Floating dock section

FIELD: transport.

SUBSTANCE: invention relates to ship building. Floating dock section contains pontoon where side towers are installed, ballasting facilities, dock floor with primary framing made as structure of longitudinal and transverse frames, main framing beams resting on it on which beams the decking is placed. The pontoon is divided into central and side ballast compartments by vertical waterproof bulkheads. In the vertical longitudinal pontoon symmetry plane, vertical support bulkhead is installed which bulkhead is made permeable. Relative (to dock width) width of central ballast compartment (size of segment with transverse framing system) is calculated by formula given in description. Longitudinal vertical waterproof bulkheads are placed equally spaced from the vertical support bulkhead. The main framing of the central ballast compartment is executed according to transverse scheme, and the main framing of the side ballast compartments - according to longitudinal scheme.

EFFECT: decreased scuffing of decking in places of framing welding during equipment movement, mainly along dock side towers; reduced pontoon weight; reduced ballast asymmetry and dock tilting.

2 dwg

 

The invention relates to shipbuilding and for the design of floating docks.

Well-known section of the floating dock containing side of the tower and pontoons, divided by a longitudinal vertical watertight bulkheads at the Central and side ballast tanks, means for ballasting the dock and berth - deck, containing a frame set in a frame of longitudinal and transverse frames, leaning against him cross the core set, hosts deck flooring (see "floating dock No. 220, project FD 220. Steel, non-self-propelled floating dock lifting capacity of 27000 tons built in July 1969 at the shipyard Oresundsvarvet AB Gotaverken (glandstone, Sweden) on the class Lloyd's Register).

Also known section of the floating dock containing side of the tower and pontoons, divided by a longitudinal vertical watertight bulkheads at the Central and side ballast tanks, means for ballasting the dock and berth - deck, containing a frame set in a frame of longitudinal and transverse frames, leaning against him longitudinal core set, hosts deck flooring (see "floating dock PD-83 m, the project S878. Steel, self-propelled, floating dock lifting capacity of 25000 tons built in August 1965, at the shipyard of Mitsubishi Heavy Industries, Ltd. (Yokohama, Japan) on the class Lloyd's Register).

The disadvantages of the known technical solutions aplaydevices damaging structural elements of the most loaded during finishing operations of the Central compartments, the low resistance of the decking when the longitudinal system of recruitment and high attrition towers from equipment movement in the transverse system, a complex system of ballasting dock, leading to asymmetric filling of the compartments and overload structures compartments. In addition, the large distance of the longitudinal vertical watertight bulkheads from the longitudinal vertical plane of symmetry of the pontoons is not possible to provide reliable support for dock cells in the production of small and medium ships.

The challenge which seeks the proposed technical solution is to increase the strength and reliability section of the floating dock by combining systems set the boat-deck pontoon dock, join the Central compartments into one and reducing the width of the Central compartment.

Technical result achieved when the solution of the problem, reflected in the increasing stability of the flooring of the boat-deck in the center of the pontoon and reduced abrasion of the towers when the movement of the vehicle, reducing congestion compartments and simplifying control ballasting reducing the number of elements of the ballast system and reduce the likelihood of asymmetry ballast and roll dock. Furthermore, the reduction in size of the Central compartment allows you to position the longitudinal bulkhead closer to vertical prodol the second plane of symmetry of the pontoon, that makes it possible to provide a reliable support for dock cells in the formulation of medium and small vessels. The use of longitudinal system set in the side compartments instead of the lateral system reduces overall weight of the pontoon.

The problem is solved in that section of the floating dock containing side of the tower, placed on the pontoon, which is divided into longitudinal vertical watertight bulkheads in ballast tanks, means for ballasting the dock and berth-deck, containing frame set, made in the frame of longitudinal and transverse frames and deck flooring placed on the beams of a core set supported on the frame, characterized in that the vertical longitudinal plane of symmetry of the pontoon is placed vertical retaining bulkhead, made permeable, while the relative width of the Central ballast compartment defined by the formula:

wherethe relative weight of the tower dock;

the relative weight calculation of a ship;

the relative distance to the center of gravity of the tower from the outer wall of the dock;

- the ratio of the critical stresses for the flooring of the boat's deck to the calculated normative yield stress normal is between voltages;

the relative bending moment in the transverse plane of symmetry of the pontoon;

The p - weight of the dock;

In - the width of the dock;

Pb- weight of the tower;

Pc- the estimated weight of the ship;

Inb- distance to center of gravity of the tower from the outer wall of the dock, and the walls of the Central ballast compartment is made in the form of a longitudinal vertical watertight bulkheads, equidistant from the vertical retaining bulkhead, with a core set of Central ballast compartment are designed for cross air flow, and on-Board ballast compartments - longitudinal schema.

Comparative analysis of the essential features of the proposed solution with essential features unique and prototype demonstrates its compliance with the criterion of "novelty".

The characteristics of the characterizing portion of the claims, solves the following functional tasks.

Signs "...in the vertical longitudinal plane of symmetry of the pontoon is placed vertical retaining bulkhead, made permeable..." aims at bringing more loaded during finishing operations of the Central compartments in one, allowing you to more easily control the ballasting and reduce congestion compartment. This reduces the number of elements of the ballast system of the dock and reduces the likelihood of asymmet the AI ballast and roll the dock.

The mathematical formula will calculate the relative (to the width of the dock) the width of the Central compartment (plot size with the cross-system).

Signs "...the walls of the Central ballast compartment is made in the form of a longitudinal vertical watertight bulkheads, equidistant from the vertical retaining bulkhead..." can provide reliable support for dock cells in the production of small and medium ships.

Signs "...a core set of Central ballast compartment are designed for cross-scheme..." provide better perception of the compressive effort slipway-deck that occur when the transverse deflection of the pontoon from the action of the weight of the vessel.

The longitudinal system set in the side compartments can reduce the abrasion of the berth-deck welding in places set in motion machinery mainly along the towers of the dock.

Figure 1 shows a schematic cross-sectional section of the floating dock, figure 2 - system set of ship-deck.

In the drawings shows the pontoon 1, the side of the tower 2, the berth-deck 3, 4 longitudinal and transverse frame 5, the beam core set 6, which are deck deck 7, a longitudinal vertical watertight bulkheads 8, 9 Central 10 and side ballast tanks, the axis of symmetry 11, the vertical retaining bulkhead 12.

Section floating dikasteria pontoon 1, on the hosting side of the tower 2, ballasting means (not shown), the berth-deck 3, containing frame set, made in the frame of 4 longitudinal and transverse 5 frames, supported on his main beams 6, on which is placed the deck flooring 7.

The pontoon 1 is divided longitudinal vertical watertight bulkheads 8 9 Central 10 and side ballast tanks. To combine more loaded during finishing operations of the Central ballast compartments 9 in one in the vertical longitudinal plane of symmetry 11 of the pontoon 1 is placed vertical retaining bulkhead 12, made permeable. Relative to the width of the dock) width of the Central ballast compartment 9 (plot size with the cross-system) calculated by the mathematical formula. Longitudinal vertical watertight bulkheads 8 placed at equal distance from the vertical retaining bulkhead 12 (according to the calculation). The main set of 6 Central ballast compartment 9 is executed on a cross air flow and provides a better perception of the compressive effort in deck deck 7 arising from the transverse deflection of the pontoon 1 from the action of the weight of the vessel and on-Board ballast compartments 10 - longitudinal pattern. The longitudinal system of the main set of 6 onboard ballast tanks 10 allows smart is to sew abrasion deck 7 at the welding set in motion machinery mainly along the side of the towers 2 dock. In addition, the use of longitudinal primary set of 6 reduces the total weight of the pontoon 1.

Section of the floating dock containing side of the tower, placed on the pontoon, which is divided into longitudinal vertical watertight bulkheads in ballast tanks, means for ballasting the dock and berth-deck, containing frame set, made in the frame of longitudinal and transverse frames and deck flooring placed on the beams of the main set, supported on the frame, characterized in that the vertical longitudinal plane of symmetry of the pontoon is placed vertical retaining bulkhead, made permeable, while the relative width of the Central ballast compartment defined by the formula:

wherethe relative weight of the tower dock;
the relative weight calculation of a ship;
the relative distance to the center of gravity of the tower from the outer wall of the dock;
- the ratio of the critical stresses for the flooring of the boat's deck to the calculated normative yield strength at normal voltages;
the relative bending moment in the transverse plane of symmetry of the pontoon;
The p - weight of the dock;
In - the width of the dock;
Pbthe weight of the tower;
Pwith- the estimated weight of the ship;
Inb- distance to center of gravity of the tower from the outer wall of the dock, and the walls of the Central ballast compartment is made in the form of a longitudinal vertical watertight bulkheads, equidistant from the vertical retaining bulkhead, with a core set of Central ballast compartment are designed for cross air flow, and on-Board ballast compartments - longitudinal pattern.



 

Same patents:

Aircraft // 2370408

FIELD: aircraft construction.

SUBSTANCE: invention concerns aircrafts heavier than air, lifting up without the help of special-purpose motors (jet or propeller motors). Aircraft includes case comprised by upper and lower parts, control and steering devices. Upper case part is attached to lower part by bearings and can rotate against it. External surface of upper case part is rugged with radial cogs with heating elements such as gas burners installed inside the cogs. Adjustable louver shutter is mounted along the perimetre of upper case part.

EFFECT: aircraft elevation and propulsion in air medium and aerodynamic property setting.

4 cl, 5 dwg

FIELD: shipbuilding.

SUBSTANCE: invention relates to ship-raising and can be used for carrying out rescue operations at sea, lifting from the bottom of water bodies and subsequent transportation of sunken ships and other objects. The method of lifting a sunken object is characterised by that, flexible elastic hollow covers are attached to the outer surface of a rescue submarine, as well as on the body of the sunken object. The sunken object is held using these covers. The device for lifting a sunken object using a rescue submarine is characterised by that, the above mentioned covers can be joined to each other and attached to the outer surface the sunken object, with possibility of holding it, and on the outer surface of the rescue submarine. These covers are so flexible that, they take the shape of the outer surface of the rescue submarine. Compressed gas used can be gas obtained from reacting chemical reagents with seawater.

EFFECT: invention allows for realising a cheaper and reliable method of lifting sunken objects, including submarines, without breaking them up, which makes it possible to carry out rescue operations independent of the time of the year and conditions on the surface of the sea when using the device, which can be easily mounted on the rescue vessel and suitable for repeated use when realising the method described above.

3 cl, 8 dwg

FIELD: shipbuilding.

SUBSTANCE: invention relates to sea transport, namely, to underwater transport complex allowing transportation of cargoes in extreme conditions of Arctic Ocean. The underwater transport complex comprises the adequately equipped sea-based ports, surface icebreaking sea sips or submarines with load-bearing radial plating and necessary complex of systems, seaports, underwater lines connecting them, underwater stationary navigation system and a team of freight submarines. A signaling cable is rigidly fixed all along the route axis. Note here that each seaport incorporates an internal reservoir and a platform with the elevating device located in the said reservoir to accept and ship freight submarines in underwater position.

EFFECT: higher traffic safety of freight submarines plus increased underwater traffic speed.

4 cl, 22 dwg

FIELD: building, transportation.

SUBSTANCE: invention relates to floating shipbuilding, in particular, to floating moving marine dock. Floating moving marine dock (10) includes a one-piece molded frame limiting ship receiving area (30). The ship receiving area (30) includes rolling mechanisms (72) on the bottom of the ship receiving area and sliding mechanisms (42) on the side faces of the said area. The rolling and sliding mechanisms can be easily removed and changed in the course of maintenance of a ship dock. For elongation of a ship dock, proposed elongating section (130) can be adjusted to it. The elongating section includes a frame (132) and a ledge (134) emanating from the elongating section frame. The ledge has such size and form so that its lower part serves as the addition to the shipping dock entrance (30) of the shipping dock frame. The elongating section also includes a shipping receiving dock (139), which, in case of adjusting of the section, elongates the ship receiving area.

EFFECT: wider range of technical means.

29 cl, 28 dwg

Vessel-dock // 2326786

FIELD: transportation.

SUBSTANCE: vessel-dock contains a dock chamber, a moving gate for closing the dock chamber, a ballast compartments provided by kingston valves and vent valves, adjustable support devices for vessels carried by the dock, a compressed air system connected to ballast compartments via pressure feed valves. The vessel-dock is equipped with extending stops to rigidly center a carried vessel, in particular, a submarine, a flying bridge arranged to move above the dock chamber, a remote control system to control an in-out motion mechanisms, installation and positioning of carried vessels inside the dock chamber and a set of load-lifting mechanisms.

EFFECT: increase of operating performances of the vessel-dock.

7 cl, 3 dwg

FIELD: shipbuilding; equipment for raising the ships onto shore slipway and lowering ships from shore slipway.

SUBSTANCE: proposed dock has pontoon or pontoons to be ballasted and additional pontoon-pier which is also ballasted. Additional pontoon-pier has supports projecting from its bottom which enter inter-pontoon gaps or wells during lowering and raising the dock; these supports are secured at required height by means of retainers located in the said inter-pontoon gaps or in wells.

EFFECT: extended operational capabilities of dock.

3 dwg

FIELD: equipment of swimming pools.

SUBSTANCE: proposed unit is provided with air conditioner for cleaning the air and maintaining its parameters, such as humidity, temperature and pressure. Provision is also made for distributing main for supply of air to swimmers. This main is provided with breathing hoses, 6 to 8 m long and mobile distributor provided with trolley with metal cabinet which is fitted with horizontal pipe at the top connected with air conditioner by means of hose. Unit is also provided with branch pipes of individual sections of metal cabinet. Each section is provided with splitter adapter pipe fitted with gas cock and connected with side branch pipes of flow divider. Flow divider is provided with four outlet pipes which open and close in pairs and in turn. These pipes are connected with breathing hoses. One end of inspiration valve body is inserted into lower end of each breathing hose. Other end of valve body is inserted detachably into air duct branch pipe provided with mouth-piece and expiration valve.

EFFECT: enhanced reliability of air supply to swimmers.

2 cl, 5 dwg

FIELD: shipbuilding; pilotage and placing of ships in dock, mainly submarines in shallow waters.

SUBSTANCE: proposed ship positioning system includes pontoons at adjustable buoyancy and ship raising unit containing load-bearing members provided with devices for securing them on pontoons. Ship raising unit has at least two load-bearing members made in form of curvilinear beam. At least one curvilinear beam may be mounted on supports by means of quick-release gripping devices of bayonet joint type. Supports are provided with foundations which may be rigidly connected with main hull of ship. Each curvilinear beam has box-type section. At least one curvilinear beam is mounted on two supports symmetrically relative to ship' CL. Each support may be made cylindrical and may be provided with rests onto foundation which is welded to main hull of ship. Each beam may be secured on pontoon by means of turnbuckles fitted with locks.

EFFECT: avoidance of damage to submarine hull; facilitated procedure of docking her.

15 cl, 4 dwg

FIELD: shipbuilding; pilotage and placing of ships in dock, mainly submarines in shallow waters.

SUBSTANCE: proposed ship positioning system includes pontoons at adjustable buoyancy and ship raising unit containing load-bearing members provided with devices for securing them on pontoons. Ship raising unit has at least two load-bearing members made in form of curvilinear beam. At least one curvilinear beam may be mounted on supports by means of quick-release gripping devices of bayonet joint type. Supports are provided with foundations which may be rigidly connected with main hull of ship. Each curvilinear beam has box-type section. At least one curvilinear beam is mounted on two supports symmetrically relative to ship' CL. Each support may be made cylindrical and may be provided with rests onto foundation which is welded to main hull of ship. Each beam may be secured on pontoon by means of turnbuckles fitted with locks.

EFFECT: avoidance of damage to submarine hull; facilitated procedure of docking her.

15 cl, 4 dwg

FIELD: shipbuilding; devices for isolation of sunken objects.

SUBSTANCE: dock has bottom part with ballast tanks, central part with tower heeling tank and of top part, pontoon dock-gates, systems and devices for filling tanks in and emptying them. When using the method, the dock is tugged into area of operation, put upside down, submerged and guided onto sunken object. After it the dock is pressed against ground due to getting ballast into tanks.

EFFECT: reliable and quick isolation of ecologically dangerous sunken objects.

2 cl, 7 dwg

The invention relates to the field of shipbuilding, namely the systems of courts, interacting in the open sea, are equipped with comprehensive facilities to ensure the interaction of courts and manage, and can be used, for example, when servicing underwater vehicle surface vessel catamaran base type

FIELD: transport.

SUBSTANCE: invention relates to ship building. Floating dock section contains pontoon where side towers are installed, ballasting facilities, dock floor with primary framing made as structure of longitudinal and transverse frames, main framing beams resting on it on which beams the decking is placed. The pontoon is divided into central and side ballast compartments by vertical waterproof bulkheads. In the vertical longitudinal pontoon symmetry plane, vertical support bulkhead is installed which bulkhead is made permeable. Relative (to dock width) width of central ballast compartment (size of segment with transverse framing system) is calculated by formula given in description. Longitudinal vertical waterproof bulkheads are placed equally spaced from the vertical support bulkhead. The main framing of the central ballast compartment is executed according to transverse scheme, and the main framing of the side ballast compartments - according to longitudinal scheme.

EFFECT: decreased scuffing of decking in places of framing welding during equipment movement, mainly along dock side towers; reduced pontoon weight; reduced ballast asymmetry and dock tilting.

2 dwg

FIELD: transport.

SUBSTANCE: invention relates to ship building, particularly to sea accidents elimination equipment. Proposed complex comprises floating and transport facilities. Floating facility incorporates equipment to carry out decontamination and pulling-and-running operations and can move in shallow waters. Floating facility hull accommodates ballast compartments. Transport facility comprises cargo compartment arranged in its underwater section to accommodate and fix floating facility therein in semisubmerged position. Both facilities can operate in deep waters. Proposed complex moves driven by propulsive machinery.

EFFECT: reduced time for coupling floating and transport facilities.

3 dwg

FIELD: transport.

SUBSTANCE: invention relates to ship navigation. Proposed method of piloting ships in channels and shallow inland waters consists in using auxiliary engineering means. Said auxiliary means represents pontoons. Said pontoons represent bow and stern buoyancy modules. Underkeel clearance is increased by reducing wave resistance in running in shallow waters due to absorption of waves reflected from the hull. Waves are killed by aforesaid buoyancy modules. Pontoons are furnished with elements to secure them to ship hull. Said modules are shaped to ship hull bow and stern. Said fastening elements are made up of retainers furnished with jacks and cables to fasten buoyancy modules aboard the ship.

EFFECT: higher efficiency.

2 cl, 3 dwg

FIELD: electronics.

SUBSTANCE: invention relates to automated systems. System comprises hardware-software complex (HSC) of regional centers connected by means of satellite radio communication with HSC of remote transfer of ENM, which by Wi-Fi radio are connected to automated workstations (AWS) of users and HSC of hydrographic information sources.

EFFECT: technical result is reduction of time for receiving hydrographic information from vessels required to correct electronic navigation maps (ENM) and to bring ENM to vessels in conditions of absence of cellular communication, as well as higher reliability of ENM caused by fast updating them.

5 cl, 1 dwg

FIELD: transportation.

SUBSTANCE: arctic navigation transport vessel is proposed, made in the form of a lighter carrier equipped with a crane, a tow vessel and a staff lifting device, located on its deck, for loading on and unloading from the vessel the lighters, and equipped with a composite self-propelled ferry for performing loading and unloading operations in the shallow water to the unequipped shore by means of the lighters carried by the transport vessel. The ferry is made up of at least three modules articulated with each other, predominantly lighters transported with the vessel, and is equipped with the propulsion and steering system with a power plant, located on one of the mobile units of the ferry, with measuring and navigation equipment and with an apparel.

EFFECT: expanding the operational performances of the transport vessel.

3 dwg

FIELD: transportation.

SUBSTANCE: trimaran type ship with outriggers-energy modules, consisting of the main body, two lateral buoyancy - outriggers and underwater bridges connecting them with the body is proposed. The whole energy plant of the ship is taken out of the hull into outriggers and bridges. This provides the formation of an extended tunnel in the hull, adapted for entering a floating craft into it through a cutout in the hull transom.

EFFECT: basing of relatively large floating crafts on a relatively small vessel without lifting them on the ship and without a bulky lifting device.

4 cl; 3 dwg

FIELD: shipbuilding; devices for isolation of sunken objects.

SUBSTANCE: dock has bottom part with ballast tanks, central part with tower heeling tank and of top part, pontoon dock-gates, systems and devices for filling tanks in and emptying them. When using the method, the dock is tugged into area of operation, put upside down, submerged and guided onto sunken object. After it the dock is pressed against ground due to getting ballast into tanks.

EFFECT: reliable and quick isolation of ecologically dangerous sunken objects.

2 cl, 7 dwg

FIELD: shipbuilding; pilotage and placing of ships in dock, mainly submarines in shallow waters.

SUBSTANCE: proposed ship positioning system includes pontoons at adjustable buoyancy and ship raising unit containing load-bearing members provided with devices for securing them on pontoons. Ship raising unit has at least two load-bearing members made in form of curvilinear beam. At least one curvilinear beam may be mounted on supports by means of quick-release gripping devices of bayonet joint type. Supports are provided with foundations which may be rigidly connected with main hull of ship. Each curvilinear beam has box-type section. At least one curvilinear beam is mounted on two supports symmetrically relative to ship' CL. Each support may be made cylindrical and may be provided with rests onto foundation which is welded to main hull of ship. Each beam may be secured on pontoon by means of turnbuckles fitted with locks.

EFFECT: avoidance of damage to submarine hull; facilitated procedure of docking her.

15 cl, 4 dwg

FIELD: shipbuilding; pilotage and placing of ships in dock, mainly submarines in shallow waters.

SUBSTANCE: proposed ship positioning system includes pontoons at adjustable buoyancy and ship raising unit containing load-bearing members provided with devices for securing them on pontoons. Ship raising unit has at least two load-bearing members made in form of curvilinear beam. At least one curvilinear beam may be mounted on supports by means of quick-release gripping devices of bayonet joint type. Supports are provided with foundations which may be rigidly connected with main hull of ship. Each curvilinear beam has box-type section. At least one curvilinear beam is mounted on two supports symmetrically relative to ship' CL. Each support may be made cylindrical and may be provided with rests onto foundation which is welded to main hull of ship. Each beam may be secured on pontoon by means of turnbuckles fitted with locks.

EFFECT: avoidance of damage to submarine hull; facilitated procedure of docking her.

15 cl, 4 dwg

FIELD: equipment of swimming pools.

SUBSTANCE: proposed unit is provided with air conditioner for cleaning the air and maintaining its parameters, such as humidity, temperature and pressure. Provision is also made for distributing main for supply of air to swimmers. This main is provided with breathing hoses, 6 to 8 m long and mobile distributor provided with trolley with metal cabinet which is fitted with horizontal pipe at the top connected with air conditioner by means of hose. Unit is also provided with branch pipes of individual sections of metal cabinet. Each section is provided with splitter adapter pipe fitted with gas cock and connected with side branch pipes of flow divider. Flow divider is provided with four outlet pipes which open and close in pairs and in turn. These pipes are connected with breathing hoses. One end of inspiration valve body is inserted into lower end of each breathing hose. Other end of valve body is inserted detachably into air duct branch pipe provided with mouth-piece and expiration valve.

EFFECT: enhanced reliability of air supply to swimmers.

2 cl, 5 dwg