adjacent to the ore camera array. Hanging side is in a stable state. Therefore, the proposed mine upon completion of the break-down of inventories in the first on the horizon generation 4 length of 120 m project pliable IBC width of 10 m ore body thickness of 15 m and the height of the floor 60 m Cutting the slit 8 of the next block must be referred from the border IBC 7.5 M. This layer of ore will be repulsed by cutting a slit through short-delay blasting three fans wells simultaneously with the breaking of three-cornered prism in IBC.

In the next block when the thickness of the ore body 40 50 m was left pliable IBC width 15 m Block had a length of 50 m and also succeeds.

Application of the proposed method of development allows 2 to 3 times to reduce the amount of ore in the IBC, while maintaining its stability and preventing it rock bursts. Repulsed from IBC ore is produced usually with losses and blockage up to 50% and Consequently, as a result of lower volume of ore in the AMI with pliant pillars, including the sinking of mines, drilling and blasting of the array of fans wells, formation of pliability mezhdunarodnogo pillar by blasting borehole charges, characterized in that the pass of the cutting slit for blasting connecting the camera to the formation of pliability mezhdunarodnogo pillar, yielding pillar formed by blasting it under the hanging sideways triangular prisms alternate short-delay blasting to the goaf previous block hole fans with a decrease in each subsequent fan of its width, and the last hole in the corner thump of hands prism Buryats from the border mezhdunarodnogo pillar to the side of the camera at a distance of radius fracture of the explosion of the charge of this well, then work out the chamber reserves and obresult patrocinia pillar previous block and mezhdublokovite pillar.

2. The method according to p. 1, characterized in that the cutting slot in the adjacent block are from mezhdunarodnogo pillar at a distance equal to the thickness of the layer, the thump of hands in one massive explosion together with the breaking of a triangular prism in the pillar.

 

Same patents:

The invention relates to mining and can find application in stoping of coal seams using the energy of rock pressure

The invention relates to underground mining of mineral deposits

The invention relates to the field of mining industry and can be used for coal mining, diamonds and other minerals

The invention relates to the mining industry and can be used for developing powerful steep seams tab cast hardening mixtures goaf

The invention relates to the development polegada ore deposits large and medium power

The invention relates to mining and can be used mainly for the development of diamond-bearing pipes, coal deposits, occurring in complicated mining and geological conditions

The invention relates to the mining industry and can be used for the recovery of minerals under rivers, ponds, and also for the development of water-saturated rocks

FIELD: mining industry.

SUBSTANCE: method includes use of screw-drilling machine for driving of several first ventilation shafts in ore body and driving several second shafts, while second and each second shaft crosses, at least, one matching first shaft, forming first support walls, supporting ceiling. First supporting ceilings consist of ore body zones between neighboring second shafts, each first support wall has portion of at least one first shaft, passing horizontally through it. Horizontal channels are formed, each of which is placed transversely to matching second shaft between appropriate portions of first shaft, formed in adjacent support walls, for forming of group of continuous ventilation shafts. Second shafts are filled for forming second supporting walls, supporting well ceiling, and first supporting walls are extracted. First ventilation shafts can be made parallel to each other. Second shafts may be directed perpendicularly relatively to first ventilation shafts. In ore body air-outlet and air-inlet ventilation mines can be formed, placed at distance from each other along horizontal line, while first or each first ventilation shaft passes through portion of ore body between air-inlet and air-outlet ventilation mines. Driving of second or each second shaft can be performed by cutting machine, or by drilling or explosive mining.

EFFECT: higher efficiency.

7 cl, 11 dwg

FIELD: mining industry.

SUBSTANCE: method includes partial filling of extracted space of side and central mains by filling stripes from lava extracting shafts. At center of semi-lava on the side of massive, wherein next extractive column will be cut, filling shaft is additionally driven, wherefrom full filling of space between central fill stripe and fill stripe on the side of massive is performed. Preparation of next extraction column is performed under protection of erected fill stripes.

EFFECT: higher safety, higher efficiency.

1 dwg

FIELD: mining industry.

SUBSTANCE: method includes cutting well field portions by driving bed and field mines. At mine fields to be prepared with weak rock stability driving of several field preparatory mines is performed at portion of field with width determined from formula. Bed preparation mines on same portion are driven alter, with displacement of cleaning operations from these may be driven in portions, at which their stability is provided for technological time period with inter-drift blocks of given rigidity.

EFFECT: higher safety.

2 cl, 1 dwg

FIELD: mining industry.

SUBSTANCE: method includes extraction of mineral resource by underground mine method in liquid environment, under protection of water-resistant rock massif. Full flooding of auxiliary extracting and preparatory mines is performed, which provide for start of wiping operations, with working liquid, neutral relatively to mineral resource and enveloping rocks and being under pressure, matching value of pressure at depth of mine. Process of removal of separated rock beyond underground flooded space is synchronized with replenishment of working liquid volume in this space. Working liquid pressure can be formed by effecting it with force liquid, which is placed either in mine shaft, hydraulically connected to lower flooded auxiliary extracting mine, or in mine shaft and force column, placed on earth surface, above mine shaft, and hydraulically connected thereto. Required height of force liquid column is determined from mathematical expressions. After mineral resource extraction is finished within mine field, flooded extracted space is used for placement of toxic and non-toxic wastes of industries or strategic objects, while process of transfer of wastes or strategic objects into liquid environment is performed synchronously with removal of working liquid beyond flooded space in volume, equal to volume of transferred wastes or strategic objects.

EFFECT: higher safety.

3 cl, 1 dwg, 1 ex

FIELD: mining industry.

SUBSTANCE: method includes separating resources of all levels on blocks, in form of upwardly elongated hexahedrons. Blocks on adjacent levels are positioned in staggered order with displacement of some of them relatively to others for half of blocks width. Resources of each block within limits of hexahedron are divided on two portions: hexagonal chamber inside the block and block itself of same hexagonal shape on all six sides of chamber. Preparation and cutting of chamber resources is realized by driving field level drifts and mines, intermediate sub-level drifts and mines, and also level and sub-level orts and drifts, driven through mineral resource, from which resources of chambers and blocks are drilled and exploded. Extraction and outlet of mineral resource is performed in three rows - first chamber resources, than inter-chamber blocks under protection of ceiling blocks, after that ceiling blocks deposits. Outlet of resources from chambers and blocks is performed trough ends of level orts and mines, an also through ends of intermediate sub-level mines.

EFFECT: better use of mineral resources, lower laboriousness, lower costs, decreased block preparation time.

2 dwg

FIELD: mining industry.

SUBSTANCE: method includes determining width of edge zones of block, subjected to influence from support pressure, then preparatory mines are driven along block at limits of these zones and permanent rigid supports are erected therein. After that portion of block from preparatory mines to block center is extracted.

EFFECT: increased mineral resource yield coefficient, safer extraction of inter-panel support blocks, without breaking their carrying ability and without using backfill materials.

2 dwg

FIELD: mining industry.

SUBSTANCE: method includes dividing a level on hexahedral sections of upwardly elongated shape and is prepared by driving of field backup drift. From drift below each section shafts are driven, from which along mineral resource ascending shafts are drilled. For drilling chambers deposits by wells, sub-level drift is driven along mineral resource, access to which is provided by driving field sub-level drift and shafts. Outlet of extracted rock is performed through ends of shafts. After letting out rock from all sections ceiling beam is brought down and also let out through ends of shafts.

EFFECT: lower laboriousness, lower costs, higher efficiency, higher personnel safety.

2 dwg

FIELD: mining industry.

SUBSTANCE: method includes separation of a level on hexahedral sections of upwardly elongated shape and is prepared by driving of field backup drift. From the drift shafts are driven below each section, from which along mineral resource ascending shafts are drilled, meant for drilling from them by horizontal or slanting wells and extracting sections resources. Outlet of extracted rock mass is performed through ends of shafts. After outlet of rock mass from all sections ceiling beam is brought down and let out also through ends of shafts.

EFFECT: lower laboriousness, lower costs, higher efficiency, higher personnel safety.

2 dwg

FIELD: mining industry, particularly methods of underground mining.

SUBSTANCE: method involves advancing breakage face in under-roof layer; drilling bores in the under-roof layer and injecting weakening reagent to separate zones through the bores; drilling blind drift in front of the breakage face, wherein the blind drift has length of not less than breakage face length; drilling bores for following weakening reagent injection from the blind bore; additionally boring intermediate bores between above bores for following gas exhausting; performing under-roof layer development so that non-developed bank is left directly above breakage face support; performing stepwise weakening reagent injection into corresponding bores and evacuating gas from intermediate bores; leaving bores filled with weakening reagent for 1-2 days and supplying the weakening reagent into intermediate bores.

EFFECT: increased efficiency of mineral preparation.

3 cl, 3 dwg

FIELD: mining, particularly methods of underground mining.

SUBSTANCE: method involves cutting mineral by hydrocutting machines and headers from face massif in rectangular blocks; putting on metal cases on the blocks to facilitate loading-and-unloading operations and transportation; loading the cut blocks on hauling truck along side previously opened from breakage face side, wherein the truck position is fixed by spacing apart hydraulic post permanently connected to the hauling truck; moving loaded hauling trucks inside breakage face by hauling tracks along channel, V-shaped guiders or guiding rails with the use of haulage cargo winches arranged in berms near conveying tunnels or with the use of independent drives, wherein the conveyance is carried out to conveying and venting tunnels abutting the breakage face; loading mineral blocks from hauling trucks onto wheeled transport platforms without block turning for following transportation. Distance between rail tracks is equal to rail track width to transport blocks on paired wheeled platforms in which locomotive moves along medium track. Working area face is strengthened by individual hydraulic posts and metal hydraulic jacks and metal roof bars or by mechanized face support. The face support has fastening sections including above hydraulic jacks and roof bars, as well as wheel guiding means sections and hydraulic movers with control panel arranged on each fastening section pair. The roof is controlled by partial filling the excavated space with mineral blocks. Distance between neighboring mineral units arranged on one paired wheeled platform and on adjacent platforms may be identical and equal to distance between guiders in breakage heading. Mineral blocks are cut in several rows, wherein depth of slot at seam ground and roof is two times as thickness of mineral blocks to be cut.

EFFECT: increased output, improved safety and ecology.

3 cl, 14 dwg