The method of construction of piles

 

(57) Abstract:

The inventive form in the soil well, then carry out the heating of the lower part of the pile shaft, consisting of a fusible material to a temperature equal to /05-075/t LP where t is the melting temperature of the fusible material , set the pile in the hole and carry out its doporueene with the formation of SIRENIA. .

 

Same patents:

FIELD: building machinery, particularly for forming cast-in-place piles, pile foundations, retaining walls, slope protection structures and ground bases for floors.

SUBSTANCE: device comprises percussion unit with working forming unit made as sharpened cylinder and integrated in front part of percussion unit. Sharpened cylinder has outline including alternating convex and concave parts. Operational forming unit comprises two members with conical surfaces on front outer side thereof and spaced one from another along longitudinal device axis. Operational forming unit has seat surfaces located on outer rear part surface of front member and on inner surface of rear member.

EFFECT: increased efficiency of well driving.

3 cl, 3 dwg

FIELD: building, particularly foundation building, namely for erecting pile foundations in seasonally freezing ground.

SUBSTANCE: method involves forming well extending for the full thickness of seasonally freezing ground layer, wherein well diameter increases pile diameter; installing heater in the well; transferring heat; driving casing pipe with detachable tip in ground through heater cavity; concreting well bore along with simultaneous lifting casing pipe and removing heater. Heat is supplied to concrete mixture within the limits of seasonally freezing ground after casing pipe removal. Inductor made as copper wire coil covered with heat-protective layer and located outside metal pipe is used as the heater. Heating is performed within 10-12 hours along with maintaining 75-80°C temperature of concrete mix by regulating inductor power up to obtaining concrete strength equal to 80% of design strength. After inductor removal from the well gap formed between well wall and pile body is filled with non-heaving ground.

EFFECT: reduced power inputs along with maintaining high productivity and increased load-bearing pile capacity.

2 cl, 3 dwg

FIELD: building, particularly to create bored piles in cased wells during building and building structure foundation erection.

SUBSTANCE: method involves heating ground surrounding place of pile erection and heating concrete mix with induction heater. The concrete mix is vibratory treated in pulsed mode at the beginning of heating operation by applying electromagnetic field generated by induction heater to metal reinforcement bars, wherein high-frequency current of induction heater is subjected to low-frequency modulation. At concrete mix setting beginning the pulsed mode is changed into high-voltage one. Device for above method realization comprises induction heater comprising steel pipe put on asbestos-cement pile casing pipe and winding made of copper coiled bus linked with high-frequency power source. The winding is connected to metal pipe. Diametrical longitudinal orifices are made in the steel pipe. The power source comprises circuit providing high-frequency current modulation with low frequency.

EFFECT: possibility of simultaneous heat and vibration application to concrete mix, reduced cost of the device along with reduced number of working tools, simplified control, provision of concrete shrinkage and compaction under heating, which is performed by single device.

2 cl, 4 dwg

FIELD: building, particularly to consolidate weak ground at building or building structure base.

SUBSTANCE: mixing and drilling bit comprises hollow body provided with at least one orifice for technological solution injection, starter and at least two blades with front cutting edges. Each blade is secured to hollow body and may perform limited rotation. Geometrical rotation axis of each blade is offset relative center of gravity defined by blade surface towards front cutting edge.

EFFECT: reduced labor inputs and simplified operation.

3 dwg

FIELD: civil and industrial building, particularly to erect piles adapted for new building erection and reinforcement of foundation of building to be reconstructed or repaired in soft ground.

SUBSTANCE: method involves forming well in ground by forced ground pressing to well walls without ground removal from well, wherein the well is created with the use of drilling string provided with tip to be left in well; supplying hardening material simultaneously with tip deepening in ground; forcing hardening material into well walls; creating excessive pressure in soft ground zones. Drilling string comprises drilling rods with separate auger sectors. Drilling string section near tip is made as auger. Tip includes conical and cylindrical rollers fixedly connected with each other.

EFFECT: increased load-bearing capacity of the pile, possibility to use the pile for foundation reinforcement.

3 dwg

FIELD: construction.

SUBSTANCE: discharge switch for grouting piles consists of a vertical upper electrode and lower electrode containing five current-conducting elements, which are arranged at some distance from each other opposite the holes made in forming box body. To utilise hydrodynamic effect to a maximum extent, reflecting shield is fixed to the body. In order to switch low electrodes sequentially, a cable is connected to sharing selector switch. The type of electrodes is accepted in this device as "symmetrical bumpy surface - apex". It allows for producing discharges sequentially one after another. The number of electrodes corresponds to the number of holes made in forming box. The electrodes are arranged opposite to holes made in forming bob body. The number of electrodes has to be even. The axis of current-conducting element in the lower electrode is perpendicular to the working surface of the upper electrode. To achieve maximum effect of shock waves directing, the above-mentioned reflecting shield is used. The tilt angle between shield working surface and axis of current-conducting elements in the lower electrode is 45-60 degrees as quality of hydro pulse shock wave formation is used such as direction of their action.

EFFECT: reduced energy consumption, improved bearing capacity of pile.

4 cl, 2 dwg

Bearing pile // 2251609

FIELD: building, particularly for constructing foundations of various building structures.

SUBSTANCE: bearing pile comprises head, rod and tip fixed to embedded rod part by embedded member. The tip is formed of thermoplastic concrete and has electric heater located inside the tip. Electric heater heats the tip after driving thereof into ground as far as it will go to obtain softening temperature of 80-150°C. Then the pile is fully driven in ground. Electric heater wires are placed in tube in longitudinal rod direction and brought outside under pile head for connection thereof with electric power source.

EFFECT: increased load-bearing pile capacity due to provision of widened pile tip support area.

2 cl, 5 dwg

FIELD: bulkheads, piles, or other structural elements specially adapted to foundation engineering, particularly concrete or concrete-like piles cast in position with enlarged footing or enlargements at the bottom of the pile.

SUBSTANCE: reinforcement device is used to erect pile foundation with the use of foundation pile having at least one longitudinal cavity. Reinforcing device comprises a number of joined reinforcement members hingedly connected with central annular member located so that reinforcement device may be collapsed during installation and erected during device usage. Reinforcement device is connected to pile by at least one member working in tension. Foundation pile reinforced with the use of said device and method for foundation pile driving and pile bottom reinforcement are also disclosed.

EFFECT: increased uniformity of reinforcement distribution over pile bottom, improved compression and stretching force damping, decreased labor inputs and material consumption.

36 cl, 25 dwg

FIELD: construction, particularly bored piles with enlarged footing or enlargements at the bottom of the pile.

SUBSTANCE: method involves drilling well; filling the well with concrete mix and non-detonating composition including fuel and oxidizer; igniting non-detonating composition by applying low-voltage pulse to electric igniter and combusting non-detonating composition in deflagration regime to create camouflet void with following concrete mix hardening. The fuel is solid hydrocarbon selected from polyethylene, polypropylene and polystyrene. The oxidizer is sodium or potassium chlorate. Non-detonating composition is supplied in well before well filling with concrete mix.

EFFECT: decreased pile production time due to accelerated concrete mix hardening and improved produced pile quality.

6 cl

FIELD: building.

SUBSTANCE: invention refers to building, in particular, to strengthening of the bases under the basements. The way of strengthening of the basement erected on waterlogged priming coats and near to the located constructions includes supply of early strength concrete in the metal tubing established in driven wells, drilled through a basic part of the basement and a ground. Pipes are made with the welded boots, in pipes lower explosive charges and fill with early strength concrete, then the explosive charges are detonated, remaining hollownesses of driven wells and pipes are filled with early strength concrete.

EFFECT: provision of reliable strengthening of the basements erected in waterlogged priming coats and near to located constructions; increase of load-carrying capacity.

2 dwg

FIELD: construction.

SUBSTANCE: invention is related to methods for arrangement of pile foundations for structures, to pile foundations and shell structure for creation of widened foot for pile foundations. Method for creation of pile foundation for structures, according to which the following stages are executed on site to arrange the mentioned foundation - well for installation of foundation pipe is drilled with the help of the first auger drill. The following section is drilled under lower end of installed foundation pipe. Cavity is arranged in the specified section by means of scraper and pressure of water jet. Loose soil is removed from specified cavity by mentioned first drill. Pipe for set of tools and accessories with the second auger drill and flexible shell that envelopes the lower part of the second specified drill is lowered through foundation pipe into lower part of specified section. Excess pressure is built up in specified shell, and moulding material is injected into specified cavity, surplus of which is then removed by the second auger drill. After mentioned material hardens, the specified shell is blown off and removed via specified foundation pipe. Reinforcing device is lowered into foundation pipe. Concrete material is poured into foundation pipe, at that specified cavity is filled, and specified reinforcing device is embedded into concrete, thus creating widened foot for foundation pipe. Versions of method and pile foundation are also stated.

EFFECT: higher stability and resistance to compressing and stretching forces, lower material intensity.

5 cl, 26 dwg

FIELD: construction industry.

SUBSTANCE: invention refers to construction industry and namely to construction of bearing piles in ground rock. Device for making multi-layer sealed pile in ground rock includes, in the combination, elongated hollow tube having longitudinal axis, upper inlet end for material, open lower discharge end for material and diametre of the first external surface and common formed lower head element at open discharge end, which has diametre of the second external surface, which is more than diametre of the first external surface and made with the possibility of transmitting combination from axial and transverse stress components when hollow tube is lowered. Head element consists of common attachment to hollow tube; at that, head element includes lower driving end which in general has configuration of flattened cone between head element of external surface and lower discharge hole made in the lower driving end, and back end having in general the configuration of flattened cone, and cap of the head element covering lower discharge hole. Lower head element with the cap and hollow tube are formed for being introduced into ground rock and for displacing the earth when hollow tube with lower head element and the above cap is lowered into ground rock so that a cavity is formed in ground rock. The cap is at least partially removed from lower discharge hole when hollow tube is then lifted from the formed cavity in order to perform passage of material through lower discharge hole to the cavity section released with hollow tube and lower head element. The latter has the form of cross section and the sizes which are more than the shape of cross section and sizes of hollow tube in order to decrease friction forces on hollow tube when penetrating into ground rock and being removed from it.

EFFECT: improving reliability of the pile and capacity and production effectiveness of piles.

34 cl, 26 dwg

FIELD: oil-and-gas.

SUBSTANCE: invention related to construction, particularly can be used for bored piles with enlarged base arrangement. The method includes hole boring, hole opening with mechanical clampshell enlarger, reinforced cage installation and filling in the hole with concrete mixture. Developing enlargement with ration of enlargement diametre to hole diametre, equal de/dh≥2 with rotation velocity equal n=20-100 revolution per minute, dependant on ground conditions. After covering distance 0.8 h, where h - height of enlargement, stop axial supply of boring media and at that level, during 3-5 revolutions execute enlargement base cleaning, and ground collector and voids between enlarger blades complete filling. Turn on axial supply and execute boring till enlargement total height and enlargement blades closure. Take away enlarger, then concrete enlarged base, install reinforced cage and complete bored piles arrangement with concreting its core.

EFFECT: method of bored pile arrangement efficiency increase and hole enlarger design improvement, hole enlarger reliability increase, easing of ground withdrawal out form ground collector and better quality of constructed bore pile.

4 cl, 3 dwg

Driven pile // 2386748

FIELD: construction.

SUBSTANCE: invention is related to construction, in particular to pile foundations. Driven pile consists of shaft with axial hole, sharpened tip with circular base and conusoidal shell with spike, cavities inside shell filled with hardening solution. There is a threaded hole in tip base, which is closed with threaded plug with stem. Tip shell is rumpled with submergence force after removal of threaded plug and additional submersion of pile. For additional increase of bearing capacity there is an elastic shell on lower part of shaft with facilities for fixation of its upper and lower ends; cavity between elastic shell and shaft surface; protective jacket with facilities of its fixation of shaft, which slides in radial direction and embraces elastic shell. There is a radial hole in shaft, which connects longitudinal hole with specified cavity transformed into support belt after the pile has been submerged at the specified depth, the cavity has been filled with hardening solution via holes in shaft and the solution has hardened.

EFFECT: improved bearing capacity of hollow piles.

4 cl, 7 dwg

FIELD: construction.

SUBSTANCE: method of drilled pile manufacturing includes well arrangement in soil. Supply of material into it. Compaction of soil under lower end of formed pile. In process of soil compaction, in the base of formed drilled pile with parametres equivalent to driven pile, its conventional camouflet cavity is arranged with diametre Dkp equal to diametre of dzs equivalent to driven pile, where: dzs - diametre (m) of equivalent driven pile. DkP - diametre (m) of conventional camouflet cavity produced in soil as it is displaced under lower end of formed drilled pile, by means of supply of controlled material volume to fill conventional camouflet cavity according to the following dependence : where V is controlled volume (m3) of material spent for filling of conventional camouflet cavity produced in soil due to its displacement into pile foundation. As well is filled with material in the form of hardening mix, preferably plastic concrete mix, diametre of equivalent driven pile is identified according to dependence , where dzs - diametre (m) of equivalent driven pile. Dskw - diametre (m) of well; Δh - measured value of subsidence (m) of plastic concrete mix in well as conventional camouflet cavity produced due to displacement of soil under lower end of formed pile is being filled. And in order to produce drilled pile with parametres of driven one of the same diametre, soil is treated in the lower end of pile till material subsides, preferably concrete mix, in well by value, which is compared with the one defined from the following ratio: Δh/Dskw=0.4. Besides in the lower end of well soil is exposed to forces, and their sufficiency is controlled (assessed) by flow of material additionally supplied to well in process of soil treatment, and its volume is identified according to formula , where Dskw - diametre (m) of formed pile. Besides in well reinforced with casing pipe, dynamic actions at soil are carried out until material subsidence value in casing pipe makes at least the following: , where Δhtr is subsidence (m) of material in casing pipe. Dskw - diametre (m) of well. Dfr - inner diametre (m) of casing pipe. Dynamic actions at soil in lower end of formed pile are carried out to achieve conventional failure, which is represented by material subsidence of not more than 2 mm in process of the last action, and when soils are compacted by electric explosions in pile foundation with application of electrode system, dynamic treatment is interrupted provided that electrode system freely installed on bottomhole in process of electric explosion sinks by not more than 1-2 cm, and in process of soil dynamic treatment at least one additional camouflet expansion is created along pile length, preferably, in zones of well opening of soils that are most pliant to compaction, which is detected by reaction of soil to test dynamic actions performed along pile length.

EFFECT: development of drilled piles with bearing capacity by soil, same as for driven piles, with minimum possible usage of resources and maximum possible usage of properties inherent in massif of soil that contains pile.

7 cl

FIELD: construction.

SUBSTANCE: device for compaction of soil in drilled pile well bottomhole includes casing pipe, bushing fixed on it with working element pulled through it. Working element is arranged in the form of hollow pipe, at the lower end of which there is a thrust journal and sealing attachment, and at the upper end there are upper and lower supports and inertial mass, placed on hollow pipe between upper and lower supports with sliding fit.

EFFECT: improved bearing capacity of drilled piles erected in watered and soft soils.

4 dwg

Up!